HomeMy WebLinkAbout2012-228 CONT Chg Order #2-3 - Pilot Rock Excavation CITY OF ASHLAND DEPARTMENT OF PUBLIC WORKS CONTRACT CHANGE ORDER NO. #02-Revised PROJECT: N. Main/Wimer/Hersey Intersection Realignment DATE: 08/16/12 LOCATION: Various locations on project PROJECT NO.: 2002-05 CONTRACTOR: Pilot Rock Excavation, Inc. You are requested to perform the following described work upon receipt of an approved copy of this document or as described by the Engineer: Item No. Description Quantity Unit 11 Amount Item#1 jBid Item Adjustment I LS $ (8,200.00) Total this Change Order $ (8,200.00) Previous Change Order $ 8,400.00 Original Contract Total $ 580,545.00 Revised Contract Total $ 580,745.00 PERCENT CHANGE OF ORIGINAL CONTRACT 0.03% The time provided for completion of this contract is 'ncreased by no calendar days. This document shall become an amendment to the contract and all provisions of the contract wil pp Recommended By: q Z roject ger to Approved By: w _P 9 /7 / /p Public Works Director Date Accepted By: Pilot Rock Excavation, Inc. 650 E. Pine Street, Suite 102B Central Point,,FOR 97502' 9 7/Z Contractor Representative Date PUBLCN'ORFSIENGISEERING Teb54 10 88-5 34] 20 As E.Main Soon ra<:5410865.2900 Ashlmrd Oregon 97520 TTY: 800-]35-2900 ..ashla nl.orus G9pub-wrks�eng=-05 N.Main Hersey Wmer Intersection Realigna Admin102-05 Proi Acct Workbook-ConstructionAm PILOT ROCK EXCAVATION,INC. ORIGINAL BID QUANTITIES UPDATED BID LIST ITEM NO.SPEC.REF. DESCRIPTION QTY.UNIT BID PRICE TOTALBIDASIOUNT QTY.UNIT BIDPRICE TOTALBIDASIOUNT TOTALCHANGE Sesion 400 Drainage and Sewers 250 445 Ism 5f Irvin decreased, F 401 306 LF S 3000 S 9,18000 216 LF S 3000 S 6,480.00 S (2,70000) 260 445 I n .S Itcu increased.see FC d02 25 LF S 30.00 $ 750.130 235 LF S 3000 S 7,050W S 6,30000 Session 1000 Right-of-Nby Development and Control S - 840 1050 Ct 4 h in fi.k F,ri,e Wth VuO Cled F.b,ic ti Wall 111cm'n revs d si,,IT 03 80 LF S 4000 $ 3,200.00 160 LF S 40W S 6,400.00 E 3,20000 850 1095 BlwoleR6ck with Shelter Men deleted,see leper dated)uly 19.?012 1 EA S 6,500.00 $ 6,500.00 0 EA S 6,50000 $ - $ (6,500.00) 860 1095 Bench"fItem deleted.we letter dated July 19.20121 3 EA S 2,000.00 S 6,000.00 0 EA S 2,000.00 S - $ (6,000.00) Section 1100 Water Supply Systems $ - 870 1120 Irrigation stem mail dated July 23rd for once I.,ren no to S 195 1 LS $2 100000 $ 22"W 1. LS S 19500.00 S 19500.00 S '_50000 $ 39,430.00 $ (8;200.00) G:1pub n a%s,=-05 N.Main Hens/Nor ar IMenection Feelgnsa MMMA2-05 Pal Aw WoMMok-COmWcpon.v6a V VW012 821 AM I CITY OF ASHLAND July 25,N 12 Pilot Rock Excavation 650 E. Pine Street Suite 10.213 Central Point.OR 97502 Attn: Rand LeBaron RE: N.Mnin/Wimer/Hersey Intersection Realignment(Project#2002-05) FC #01—.Elimination of 12-inch Storm Drain Pipe Dear Rand, The City of Ashland requests the elimination of 90-feet of 12-inch storm drain pipe that is shown to be installed on Sheet C.I of the project plans. Instead of installing this pipe,the existing slurry capped 15-inch storm dram pipe shall remain in place. All manholes shown to be installed shall still be constructed. If you have any further questions feel free to contact me. j Sincerely, �^ Karl Johnson.EIT Associate Engineer cc: Mikc Uss y.Pitt Rock Fscadation .left Folvler,Pilot Rmt Fxcnvntion .PUBLIC WORKSIENGINUTM niv, Tet 54148&5347 20 East Main Street Fax:5414Wi(106 ��, 0.