HomeMy WebLinkAbout2024-05-06 Study Session••�• Council Study Session Agenda
ASHLAND CITY COUNCIL
STUDY SESSION AGENDA
Monday, May 6, 2024
Council Chambers,1175 E Main Street
*This is joint study session with Ashland Parks and Recreation Commission
Live stream via rvtv.sou.edu select RVTV Prime. Recorded meetings are available on our website.
Public testimony will be accepted for both public forum items and agenda items.
If you would like to submit written testimony or if you wish to speak electronically during the meeting,
please complete the Public Testimony Form no later than 10 a.m. the day of the meeting.
5:30 p.m. Study Session
1. Public Input (15 minutes - Public input or comment on City business not included on
the agenda)
2. Wildfire Season Preparation Review
3. Water Treatment Plant Update
4. Adjournment of Study Session
In compliance with the Americans with Disabilities Act, if you need special assistance to participate
in this meeting, please contact the City Manager's office at 541.488.6002 (TTY phone number
1.800.735.2900). Notification 72 hours prior to the meeting will enable the City to make reasonable
arrangements to ensure accessibility to the meeting (28 CFR 35.102-35.104 ADA Title 1).
Page 1 of 1
nralts Council Study Session
May 6, 2024
Agenda Item
Wildfire Season Prep Review
From
Ralph Sartain / Mark Shay / Kelly
Burns
Title Fire Chief / Fire Marshal / Emergency
Manager
Contact
Ralph.sartain(@ashiand.or.us mark.shay(o)ashland.or.us, Kelly.burnsrcDashland.or.us
Item Type
Requested by Council ® Update M Request for Direction ❑ Presentation
SUMMARY
Staff will provide an update of City preparations for the upcoming wildfire season, as well as regional firefighting
resource availability.
POLICIES, PLANS & GOALS SUPPORTED
Wildfire risk reduction and Climate Energy Action Plan execution are supported through the wildfire mitigation
projects and updates to the Community Wildfire Protection Plan (CWPP). Regional Cooperation, Public Safety,
and community resilience are supported through the efforts and continuing work of our Emergency
Management Program.
BACKGROUND AND ADDITIONAL INFORMATION
This serves as the annual wildfire season preparation update to City Council.
FISCAL IMPACTS
None
DISCUSSION QUESTIONS
None
SUGGESTED NEXT STEPS
None, this is an informational presentation to City Council
REFERENCES & ATTACHMENTS
PowerPoint presentation
Page 1 of 1 IF
Ir
FIRE
RESCUE
1887
4 foa
ANA
7,n
—Mbm—
Fire Season 2024 May 6,2024
Preparedness summary
Firefighting Resource Availability
Ashland Fire & Rescue
Structural firefiahtina cartners
Wildfire Mitigation & Preparedness
➢ Helicopter Logging Update
➢ CWPP update
➢ Weed abatement process
➢ Expanded CERT training
➢ Ashland Wildfire Mitigation Project
➢ Green debris drop off events
➢ Outreach and education
Ell
Wildfire Mitigation & Preparedness
Wildfire Mitigation & Preparedness
➢ CWPP update
➢ Funded by a USDA Forest Service Grant
➢ Ongoing throughout the year
➢ Risk assessment conducted via drone with
Li Da r
➢ Collaboration with Oregon State University
and Boise State University
Wildfire Mitigation & Preparedness
➢ Weed Abatement
➢ Notices will be mailed June Is'
➢ Standardized process
➢ Increased collaboration with Code
Enforcement
➢ Data tracking
Wildfire Mitigation & Preparedness
➢ Expanded CERT Training
➢ Utilizing decommissioned Battalion Chief
vehicle as new CERT vehicle
➢ Increased number of authorized drivers
➢ Increased capacity to provide firefighter
rehab
➢ Annual evacuation exercise in June in
collaboration with Emergency Management
VI
Wildfire Mitigation & Preparedness
Ashland Wildfire Mitigation Project
➢ Catching up on completing previous projects
➢ Will begin opening new projects this month
➢ 155 properties mitigated including 11 roofs
replaced.
