HomeMy WebLinkAbout2012-175 CONT Chg Order #1 - NW Biological Consulting CITY OF ASHLAND DEPARTMENT OF PUBLIC WORKS CONTRACT CHANGE ORDER NO. I PROJECT: Ashland Creek Bank Restoration DATE: LOCATION: At Water Street Bridge PROJECT NO.: 2006-29 CONTRACTOR: Northwest Biological Consulting The following described work has been directed to be performed by the Public Works Director. Item No Description Quantity Unit Price Amount Provide large pumps to handle increased flows in Ashland Item#I Creek: $ 25,815.65 Removal of 26" white alder tree which is a safety hazard to the Item#2 Ashland Creek Inn $ 750.00 Total this Change Order $ 26,565.65 Previous Change Order $ Original Confract Total $ 247,452.00 Revised Contract Total $ 274,017.65 PERCENT CHANGE OF ORIGINAL CONTRACT 10.7% Prepared By: 8/3/2012 Pr jec anager Date Recommended By: t(311-Z Engin in S vices Manager Date Approved By: g 13 i (Z Public Works Director Date Accepted By: North West Biological Consulting 324 Terrace Street Ashland, OR 97520 - 813 -20(2 Contractor epresentative Date ENGINEERING Tel 541488-5347 20 As l Main Street F. 541488-6W6 900-7 5-29 Ashland,Oregon 97520 TTY. 800-7354900 w ashland.oros G:\pub-wrks\eng\06-29 Ashland Ck Riparian Ren\AdmmCcastmclion Admin\NW Biological-Payments and Change Orders\Change Order No 1 xlsx ...u+: ''_ NORTHWEST BIOLOGICAL CONSULTING HABITAT RESTORATION-ENVIRONMENTAL PLANNING Col. Engineering Contractors Lic. x599428 August 1, 2012 To: Morgan Wayman, City of Ashland Project Manager for the Ashland Creek Bank Restoration Project. Proj. Number 2006-29 Ph. 541-488-5347 From: Scott English, Principal of Northwest Biological Consulting (NBC), General Contractor for Ashland Creek. Project Number 2006-29 Ph. 541-941-2042, 324 Terrace St. Ashland, Oregon 97520 Re: Request for Contract Change Order to Cover Additional Costs Associated with Providing a 'Larger De-Watering System that is Adequate to Handle Creek Flows Above 3.1 cfs which are anticipated to be in the range of 7cfs. or higher. Also, I am requesting that additional funds be added to this change order to cover the removal of a large white alder that is in the way of the new irrigation pipeline. Rational for Requesting a Change Order: The project scope of work regarding the dewatering of Ashland Creek during construction calls for a dewatering system capable of handling up to 3.1 cfs or 1395 gallons per minute (each cfs equals about 450 gallons per minute). The flows today in Ashland Creek through the project reach are approximately 7 CFS which is about 3150 gallons per minute. Also, due to the high water year and TID input, it is possible to have flows higher than 7 cfs. These flows are unusually high for this time of year and apparently the City does not have the ability to reduce the flows to 3.1cfs. The dewatering system we planned to use for the project is comprised of two diesel pumps capable of pumping approximately 1500 gallons per minute which is a little higher than 3.1 cfs but not large enough to handle substantially higher flows of over 3150 gallons per minute and greater. In order to provide a dewatering pumping system to pump 3150 gallons per minute or greater we will need to upgrade our pumping system to a larger pump system which will cost more money. The 26 inch white alder is in the way of the pipeline route and it was missed during the initial design survey and therefore was not included in my bid. It need so come out pending approval from the tree commission. Cost Estimate: The following is an outline of estimated costs to provide a larger capacity pump system capable of handling the increased flows in Ashland Creek. Tree removal costs are also included. • Godwin Pumps of Hubbard Oregon will provide a combination of electric and critically silenced diesel pumps and fittings to manage flows up to 2500 gallons per minute or greater. Refer to the attached Godwin cost estimate which includes mobilization and setup costs. Cost — — — __ __ — --- ------------$14,418.65 • Welburn Electric of Phoenix Oregon will provide the electric hook-up for the electric pumps which will be 3 phase 240 volt service with metering, etc. Refer to the attached Welburn cost estimate. Cost----------------------------------------------------------$8,197 • NBC will provide labor to install the additional system which also includes diesel fuel for the pumps and the electricity estimate. Cost--- _ _$3,200 • NBC will provide labor to have the tree cut down and the stump removed to allow for the pipe installation. Cost-------------------------------------------------------$750 Total Cost Estimate for Change/Order is----------------$26,565.65 OV 8 - 3- 2viZ r Bid Pro osal 4529 S. Pacific Highway HIS_IS Phone(541)535-3727 P.O. Box 329 �� Fax(541)535-3572 Phoenix, Oregon 97535 Vm Oregon Lie.