$hW W,Oregon 97520 TTY: 80o-735-2* .wwHashtend.rn.us G!pub 4sleng102-0S N.Man Hersey Wimer lntemmtior,Oia%n''C Consauctohicotrespondmzi?oonttactoAFietd Changest02-05 FC 01-Elimination of Stonn Brain Pipe I astatatiul-07-2512.b= s h 2 PROPOSED ELEC.-VAULT& P.P. TRANSITION TO MATCH SEE ECEC PLANS MATCH £XISRNG k w'I� �� 1' a R MATCH EXIS77NG EXISTING AC DRIVEWAY WALK I II CURB, GUTTER R'WALK R I STA8+36.53, 1295'LT MATCH fXlSI7N h _Q at I 7CN CUR I I,_ DRIVEWAY (((\�tl� �. '� II 11689.50 EX, 7C 4 \ YJ EXIS7lNC R/W ^ 2 " I1 17888.87 LX PV 1 9 / + \ GE i"i B V PROPOSE SD m 6 •\ C£NTERUN 4 6 14 1G I �fi` x—x—x x x EX7.ST77NG SIDf CK _ k'�: ( .,T k �. r9`n .- 4% T T PROPOSED ----._-----EMSPNGC �T •• � -\�^ r k�� X ib. -I 1 CENTERUNE _ 6 —EX.fz 1'L--per' =2+ 4.07 9 ml 8+00 N7709 J6 E ----Er.ssS ———— EX. so so 12'SD I T 9 so 'i- r .1 � �sD ' EXISTNG R/W Lu PROPOSED R/W I _ _ 12W II I MATCH £XIS77NG I I. 9 I 2 \ 1 hlr I' CURB R OU77ER PPROPOSED RETAINING WALL 1 1 1 Z 1 STA 6+69.14, 14.12RT 1 MATCH EXISTING 1 SEE SHEET W.1 1 1 1 6 ry S.G��G I 'ORIIEWAY I �15r��G TREE DURING MATCH MATCH EXISTING 1'ff✓' 1 I 6�I1O I 1 �16D CONSTRUCTION WALK 1 I--- 0---__— L-0——————— 94 API s� I OI 6 1 10+00 = St m 1 1 — — — — NORTH MAIN.S Z TREET I ��I I % I MATCH EX. CURB '11 1ssz6a.Ex. TIC ml II _ 166716 EX F/L � oil " �I IN NI 1I W h I Ih� 1IIli i EXBsD II iIZS i mh WIMER STREET 1905 I I Ainiru rMrAlr riivn I I CURB S GUTTER STANDARD CURB I I i CITY OF -ASHLAND July 25,2012 Pilot Rock Excavation 650 E.Pine Street Suite 102B Central Point,OR 97502 Attn: Rand LeBaron RE: N.Main/Wimer/Hersey Intersection Realignment(Project#2002-05) FC#02-Additional Storm Drain Pipe InstallatiOn Dear Rand; The City of Ashland requests the installation of an additional 210-feet of 15-inch storm drain pipe in Hersey Street. The new pipe run shall start at the manhole at Station 10+21,near the intersection of N.Main and Hersey Street,and finish at the manhole at Station 12+34, near the intersection of Hersey Street and Lori Lane. The beginning and ending manholes shall remain in place and only be altered to allow for a 15-inch pipe to enter/exit them. The existing manhole near Station 10+83 shall be adjusted if possible,but if necessary,a new manhole shall be installed at this location. -The new manhole at Station11+68 shall be installed,but altered to allow for the 15-inch pipe. The Cih•of Ashland also requests confirmation that these changes will use die same costs of the original bid items that relate to this additional work: ITEPA NO. f PTI DESCRiONs ifi\IT .:UNIT<PR10E 90 Asphalt Pavement Cutting LF S2.50 100 Removal of Asphalt Surfacing SY S5.00 260 15 inch StormSeµror Pipe,5 Ft Depth LP 532:00 280 Concrete Stone Sewer Manboles EA S1,800.00 if you have any further questions feel free to contact me. Sincerely Rarl Johnson. EIT Associate Engineer cc: Mik-4 Ussary.Pilot Roc--Excavation Jeff Fowler,Pilot Roc-Eacavatlon PUBLIC WORKSIENGINEERING DIV. Tel:5414811­5347 20 East&'lain Streak Fac 541-08&6['06 Ashtand,Onon 97520 TTY: 800-735.29011 anva.oshlaM onus G:IpubAwkslwgT2.05N.Win Hosey.Whwtntemection Rearyn4CCoislnwaton!Co spondancc'tortracim field6hwgesd2-05FCa2-Adduonel Storm Drain Pipe Installation•07.25.12Ac;a `PARKING LOT IMPROVEMENTS 2 B SEE SHEET C.3 EX7577NG OVE �iJ � J rNPaPCr � REM '� G DRIVEWAY APR 1-�� 6�I��IRG I II III f o PROPOSED R/W ^,/> f✓\ SEE SHEET kETAI (NG.WALL II S�tJ KING X01 4 11' 1RANSInON >n MATCH XlS7INC