➢ Grant period concludes March 2025
Wildfire Mitigation
Preparedness
yen Debris Drop Off Events
Collaboration with Jackson
Emergency Management
April 271h and May llth
Wildfire Mitigation & Preparedness
`r Outreach and Education
Smokewise workshop on May 2nd
Community Wildfire Education Day on May
18th
AF&R Open House on May 31st
y WRAP program update
QUESTIONS?
Emergency Management Program
Evacuations Work
Evacuation Zone signs
Evacuation Zone map expansion
Evacuation Task Force
Regional Coordination:
Emergency Operations Center work
Evacuations Summit 2024
Citizen Alert/Everbridge
Individual Preparedness:
Home Evacuation Drills
Research Projects
Emergency Management
Evacuations Work
Evacuation Zone
signs
Coordination with Ashland GIS,
Street Department. Plans and
budget for more next year.
Emerqency Management
Evacuations
•.4 Wn-IZon
Evac Zone map
expansion.
Coordination with Jackson
County Emergency
Management, Jackson County
GIS, Ashland GIS
Emergency Management
Evacuations
Evacuation Task
Force
Operational group tasked with
solving the problem of
managing mass evacuations
I.
zone 6
I-
Emergency Preparedness
Regional Cooperation
Emergency Operations
Coordination with City, SOU, ASD.
Ongoing work: training, exercises,
and joint -policy development.
Emergency Preparedness
Regional Cooperation
Evacuations Summit
Coordination with Butte County
Officials and regional response
agencies.
Emergency Preparedness
Regional Cooperation
Citizen Alert
Emergency Messages
Coordination with Jackson County
emergency management to join
alerts regional platform Everbridge.
Emergency Preparedness
Individual Preparedness
Home evacuation drills
BSU Research project
Public Outreach and
LEVEL 2
BE SET
BE SET TO EVACUATE AT A MOMENT'S NOTICE
SIGNIFICANT DANGER IN THE AREA
Jk Follow your emergency plan and grab your go -kit of supplies.
n Check news and radio for updates.
Education A Inform loved ones of your evacuation plans.
Exploring more collaboration with nditions can change rapidly. Leave if you feel unsafe.
BSU and OSU in mass evacuation
drills April/May 2025.
THOUGHTS, QUESTIONS,
emergency
nagement
nrl Council Study Session
May 6, 2024
Agenda Item
Water Treatment Plant Project Update
From
Scott Fleury PE
Public Works Director
Contact
Scott.fleury,(@ashland.or.us
Item Type
Requested by Council ® Update ® Request for Direction ❑ Presentation ❑
SUMMARY
Before the Council is a status update and information presentation regarding the Water Treatment Plant Project.
The update includes the following information:
1. Current Project Status and Cost Estimate
2. Previous Studies/Analysis Background Information
3. Medford Water Commission Connection Information (TAP)
4. Fiscal Implications (Funding Mechanisms, Rates, Cost of Service, Low Income Utility Assistance)
POLICIES, PLANS & GOALS SUPPORTED
City Council Goals, Visions and Values:
• Public Safety, including emergency preparedness for climate change risk
• Quality infrastructure and facilities through timely maintenance and community investment
Essential Services
• Infrastructure
Department Goals:
• Maintain existing infrastructure to meet regulatory requirements and minimize life cycle costs.
• Deliver timely life cycle capital improvement projects.
• Maintain and improve infrastructure that enhances the economic vitality of the community.
• Evaluate all city infrastructure regarding planning management and financial resources.
BACKGROUND AND ADDITIONAL INFORMATION
Water Treatment Plant Design Status
The design of the new conventional filtration plant with Ozone pretreatment is 100% complete along with the
100% cost estimate, see table #2. As a reminder the current water treatment plant is a direct filtration plant,
which treats water through chemical addition, filtration and chlorination. The new plant was designed to provide
the Environmental Protection Agency multibarrier approach to the treatment process. The new plant includes
ozone pretreatment, chemical addition, high rate sedimentation, filtration and chlorination. The new plant was
designed for a 100-year life span (facility) and to meet the current Oregon Specialty Structural Code (seismic).