# 15-189C C.C.B. Lie.#78794 Biological ELECTRIC) INC. California Lie.#777522 PROPOSAL RECIPB"N Northwest Biological Consulting PHONE: 541941-2042 FAX: DATE: 8/2/12 STREET: 324 Terrace St JOB NAME: Ashland Creek Restoration Project CITY.STA E]JP: Ashland OR 97520 JOB OCA ON Water& B Street Ashland Or JOB PRONE: N/A DATE OF PLANS: N/A ARCHITECT. N/A WE HEREBY SUBMIT SPECmCATmNS AND ESTDNATES FOR Per our job site review 8/2/12 Item # 1 $327.00 ➢ Provide and install 2- 20 amp 240 volt single phase weather proof outlets. Provide and install new circuit breakers connect outlets to existing panel. Item #2 $7,870.00 ➢ Provide and install 200 amp 3 phase service. ➢ Extend 125 amp feeder from service to proposed coffer dam location. ➢ Provide and install 125 amp 3 phase panel at coffer dam location for submersible pumps. ➢ Provide and install 24"x36" backboard for new panel and pump control panels. ➢ Install pump panels and connect new pumps, proposed pumps I- 13HP, 2- 8HP. ➢ Remove service and equipment after completion of project(6-Weeks) Not Included: Excavation for poles and backboard. Utility fees. Supplying of pumps or pump control panels. Installing pumps and floats in coffer dam We propose hereby to furnish material and labor—complete in accordance with above specifications,for the sum of Please Make Your Selections $ PAYNCENT TO BE MADE AS FOLLOWS: For all new customers payment to be 50%down due upon acceptance of proposal, balance paid C.O.D For existing customers Payment due 15 days from receipt of invoice Authorized Signature Wayne Poland Note:This proposal may be withdrawn by us ifnot accepted within 15 days. ACCEPTANCE OF PROPOSAL The above prices,specifications and conditions are satisfactory and are hereby accepted.You are authorized to do the work specified. ACCEPTED: Company Date Signature No work will begin without a signed proposal. Please sign and return one copy of this proposal to our office. Please Note:All materials remain the property of Welbum Electric Inc.until paid in full by proposal recipient per this bid proposal, Welbum Electric Inc.may remove any or all provided materials if payment is not received within 30 days of invoice date. Contact Wayne Poland with any questions regarding this proposal. 811112 Gmail-2 photos of NBC 6 inch dri-prime pump Hi; based upon our conversations, here is pricing on the equipment needed at your site. $12,928.65 per 28 days • Includes three submersibles (1) 13HP, (2) 8HP with auto panels and floats • One Critically Silenced Diesel CD225M with floats and auto start • Twin 8"discharge lines 400feet each • Remaining adapters,fittings, and check valves to complete the system. Transportation is $525.00 each way Setup Supervision is$110.00 per hour, billed on a time and materials basis. Exclusions • Fueling of pumps • Unloading, loading and placement of equipment • Traffic Control • Suction and Discharge Locating • Clearing Path to Discharge location • Equipment and Discharge Pipe Protection • Discharge Pipe Stabilization as required • Trenching for pipe • Flushing of pipe • Pump must be serviced every 250 hours. Godwin can provide this at an additional cost • Provide labor and equipment for setup and teardown of system. Godwin can provide this at an additional cost. Contact me with questions orto place the order. Thanks, Glen McCord Branch Manager Dewatering Solutions 2754 Pacific Highway Hubbard, Oregon 97032 0: 503.981.0341 M: 503.572.3912 glen.mccord@xyleminc.com https:/Imall.google.com/mail/9ui=2&ik=aac396ec7b&view=pt&search=inbox&th=138db2fb9l6fe2a0 314 CITY OF , ASHLAND DEPARTMENT OF PUBLIC WORKS CONTRACT CHANGE ORDER NO.1 2 PROJECT: (Ashland Creek Bank Restoration DATE: LOCATION: At Water Suce't,B—dge PROJECT NO.:(. 2006'29.. .