RETAINING WALL EAIS77NG AC DRIVEWAY PRO7C T DURING PROPOSED U77LITY POLE E IISEE ELEC. PLANS MATCH EXISRNG MATCH EXST CNOG II DRIVEWAY CURB & GUTTER STA 11+72.80, N1 6S.2T.6 27 III IIII I I I I l c�i I. =III1I III�I l I I I I I.. EVS77NG R/W ca I •,.11 • \ 5 s — Y7x E>G72:SD--so`__a-- 5D SD 5D `— � �r "' �`�;'e•., ... s �-1�- sD�. -sD____--"— r-a---�_r d'c 1 I cl I. o >s � h 1 K�yL ���Y f . r� 77jj l ��► x N74.46 Z#- � E 1 r�sf ,x.XY� FAX�CiA A7�J v MATCH EK PWT STA 11+84.9 ._--- T�— �\ V` � Y2 . _ `.Y '— ,\ ✓� z - K. 2" I I W $�. - J. Xc G0. ->r.� . •\- c-. �6-''SlDEWAL ,' 257.+ 7 I I. 11N�GI 6 MA7CH EWS71NC 1 G 18 I _E X119 i CURB & GUTTER 2 _ DRIVEWAY .i I78 ��J�ING 1 1 $ STA 11+92.55,.2)68'RT PC ON CURB RI E S L $ I STA 11+64.75 DRIVEWAY 'L�—�+�—�� RELOCATED GAS.MAIN ma, »II CONTRACTOR TO COORDINATE QII ' 3 PROPOSED,ELEC. VAULT & S7REET "EXISTING 'R/W WIN AWSTA.U77LI77ES IF RELOCA77ON I W LIGHT CONTROLLER, SEE ELEG. PLANS NOT COMPLETED BY START OF MWALK CH EXISTNG CONSTRUCnONO PF I HI�1 PRO7ECT EVS77NG S7REET LIGHT& BASE IN PLACE DURING CONSTRUCnON H ERSEY STREET 0 INDICATES BE REMOViEDNPAVEMENT CITY OF -ASH LAN D July 27,2012 Pilot Rock Excavation 650 E: Pine Street Suite ]02B Central Point,OR 975022 Attn: Rand LeBaron RE: N.Main/Wimer/Hersev Intersection Realignment(Project#2002-05) FC##03-Additional Fencing Installation Dear Rand, The City of Ashland requests the installation of an additional 80 LF of fencing be installed as part of the N. Main/Wimer/Hersey Intersection Realignment Project. The additional fence shall be installed on top of Retaining Wall "A"and shall follow the same requirements called out on Plan Sheet W.1 for the fencing previously included in the project. The bid item total will be increased from the original total of 80 LF to 160 LF and shall be paid at the sane price of WfLF If you have any further questions feel free to contact me. Sincerely, Karl Johnson,Eff Associate Engineer CC-' Mike U:snry,Pilot Rock Fx©vation Jeff Fowls,Pilot Rcek Fxcn avm PUBLIC woRNs) mDerRING DM. Tet 541-488-5347 20 East Man Street Fac 541-48640006 Ashland.OM90n 9701 TTY: 800.735.2900 Ira suw.ashland.tx.us G,IpubAvft�e.% .C-0 N.Maln Hersey Whwintehedbn Reargnl,d_CcnsrovI n1ConespafdanoetcmnimctodFieb Chaige 62.C5FC03-AddidonmFdndtgtnsmlladon- 01-2]42.doa CITY OF ASHLAND July 1.9,2012 Pilot Rock Excavation,Me; Rand LeBaron 650 E. Pine Street Suite 1028 Central Point,OR 97502 RE: N. Main/Wimer/Hersey Intersection Realignment(Project 42002-05) Elimination of Bid Items Dear Rand, The City of Ashland would like to request the elimination work and materials related to the bid items listed below: ITEh1 I SPEC. BID UNIT BID TOTAL NO. REF. DESCRIPTION QTY. UNIT PRICE AMOUNT Section 1000 Right--of-Way Development and Control 850 1095 Bicycle Rack with Shelter I EA $6,500 $6,500 —d 860 1095 Benches 3 EA $2,000 $6,OW The City is also requesting the elimination of the trash receptacle that is shown to he installed on Plan Sheet 1,3 as well as the future drinking fountain that is shown on Plan Sheet 1.3. It does not appear that these items were included as incidentals to any bid item and did not have a standalone bid item either. Sidewalk bases that were to be installed for all of the above items including the items which had specific bid items can also be eliminated. Attached is a sketch that summarizes all of these eliminations. Please feel free to contact me