The new plant was also designed following the Oregon Resilience Plan for recovery from a disaster, see table #1.
The new plant was designed and located to mitigate known risks and issues associated with the existing plant:
1. Out of flood plain
Page 1 of 13
.'':.� Council Study Session
2. Away from landslide risk
3. Away from significant fire risk
4. Up to current seismic code (existing plant is un-reinforced concrete constructed before seismic codes were
in place).
5. To handle water quality fluctuations (taste and odor, algal toxins, turbidity)
Table 1: Oregon Resilience Plan (Infrastructure Recovery)
KEY TO THE TABLE
TARGET TIMEFRAME FOR RECOVERY:
Desired time to restore component to 80-90% operational
Desired time to restore component to 50-60% operational Y
Desired time to restore component to 20-30% operational
Current state (90%operational) X
TARGET STATES OF RECOVERY: WATER & WASTEWATER SECTOR (VALLEY)
2
Event 0-24 1-3 3-7 1-2 weeks- 1-3 3-6 6 1-3 3+
occur; hours days days weeks 1 months months months years years
month —1 year
Domestic Water
supply
Potable water
available at supply
source (WTP, wells,
Y
G
X
impoundment)
Main transmission
facilities, pipes,
pump stations, and
reservoirs
X
(backbone)
operational
Water supply to
critical facilities
Y
X
available
water for fire
suppression—ot key
X
supply points
Water for fire
suppression —at fire
Y
X
hydrants
Water available at
community
Y
X
distribution
centers/points
Distribution system
operational
Y
X
Page 2 of 13
.::� Council Study Session
Figure 1: Site Rendering with new plant
Table 2: HDR (engineer of record)100% Opinion of Cost Summary
Cost .511111111all,
Summary of Opinion of Probable Construction Cost
High Range
Low Range
+15%
Construction Costs
-100/0
$ 71,150,000
$ 61,869,000
$ 55,683,000
Summary of Opinion of Probable Construction Cost
High Range
Low Range
+15%
Solar Array Construction Costs
-10%
$ 3,790,000
$ 3,295,000
$ 2,966,000
Summary of Opinion of Probable Construction Cost
High Range
Low Range
+15%
BESS Construction Costs
-10%
$ 1,771,000
$ 1,W,000
$ 1,386,000
Page 3 of 13
R Mat
IFAI
I % Council Studv'Session
Project History and Background (Previous Studies/Analysis
The City has long been engaged in development of a new water treatment plant to replace the current facility
and mitigate known risks with the current facility. Going back to at least 1991 the Council and staff discussed
replacement of the current facility and management of taste and odor compounds present in Reeder Reservoir
raw water.
1991 Council Meeting Information:
Report by Director of Public Works on taste and odor problems.
Hall referenced his memo dated March 19th and a report from Brown and Caldwell dated
March 15th. The problem that occurred back in September had conditions Ashland has
never seen before. He suggested to Almquist that we seek an outside opinion, and Hall
introduced Dennis Eckhardt of Brown and Caldwell who summarized the report. He said the
problem is mostly climatic. There are new drinking water standards that staff has to meet,
which is difficult because there is less margin for error. He said algae is unpredictable. Reid
referenced Phase 3 and asked about a new plant. The existing plant is 40+ years old and in
a bad location. There has been some investment over a period of years to keep it going.
Council dedicated a piece of land to Parks up on Granite Street. Reid asked if we are
developing a park where we should be developing a drinking water plant. There is a limited
amount of space in the canyon. Laws said it seems the City needs a Master Plan for water
treatment. Eckhardt said parts cf the plant have never been used. Hall said there are funds
in next year's budget to handle some of the immediate needs. Laws moved that staff bring
back recommendations on a long range proposal for an appropriate approach to future water
treatment. Reid seconded, all ayes on voice vote.