-rx.. , CONTRACTOR: Northwest Biological Consulting tj The following described work has been requested to be performed by the the Million Ditch Users Group and has been approved by the Public Works Director. Item No. 11 Description Quantity Unit Price Amount Additional work to install pump, pipe and valves to keep Item#1 continuos flow to Million Ditch $ 6,900 00 Total this Change Order $ 6,900.00 Previous Change Order $ 26,565.65 Original Contract Total $ 247,452.00 Revised Contract Total $ 280,917.65 PERCENT CHANGE OF ORIGINAL CONTRACT 13.5% Prepared By: 8/7/2012 Pr jec646agcr Date Recommended By: Engineeri Services ager Date Approved By: WL , o— 6l7 f1 2 Public Works Director Date Accepted By: (North West Biological IPI�g 324 Terrace Street — Ashland, OR_97520 Jl Co&Ferctor Representative Date ENGINEERING Tel 541488-5 347 20 As E.Main Oregon F. 541 0-735-W As .asl Oregon 97520 TTV: %00435-2900 www.ashlandar us CiApub-wrkskng\06-29 Ashland Ck Riparian RestWdonsTonswction AdminW W 0iological-Payments and Change Orders\Change Order No 2 8-7-2012 xlsx NORTHWEST BIOLOGICAL CONSULTING HABITAT RESTORATION-ENVIRONMENTAL PLANNING Col. Engineering Contractors Lic. 6599428 August 6, 2012 To: Morgan Wayman, City of Ashland'Project Manager for the Ashland Creek Bank Restoration Project. Proj. Number 2006-29 Ph. 541-488-5347 From: Scott English, Principal of Northwest Biological Consulting (NBC) General Contractor for Ashland Creek Bank Restoration Project Number 2006-29 Ph. 541-941-2042, 324 Terrace St. Ashland, Oregon 97520 Re: Request for Contract Change Order to Cover Additional Costs Associated with Providing Approximately 0.196 cfs to the Million Ditch from About August 9 through September 15, 2012. The Water Will be Provided 24/7 with the Exception of Short Periods when the Flow will be shut off Due to Upstream Construction Needs. Rational for Requesting a Change Order: The original project scope of work regarding the dewatering of Ashland Creek during construction called for dewatering the creek and not supplying irrigation water to the Million Ditch. However, due to changing circumstances beyond the control of the Contractor (NBC) it is now necessary to provide a continuous flow of water, 0.196 cfs to the Million Ditch from about August 9 through September 15, 2012. The 0.196cfs flow amount was provided to NBC by the City Engineering Department. , In order to comply with providing water to the Million. Ditch it will be necessary to design and install a series of pipes and valves that will be connected to the ditch system. Additional pumps will be added to the dewatering system to provide the necessary water. Cost Estimate: The following is the estimated cost to provide a pump system, pipes, valves, and labor capable of providing the necessary 0.196 cfs to the Million Ditch. • Northwest Biological Consulting (NBC) will provide a combination of electric and diesel pumps as well as the necessary pipes, fittings and labor and monitoring to connect to the Million Ditch. Not To Exceed Cost--------------------------------------------------------$6,900 Total Not to Exceed Cost for Change Order#2 is-------------------$6,900 Page 1 / T Ci I..Y REGt;t�i�ER . CITY O F ASHLAND DATE PO NUMBER '_ 20 E MAIN ST. 8/7/2012 11083 ASHLAND, OR 97520 (541)488-5300 VENDOR: 017154 SHIP To: Ashland Public Works NORTHWEST BIOLOGICAL CONSULTIN, SCOTT (541)488-5587 324 TERRACE STREET 51 WINBURN WAY ASHLAND, OR 97520 ASHLAND, OR 97520 FOB Point: Req.No.: Terms: Net Dept.: Req.Del. Date: contact: Morqan Wavman Special Inst: Confirming? NO Quantity Unit Description Unit Price Ext.Price THIS IS A REVISED PURCHASE ORDER Restoration of Ashland Creek at the 247,452.00 Water Street Bridqe, Project No. 2006-29 Public Improvement Contract Effective date: June 19, 2012 Completion date: December 12, 2012 Insurance required/On file Processed change order 08/17/2012 26,565.65 Chanqe Order No. 1 Processed change order 08/17/2012 6,900.00 Chanqe Order No. 2 SUBTOTAL 280 917:66 BILL TO: Account Payable - TAX 0.00' 20 EAST MAIN ST FREIGHT 0.00 541-552-2010 TOTAL 280,917.65 ASHLAND, OR 97520 Account Number Project Number Amount Account Number Project Number Amount - E 260.08.17.00.70420 E 200629.999 140-14-5-8.