if you have any questions. Sincerely, Karl Johnson,EIT Associate Engineer PUBLIC wORKS/ENG1NEF.RING DIV. Td:541468.5347 20 Cast Mein Sired Far.541 48&460% Asldand,Oregon 97520 TfY:806-735-29DO www.nshlandar.hs O:rput-w k,s-mgt02-05 R Main 11mq•Wimcr Intersection RealigiM_AdmirS m Vendor(Pilo)Rodp,Cantrw Docamen&Winal cmdr Dm 02-05 , Elimination of aid!toms-07-19d2,docx I F- • 1 w — a \ ° J o �.0 T V UJ ZJ�i 11 � 1fyT g CL I\ a � \ � r 1• k ( VM�f� '1 �y1 N'�f.. l -pc rx �lyj�$\�I� ,V/��/✓'SE�\ f � ry �i ro +� � � y:1 1 .( J r1. \ \� `, V Y 1 �IT +L -nt M1sy4 r ,\t `CiYI��rI i r�t I w 11�. r, f^•r � pJ 1I I\v��/ (� � E SEWEP, ' I NORTH-MA1.ISTRE-ET From: Rand LeBaron To: Kad Johnson Subject: N Main/Wimer/Hersey Irrigation RCO Date: Monday,Jury 23,2012 10:39:32 AM Importance: High REQUEST FOR CHANGE ORDER Karl; As a result of the COA approving a different irrigation controller, our landscape contractor has reduced his price $2500.00. The amount previously bid for line item 870 was$22,000.00. The revised number is 519.500.00. Please call our office with any questions or concerns you may have. Thanks. Rand LeBaron Pilot Rock Excavation, Inc. 650 E Pine St. Ste. 1028 Central Point, OR. 97502 ph: 541-664-9288 fax: 541-664-9218 cell: 541-951-7411 rand @pilotrockx.com CC13# 1.57139 CITY OF ASHLAND DEPARTMENT OF PUBLIC WORKS CONTRACT CHANGE ORDER NO. #03 PROJECT: N. Main/Wimer/Hersey Intersection Realignment DATE: 09/05/12 Adjacent to Colwell Chiropractic and City Owned LOCATION: Parking Lot PROJECT NO.: 2002-05 CONTRACTOR: Pilot Rock Excavation, Inc. You are requested to perform the following described work upon receipt of an approved copy of this document or as described by the Engineer: Item No. Description Quantity Unit Amount Additional Trench & Conduit- See Item#1 1 Field Change#05 1 LS $ 3,307.00 Total this Change Order $ 3,307.00 Previous Change Order $ 200.00 Original Contract Total $ 580,545.00 Revised Contract Total $ 584,052.00 PERCENT CHANGE OF ORIGINAL CONTRACT 0.60% The time provided for completion of this contract is increased by one calendar day. This document shall become an amendment to the contract and all provisions of the contract w' y. Recommended By: 9 /Z Project te Approved By: (L 1264 � 7 /7 //2— Public Works Director Date Accepted By: Pilot Rock Excavation, Inc. 650 E. Pine Street, Suite 102B Central Point, OR 97502 315112- Contractor Representative Date PUBLC WORKWENGUNEE]MG Tel:541488-5347 20 E.Main sues F. 541488.6006 Ashland Oregon 97520 TTY: 800-735-2900 ,� w ashland.or.us G:\pu1b-wrks\eng\02-05 N.Main Hersey Wmer Intersection Realign%A_Admin\02-05 Pmj Acct Workbook-ConslructionAsx CITY OF ASHLAND k August 29,2012, Pilot Rock Excavation 650 E.Pine Street Suite 102B Central Point,OR 97502 Attn: Rand LeBaron RE: N.Main/Wimer/Hersey intersection Realignment(Project#2002-05) FC NOS—Additional Electrical Conduits j I f i Dear Rand, The City of Ashland requests the"installation of two additional electrical conduits parallel to N.Main Street and adjacent to the Colwell Chiropractic and the City of Ashland owned taxlots. One 2-inch conduit shall be installed with the conduits already designed to cross in conduit trench C7 and then this conduit shall continue north parallel to sidewalk to a location adjacent to the existing street light shown on the plan set,where a City supplied handhole shall be installed and this 2-inch conduit run can end. From this same handhole, one 2-inch conduit shall be installed towards the north and end in an additional City supplied handhole that shall be installed on the backside of the sidewalk on the City owned property. An additional l '/.