BACKGROUND
At the March 21, 1991 meeting the Council received a report from
Mr. Dennis Eckhardt of Brown and Caldwell in reference to the
September, 1990 taste and odor incident.
The report was intended to serve two functions:
- to give the Council and staff an independent critique and
analysis of the taste and odor incident.
- to deal with the reasons for the incident and potential
changes that could be made in testing and processing water
in relation to algae blooms in Reeder Reservoir.
The Council began expressing concerns about the condition and
lifespan of the existing plant. As a result of those concerns,
the Council directed staff to return with a recommended course of
action including a "master plan" for the water treatment plant.
Page 4 of 13
.'":.\ Council Study Session
2012 Comprehensive Water Master Plan:
In 2012 the City adopted a new Comprehensive Water Master Plan, that was developed over a two (2) year
period utilizing the Ashland Water Advisory Committee (AWAC) and consultant staff. AWAC was a community
member appointed group that represented community concerns and issues during the development of the
master plan. Public meetings with the consultant firm and AWAC were held over the two year period while the
master plan was being developed. Prior to Council adoption of the Comprehensive Water Master Plan the City
also held a public town hall at the SOU campus, in which citizens attended to learn more about the plan, utility
rates and recommended capital improvement projects.
Within the 2012 Water Master Plan was the recommendation to construct a new 2.5 MGD water treatment plant
to provide peak capacity demand in the summer and operate in conjunction with the existing plant. The new
plant was meant to expand over time and replace the existing plant.
In 2016 the City began the process of updating the 2012 Water Master Plan, again utilizing AWAC as the citizen
advisory committee. As part of that process Public Works Leadership discussed the option of looking at full
replacement of the current plant and not building a supplemental plant and expanding over time.
Staff asked AWAC for concurrence to suspend the current decision and make a comprehensive cost
comparison for a single new 7.5 MGD plant and decommissioning the existing plant as opposed to making
improvements to the existing plant for a 20-year life which includes upgrades to the treatment process, and
necessary facility improvements to sustain potential earthquake and flooding damage. After general
discussion and better understanding of staff's request for defined fiscal responsibilities, AWAC unanimously
supported staff's request.
In 2017 Public Works staff discussed this potential new approach and AWAC's recommendation with the City
Council. The City Council accepted this recommendation and Public Works staff engaged Black and Veatch
along with RH2 Engineering in 2017 to perform the following tasks:
Develop costs for a new 7.5 MGD WTP with a comparable treatment process to the existing
plant.
2. Develop costs of facility and operational improvements to the existing treatment plant along with a
risk assessment for seismic, flooding and operational expandability at the current site.
Black and Veatch along with RH2 Engineering developed a Plant Evaluation Report that was presented to the City
Council on April 2, 2018, reference attachment #3.
April 2, 2018 Study Session Staff Report Excerpt:
"... it was determined that it is not possible to develop comparable alternatives due to the inability to
rehabilitate the existing plant that mitigates three major risks..."
In short, the engineering team of RH2 and Black & Veatch determined the existing plant could not fully
overcome the risks associated with seismic stability, flooding and ensuring capacity for potential future
regulatory requirements without rebuilding the WTP. Yes, the existing plant could be modified and updated
one element at a time, but in the end, short of a full rebuild, the overall risks remain - and the City would still
be operating in a less than desirable location which is also prone to wildfire and localized landslides.
Page 5 of 13
.'":.\ Council Study Session
Staff reviewed the details of the assessment and is confident in the approach taken. Although as suspected,
the short-term costs to provide upgrades to the existing plant are less than the cost to build a new plant, the
risk, not only to plant personnel, but the City as a whole is not acceptable. In addition, deferring construction
of a new plant only imposes greater overall cost to the City. The existing plant has a finite life and the City's
needs continue beyond that life span.