-8-3 E 260.08.34.00.704200 E 200629.999 140,458.82 I Authorized Signature VENDOR COPY FORM #10 CITY OF CONTRACT AMENDMENT APPROVAL REQUEST FORM ,�S H LAN D Request'for a Change Order Name of Supplier 1 Contractor I Consultant: Northwest Biological Consulting Total amount of this contract amendment: Purchase Order Number: 11083 Title 1 Description:Ashland Creek Bank Restoration Project; PINE#2006.29 $ 33,465.65 X Per attached contract amendment Change Order No's 1 and 2—see attached Contract Amendment Original contract amount $ 247.452 100 %of original contract Total amount of previous contract amendments %of original contract Amount of this contract amendment 33.465.65 13.5%of original contract TOTAL AMOUNT OF CONTRACT $ 280.917.65 113.5%of original contract In accordance with OAR 137047-0800:1)The amendment is within the scope of procurement as described in the solicitation documents,Sole Source notice or approval of Special Procurement.2)The amendment is necessary to comply with a change in law that affects performance of the contract.3)The amendment results from renegotiation of the terms and conditions,including the contract price,of a contract and the amendment is advantageous to the City of Ashland,subject to all of the following conditions:a)goods and services to be provided under the amended contract are the same as the goods and services to be provided under the unamended contract;b)The City determines that,with all things considered,the amended contract is at least as favorable to the City as the unamended contract;c)The amended contract does not have a total tens greater than allowed in the solicitation document, contract or approval of a Special Procurement An amendment is not within the scope of the procurement if the City determines that if it had describcd the changes to be made by the amendment in the procurement documents,it would likely have increased compefilion or affected award of contract Contract amendment is within the scope of procurement: YES X NO' (If"NO",requires Council approval/Attach copy of CC.) Sourcing Method: SMALL PROCUREMENT-Less than$5,000 INVITATION TO BID or COOPERATIVE PROCUREMENT.QRF or ❑'YES",the total amount of contract and REQUEST FOR PROPOSAL EXEMPTION PURSUANT TO AMC 2.50 cumulative amendments<-$6,000. X"YES",the total amount of cumulative ❑"YES",the total amount of original contract and ❑If'NO",amount exceeding authority requires amendments:5 25%of original contract amount or cumulative amendments-<$100K for Goods& Council approval.Attach copy of Council $250,000 whichever is less. Services,:5$75K for Personal Services,<$50K for Communication. ❑ If"NO",amount exceeding authority requires Attorney Fees. ❑ Exempt-Reason: Council approval.Attach copy of Council ❑If"NO",amount exceeding authority requires Communication. Council approval.Attach copy of Council ❑ Exempt-Reason: Communication. ❑ Exem t-Reason: INTERMEDIATE PROCUREMENT SOLE SOURCE EMERGENCY PROCUREMENT Goods&Services-$5.000 to$100.000 ❑ "YES",the total amount of cumulative ❑ Written Findings:Document the nature of the Personal Services -$5.000 to$75,000 amendments s 25%of original contract amount or emergency,including necessity and circumstances ❑ "YES",the total amount of cumulative $250,000 whichever is less. requiring the contract amendment amendments s 25%of original contract amount. ❑ If"NO",amount exceeding authority requires ❑ Obtain direction and written approval from City ❑If'NO",amount exceeding authority requires Council approval.Attach copy of Council Administrator Council approval.Attach copy of Council Communication. ❑ If applicable,attach copy of Council Communication. ❑ Exempt-Reason: Communication ❑ Exem t-Reason: El Exempt-Reason: SPECIAL PROCUREMENT INTERGOVERNMENTAL AGREEMENT ❑'YES",the total amount of original contract and cumulative ❑"YES",the original contract was approved by City Council. amendments are within the amount and terms initially approved by Provide date approved by City Council: (Date) Council as a Special Procurement. If'NO",Council approval is required.Attach copy of Council Communication. ❑ If'NO",amount exceeding authority requires Council approval. ❑ Contract amendment approved and signed by City Administrator. Attach copy of Council Communication. Street Collections-_jJ57-,500— SDC Storm%$157-,500- Project Number;2006.29 Account Number: 260.08.17.00.704200 roc Account Number: 260.08.34.00.704200 'Expenditure must be charged to th appropriate acco�unt 6hers for the financials to reflect the actual expenditures accurately. Atfaca pages if needed. Employee Signature: co Q' A- �6epartment Head Signature: �Lt.:.t'r.p 3'�tSy2 �"�, (Equal to or greater than$5,000) Funds appropriated for urren scat year 1, S}/ NO Gam/ L,�-- :oz, ,: Finance Director(Equaitoorgreater than$5,000) Date Comments: Form#10—Contract Amendment Approval Request Form, Request for a Change Order, Page 1 of 1,8114/2012