-in conduit shall be installed and j connected to the existing street light conduit at the north project limits. The total length of 2-inch'conduit is approximately 235 linear.feetand the total length of 1 '/4-inch conduit is approximately70-feet Conduits shall be installed at an approximate depth of 2 feet from bottom of sidewalk.'A sketch of the'conduit layout has been attached to this Field Change for reference. The City of Ashland will.expect a final additional cost summary from Pilot Rock for the material costs and the additional labor that will be needed to install these conduits. Once approved,this total will be added to the total overall cost of the project. One additional calendar day shall be included as part of this Field Change. If you have any further questions feel free to contact me. Sincerely Karl Johnson,E1T i Associate Engineer - - cc: Mike Ossary,Pilot Rock Excavation j Jell Fowler,Pilot Rock Excavation ' { i i PUBLIC WORKSIENGINEERING DIV. _ Tel:541488-5347 i 20 East Main street Fan:541 488b006 . Ashland,Oregon 97520 TTY: 800-735-29M , w .ashtend.ocus ,S 'G:1pub-wrksletg102-05 N.Main Hersey Winter Intersection Re rignXC-CmstructionkGon. spmdmmc contractoffield Changes102-05 FC 05-Additional Electrical Condu'ds- 0830-12.doa _ - - 0; V:4 x 2ICAL PLM­" awl VI -S, I A STREET LIGHT %k %. CONTROLLEF T4 50KVA D-MOUNT TRANSFORMER ------- W/644-TRANS-ASHLAND PAD-VAULT '-1 ....... �b Odh PP N d��!%tiqo "lim't ole. W',- EXTEND SECONDARY--' EXTEND S L SECi TO =XISTING PCLE a�\ TO HANDHOLE EXISTING SERVICE POLE �A- X ---------- V )RTING 95-4535 POLE, V; 6�cq -F 51 EA'A RISER SHI]�N DETAIL VAULT W/A15-9 AT EMBLY SWGR-SC TI-S ?0 1-018 0_�3 --jig 11111ING D.R. E PF STREET SECONDARY S 41 POTE� AD 44 BARRIER POST (2)\') S,-.- NOTE 45 'OLE, EXISTING A X A9R i HANCHOLE EXtS k H SEC., N-T ES 7 N STIR E LI T ----- -- ------- - EX STING, A./STR EET\LIGHT I f . CITY OF I ASHLAND C August 30,2012 Pilot Rock Excavation 650 E.Pine Street Suite 102B Central Point,OR 97502 Attn: Rand LeBaron RE: N.MainfWimer/Hersey Intersection Realignment(Project 92002-05) FC#05A—Additional Electrical Conduits-Footing Removal 1 Dear Rand, In addition to the conduit installation described,in Field Change#05,the City of Ashland requests the removal of the concrete footing for the existing street light,which the City of Ashland Electric Department removed this morning. The footing is located approximately 55-feet south of the centerline of the alley/parking lot access driveway. The City of Ashland will expect a final additional cost summary from Pilot Rock that will be include costs related to the removal of this footing this footing and these costs should be included in the total costs for the conduit installation of Field Change 405. If you have any further questions feel free to contact me. Sincerely, Karl Johnson, Associate Engineer Co. Mike Ussary,Pilot Rock Excavation �! Jeff Fowler,Pilot Rock Excavation - J I , i i I PUBLIC WORKSIENGWEERING DIV. Tel:541488-5347 - - - 20.East Main Street Fax 541A88-8006 Ashland,Oregon 97520 TTY: 800-735-2900 =® wwweshland.or.us G:Ipub-wrks,NQ2-05 N.Main Hersey Winter Intersection RealignlC__CenstrucbonlCouespondanceloontractoAField