The Council accepted staff's recommendation to move forward with development of a new 7.5 MGD water
treatment plant and staff has continuously moved forward with project development since then.
During project development the staff has worked on the following major tasks to get to the 100% design phase
currently.
1. Alternative site analysis with selection of the Granite Pit site
a. Reviewed multiple city owned properties for placement of new treatment plant
2. Treatment train analysis and pilot testing of membrane filtration
a. Performed bench scale and pilot testing of treatment alternatives
3. Preliminary and Final Engineering Design, specification development and cost estimating
a. Prepared 30%, 60%, 90% and 100% Plans, Specifications and Estimates
4. Environmental and general project permitting and coordination with regulatory agencies
a. Coordination with City Planning, Oregon Health Authority, Department of Environmental Quality, Forest
Service, Oregon Department of Fish and Wildlife, Army Corp. of Engineers, Division of State Lands, State
Historic Preservation Office, Parks Department and Ashland Woodland Trails Association.
5. Financing and funding
a. Coordination with financial advisors and funding agencies for contractual language and bond
master declaration development, along with rate forecasting and debt service calculations
In addition, numerous other items have come up along the way requiring additional analysis and consideration
by the Council. These have included a review of the design demand originally projected of 7.5 MGD for the new
plant, Envision program environmental site and development considerations, COVID pandemic slowdown, and
funding mechanism review.
During the design development phase the forecasted demand of 7.5 MGD was questioned by the Community
and Council along the way and staff coordinated multiple times with consultant engineering staff to update the
long term supply demand analysis performed as part of the 2020 Water Master Plan. The updated supply
demand analysis which included climate change impacts has shown a demand of 7 MGD within the 50-year
window and potentially up to 9 MGD within the 100-year window, thus the plant design capacity was changed
from 7.5 MGD expandable to 10, down to 7 MGD expandable to 9. This has created cost savings for the project as
facility and pipe sizes were reduced accordingly, reference attachments #4, 5.
Also as part of the design development the City has worked with HDR and others utilizing value engineering
(ve)workshops to review the design and determine efficient cost reductions measures that do not reduce the
Page 6 of 13
.'":.\ Council Study Session
level of service of the new proposed plant. Value engineering workshops were held at the 30%, 60%, and 90%
design iterations.
TAP Connection Background
A commonly asked community question is "Why can't we connect and receive all water from the Medford Water
Commission"?
1. The City currently has 1000 acre-feet of storage in Lost Creek Reservoir. To expand for full
demand of the community more water rights would need to be purchased and approved by
the Army Corps of Engineers and Oregon Water Resources Department. Staff would expect
significant hurdles from a regulatory standpoint because the City already has an allocated
and utilized water right for storage within Reeder Reservoir and municipal water rights
through the Talent Irrigation District (TID). To get to the annualized demand using the TAP
system the City would need around 3500+ acre-feet of stored water right in Los Creek.
2. The Medford Water Commission has previously stated the maximum they will provide the City
of Ashland through the TAP system is 3 MGD, which is 4 MGD less than the design criteria and
future demand projections of the City. Medford's system expansions are aligned with this
maximum amount along with the forecasted demand of the other partner city's that utilize
the MWC source.
3. If Medford were to agree to an increase to account for the full demand of the City, there
would be significant infrastructure improvements required to get to a peak capacity of 7 MGD
and expandable to 9 MGD if required in the future. These improvements would be in Medford,
Phoenix, Talent, Ashland and some within ODOT right of way. Nothing is designed and
constructed currently to handle Talent, Phoenix and the maximum day demand of Ashland at
7 MGD. Significant modeling analysis would need to be done to define the pipeline and pump
station improvements. Depending on the outcome of the analysis minor or major changes to
the TAP master plan would be required to define infrastructure maintenance responsibilities
along with cost capacities. A minor example of infrastructure issues is the current Ashland
TAP station and connecting pipelines were designed for the maximum 3 MGD flow. There is
also not booster pump station in the City's system that moves TAP water from the Granite
Zone to the Crowson Zone feeding residents south/east of the Ashland Creek divide.
4. The City would need to negotiate with MWC on system development charges for the
increased demand and staff expects the cost for this alone to be in the millions of dollars. The
City negotiated a $2.6 million dollar SDC with the MWC for the current 2.13 MGD delivery of TAP
water. The City still needs to negotiate SDC's in order to upgrade to the proposed 3 MGD.
5. The current rate for TAP water is 1.01 cents/1000 gallons in the summer and .81 cents/1000
gallons in the winter. The rate just went up by 4 cents in a recent adjustment and staff
expects continued regular annual increases by MWC as they move forward with major
expansions and system improvements.
Page 7 of 13
IF;
I17�
•�":•� Council Study Session
6. In order to determine the feasibility along with having conservations with MWC and
regulators, staff feels the whole process could last anywhere from 5-10 years given the
situation, all the while maintenance and replacements will need to be performed at the
existing plant given its age and known issues. This includes modeling and feasibility analysis,
infrastructure planning, public outreach/education, multijurisdictional coordination,
environmental permitting, preliminary design, final design, construction, and development of
the funding process for all improvements required to create a full connection. All the while the
City is still paying to maintain the existing plant.
FISCAL IMPLICATIONS
Funding Mechanisms
Typical funding mechanisms for water related infrastructure projects are "bonds" or loans when there is not
enough cash available to completely fund an infrastructure project.
Water Infrastructure Financing and Innovation Act (WIFIA) through the Environmental Protection Agency.
Current Rates and Term: 4.77% @ 35 years.
The City was invited to apply to the WIFIA under the small city's program, which funds 80% of the project, with the
other 20% coming from another source, including in -kind match. The City was able to provide in -kind match
based on the land value where the new plant will be located along with all of the engineering work completed to
date. This set the maximum funding allowed by WIFIA at $75 million.
The WIFIA program offers federal loans with fixed interest rates based on U.S. Treasury rates and flexible
financial terms. This level of financing acts like a letter of credit that is reimbursable up to the maximum
loan allowable amount. The EPA can issue bonds under their purview for project funding and these bonds
would be considered similar to the revenue bond as described below.
A single fixed interest rate is established at closing, based on the weighted average life of the loan and
the comparable Treasury rate on the day of closing. (This is true for all loans/borrowers, regardless of
credit rating.) A borrower may receive multiple disbursements over the course of project construction at
the same fixed interest rate. Interest only accrues on disbursed funds, rather than the full balance of the
loan.
Borrowers from the WIFIA program can customize their repayments to match their anticipated revenues
and expenses for the life of the loan. Payments may be deferred up to 5 years after the project's
substantial completion. This flexibility provides borrowers with the time they may need to phase in rate
increases to generate revenue to repay the loan. WIFIA loans may have a final maturity of up to 35 years
after substantial completion of the project, allowing annual debt service requirements to be lower than
other forms of financing with shorter terms. WIFIA loans can be combined with various funding sources,
including rate revenues, revenue bonds, grants, and State Revolving Fund (SRF) loans.
Infrastructure Revenue Bonds:
Current Rates and Term: 4.5% @ 30 years.
Page 8 of 13
rVA
lrr
.'":.\ Council Study Session
Revenue Bonds are usually payable from revenues generated by the project or enterprise. They may be issued
under the authority of ORS 287A.150 and must adhere to applicable state and federal statutes and regulations.
Alternatively, Revenue obligations may be issued under ORS 271.390. Both bonds and obligations have the same
security structure and considerations with the caveat that Revenue Bonds are more widely recognized by
investors outside of Oregon markets. No ad valorem property taxes are levied or pledged. Revenue bondholders
do not have recourse against the full -faith and unlimited or limited taxing power of the government and these
bonds are expected to be fully self-supporting. The bonds are generally repaid from user charges, system
development charges or from enterprise earnings and do not rely on the ad valorem taxing powers of the
government for their security.