Changes102-05 FC 05a-Additional Electrical Conduits- . Footug Removal-08-30-12.docx " i I 1 Prot RocL Excavation, Inc. "Excavation anti Pipeline Specialists" REQUEST FOR CHANGE ORDER FC#5 Sept. 4, 2012 City of Ashland Public Works Division Attention: Karl Johnson, Project Engineer Re: Field Change#5 For charges associated with installing additional electrical conduit from Hersey St. north along N. Main St. No. Item Quantity Unit Unit Cost Total 1 Trench & Backfill 195 LF 10 $1,950.00 2 Remove Street Light Footing 1 LS 500 $500.00 3 Electrician 1 LS 857 $857.00 TOTAL RCO $3,307.00 650 E.Pine St.,Ste. 1028•Central Point,OR 97502•Ph: 541-664-9288•Fax:.541-664-9218•CC8#157139 � Page 1 / 1 CITY 19rC ; E R - ' �. ASHLAND CITY O DATE PO NUMBER 20 E MAIN ST. 7/18/2012 10993 ASHLAND,OR 97520 (541)488-5300 VENDOR: 010462 SHIP TO: Ashland Public Works PILOT ROCK EXCAVATION (541)488-5587 650 E PINE STREET SUITE 1028 51 WINBURN WAY CENTRAL POINT, OR 97502 ASHLAND, OR 97520 FOB Point: Req.No.: Terms: Net Dept.: . . _ Req.Del. Date: Contact: Mike Fauqht- Karl Johnson - Special Inst: Confirming? NO -. Quantity Unit - Description Unit Price Ext.Price THIS IS A REVISED PURCHASE ORDER N. Main/Wimer/Hersey Intersection 580,545.00 Realignment Project- Contractor will complete all work associated work involved with the completion of this project including but not limited to concrete work, asphalt pavinq, electrical conduit installation, etc. COA Public Improvement Contract Effective date: July 9, 2012 Completion date: September 4, 2012 Insurance/Bonds required/On file Processed chanqe order 08/07/2012 8,400.010.1; Chanqe Order No. 1 Processed chanqe order 09/12/2012 8,200.001 Change Order No. 2 -*Revised* Processed chanqe order 09/12/2012 3,307.00 Chanqe Order No. 3 t; SUBTOTAL 584,052.00 BILL TO:Account Payable TAX 0.00! 20 EAST MAIN ST FREIGHT 0.0 541-552-2010 TOTAL 584,052'00 ASHLAND, OR 97520 Account Number Project Number - Amount Account Number- Project Number _ Amount E 260.08.12.00.704200 E 200205.120 584 052.00 9 Authc6zed Signature VENDOR COPY . FORM #10 CITY OF CONTRACT AMENDMENT APPROVAL REQUEST FORM ,�1S H LAN D Request for a Change Order Name of Supplier)Contractor)Consultant: Pilot Rock Excavation,Inc. 'Total amount of this Purchase Order Number: #10993 contract amendment: Title 1 Description:N.MainlWimerlHersey Intersection Realignment Project °$4,893.00 ® Per attached contract amendment Contract Amendment Original contract amount $580,545.00 100 %of original contract Total amount of rep vious contract amendments $8,400.00 1.4 —%of original contract Amount of this contract amendment -$4,893.00 0.8 %of on Inal contract TOTAL AMOUNT OF CONTRACT $584.052.00 100.6 %of original contract In accordance with OAR 137-047-0800:1)The amendment is within the scope of procurement as described in the solicitation documents,Sole Source notice or approval of Special Procurement 2)The amendment is necessary to comply with a change in law that affects performance of the contract 3)The amendment results from renegotiation of the tens and conditions,including the contract price,of a contract and the amendment is advantageous to the City of Ashland,subject to all of the following conditions:a)goads and services to be provided under the amended contract are the same as the goods and services to be provided under the unamended contact b)The City determines that,with all things considered,the amended contract is at least as favorable to the City as the unamended contract;c)The amended contract does not have a total term greater than allowed in the solicitation document, contractor approval of a Special Procurement An amendment is not within the scope of the procurement if the City determines that if it had described the changes to be made by the amendment in the procurement documents,it would likely have increased competition or affected award of contract Contract amendment is within the scope of procurement YES X NO' (If"NO",requires Council approval l Attach copy of CC.) Sourcing Method: SMALL PROCUREMENT-Less than$5,000 INVITATION TO BID or COOPERATIVE PROCUREMENT,QRF or E]'YES',the total amount of contract and REQUEST FOR PROPOSAL EXEMPTION PURSUANT TO AMC 2.50 cumulative amendments s$6,000. ® "YES",the total amount of cumulative ❑"YES",the total amount of original contract and ❑If'NO',amount exceeding authority requires amendments<_25%of original contract amount or cumulative amendments–<$100K for Goods& Council approval.Attach copy of Council $250,000 whichever is less. Services,<_$75K for Personal Services,<$50K for Communication. ❑If"NO',amount exceeding authority requires Attorney Fees. ❑ Exempt–Reason: Council approval.Attach copy of Council ❑If'NO',amount exceeding authority requires Communication. Council approval.Attach copy of Council ❑ Exempt–Reason: Communication. ❑ Exempt–Reaso INTERMEDIATE PROCUREMENT SOLESOURCE EMERGENCY PROCUREMENT Goods&Services-$5,000 to$100,00 ❑ 'YES',the total amount of cumulative ❑ Written Findings:Document the nature of the Personal Services -$5,000 to$75.000 amendments s 25%of original contract amount or emergency,including necessity and circumstances ❑ 'YES",the total amount of cumulative $250,000 whichever is less, requiring the contract amendment amendments s 25%of original contract amount. ❑If'NO',amount exceeding authority requires ❑ Obtain direction and written approval from City ❑If'NO',amount exceeding authority requires Council approval.Attach copy of Council Administrator Council approval.Attach copy of Council Communication. ❑ If applicable,attach copy of Council Communication. ❑ Exempt–Reason: Communication ❑ Exempt–Reason: ❑ Exempt–Reason, SPECIAL PROCUREMENT INTERGOVERNMENTAL AGREEMENT ❑'YES",the total amount of original contract and cumulative ❑"YES',the original contract was approved by City Council. amendments are within the amount and terms initially approved by Provide date approved by City Council: (Date) Council as a Special Procurement. If"NO",Council approval is required.Attach copy of Council Communication. ❑ If'NO',amount exceeding authority requires Council approval. ❑ Contract amendment approved and signed by City Administrator. Attach copy of Council Communication. Project Number 200205.120 Account Number 260.08.12.00.704200 Account Number 'Expenditure must be charged to opd t nu financials to reflect the actual expenditures accurately. A#ac extra pages if needed. Employee Signature: // Department Head Signature: (Equal to or grea r t n$5,000) Funds appropriated for current fiscal year. FS / NO Y L Zo Finance Director(equal to oiqreater than$5,000) ate Comments: G:Ipub-wrkskerg102-05 N.Main Hersey Wimer Intersection Realgn%_AdminlCons Vendor(Pilot Rock)IContmct DocumenWChange Order02-05 Form#10-Request far a Change Order-#02&03.docx