General Obligation Bond (GO)
General Obligation (GO) bonds typically benefit a community as a whole and are secured by the full -faith -and -
credit and taxing power of the Issuer. The Issuer pledges unconditionally to pay the interest and principal on the
debt as it matures. For Oregon local Issuers, a GO pledge means that the Issuer pledges all of its unrestricted
resources to meet debt service, including an unlimited property tax on all taxable property within the district.
Local government GO bonds may only be issued if authorized by a ballot election of the issuing jurisdiction.
Voter authorized General Obligation Bonds are supported by an unlimited tax levy outside of the limits imposed
by the Oregon Constitution, Article XI, Section 11.
Safe Drinking Water Revolving Fund Loan
Business Oregon manages the SDWRF Loan program for the State of Oregon. The City has previously utilized the
SDWRF process for improvements to TAP construction, pump station improvements and for the engineering
design of the new water treatment plant. Rates and terms through the SDWRF process vary depending on
qualifying project type. The SDWRF program also has limitations on the total amount that can be borrowed, thus
in utilizing this source, supplemental funding would be required. Reference attachment #6, SDWRF Fact Sheet.
Rates/cost of Service/Low Income Utility Assistance Program
Hansford Economic Consulting provided a water rate analysis package and recommendations and this
information was conveyed to the City Council at the December 4, 2023 Study Session (Staff Report) . The rate
analysis called for 10% increases for the near future to ensure the water fund has enough revenue to cover
operational and capital costs moving forward. As a reminder the rate analysis is a snapshot in time and staff
recommends updating every budget cycle to account for changes in the fund including operations and capital.
To date the rate increase recommendations have not been acted upon by the City Council. In addition to the
rate package staff provided background and recommendations for improvement to the City's low income utility
assistance program.
Affordability Analysis
In conjunction with the rate and low-income information provided in December of 2023, staff developed an
affordability matrix based on commonly accepted budget practices of accounting for 6-10% of your monthly
income to cover utility related costs.
Page 9 of 13
�r
•'"�•� Council Study Session
Table 3: Current Utility Affordability Matrix
Utility Bill Affordability Analysis
2021 Median Household Income $ 5,303.42
2% of Median Household Income Per Utility
Last Update
Utilities
Monthly Rate
% of Median Income
2019
Street Utility Fee
$ 9.56
0.18%
2021
Storm Drain Utility Fee
$ 5.44
0.10%
2019
Wastewater (average)
$ 54.20
1.02%
2019
Water (average)
$ 61.71
1.16%
2021
Electric (average)
$ 76.88
1.45%
2021
Ashland AFN
$ 65.00
1.23%
2022
Re co I ogy
$ 22.67
0.43%
N/A
Natural Gas
$ 56.00
1.06%
Totals
$ 351.46
6.63%
Table 4: Projected Utility Affordability Matrix
Projected Update
Utilities
Monthly Rate
% of Median Income
2023 (3%)
Street Utility Fee
$ 9.85
0.19%
2024 (7%)*
Storm Drain Utility Fee
$ 5.82
0.11%
2024 (6%)**
Wastewater (average)
$ 57.45
1.08%
2024 (10%)***
Water (average)
$ 67.88
1.28%
2023
Electric (average)
$ 7 6. 88
1.45%
2023
Ashland AFN
$ 65.00
1.23%
2022
Re co I ogy
$ 22.67
0.43%
N/A
Natural Gas
$ 56.00
1.06%
Totals
$ 361.55
6.82%
*Projected in the adopted Storm Drain System Master Plan (July 1, 2024)
**Projected in the adopted Collection System Master Plan (July 1, 2024)
***Projected in October 2023 Water Rate Analysis
How are water rates developed?
Ashland's current water rate structure is based on a 2016 "Water Cost of Services Study." Staff is
currently coordinating with HDR Engineering to develop an updated cost of service analysis that will
look at additions or changes to the rate structure to increase its progressiveness and align with equity
and affordability goals of the Council. Staff expects to complete the update by the end of 2024 to align
with budget priorities for the next budget biennium.
Page 10 of 13 AI
Or!
nrl Council Study Session
Residential customers pay a monthly flat rate to cover fixed operating costs. This fixed monthly cost,
includes a customer charge of $13.33, and a basic service (meter) charge depending on the diameter
of the household's water meter ($15.62 for a 5/8" to 3/4" meter) — a total of $28.95 per month.
Consumption (commodity) charges make up the rest of the revenue capture requirements as defined in
the cost of service. The commodity charges are broken into consumption tiers based on usage. The
City has 4 tiers for a majority of the year, but adds a fifth tier in summer to discourage very high
consumption.
Residential households, which make up a majority of users typically use significantly less water during
the winter months than summer. Average wintertime demand is about 1.75 million gallons per day,
while summer demand can go as high as 6.5 million gallons per day. On average a majority of Ashland
households have two (2) people or less and during the recent Water Conservation and Management
Plan update it was calculated the annualized per capita use for residential was 104 gallons per day per
person.
This equates to approximately 6,240 gallons per month for a household or 834 cubic feet of
consumption. This does fluctuate seasonally based on summer vs. wintertime demand.
Ashland Rate Comparisons:
Rate comparisons aren't apple to apple as rate methodologies and water systems are different across
the board and that is why cost of services structures are developed individually for municipal water rate
structures. Some water systems have treatment plants and raw water intakes on rivers, some pay a
wholesale price to obtain water from another purveyor, like the partner city's in the valley who obtain
treated water from Medford. Also the number of rate payers impact the overall rate structure through
and economy of scale.
These variabilities make it hard to provide a direct comparison, but the table below shows the various
rates at the 104 gallons per day per capita with a two -person household and the industry standard
calculation of 1000 cubic feet of consumption per month per residence.
Table 5: Rate Comparisons
Rogue Valley Household Water Costs
Water Rates By City
Example 1
Example 2
(gal. = gallons; ft3 = cubic feet)
A household uses
A household uses
6,240 gals (834 ft3)
7,500 gals (1,003 ft�)
n May 2024
i
in May 2024
Ashland
Flat rate: $28.95 (residences with '/4"
diameter meter)
$55.93
$61.71
Volumetric rate:
Up to 300 ft3: $.0280/ft3
301-1,000 ft3: $.0348/ft3
Page 11 of 13
�r
.::� Council Study Session
1,001-2,500 ft3: $.0472/ft3
> 2,500 ft3: $.0609/ft3
> 3,600 ft3: $.0784/ft3 (June -Sept.)
Grants
Flat rate: $38.76
$47.95
$52.52
Pass
Volumetric rate:
up to 3,740 gal.: $0.79/748 gal.
3,741-7,480 gal.: $1.57/748 gal.
7,481-18,700 gal.: $1.96/748 gal.
> 18,700 gal.: $2.36/748 gal.
Medford
Flat rate:
$18.99 for households < 1,500 ft. elevation
$26.44 �0,500 ft.
elev
$29.82 <1,500 ft
elev
$23.63 for households > 1,500 ft. elevation
$33.89 >2,100 ft.
$37.96 >2,100 ft
elev
elev
Volumetric rate:
Up to 5,000 gal.: $1.03/1,000 gal.
5,001-25,000 gal.: $1.86/1,000 gal.
>25,000 gal.: $2.70/1,000 gal.
Five elevation tiers - Increases with each
150 ft. of additional elev. over 1,500 ft. Rates
for households over 2,100 ft.:
<5,000 gal.: $1.48/1,000 gal.
5,001-25,000 gal.: $2.31/1,000 gal.
>25,000 gal.: $3.15/1,000 gal.
Phoenix
Flat rate: $40.61
$43.84
$47.09
Volumetric rate:
Up to 5,000 gal.: Incl. in flat rate
5,001-10,000 gal.: $2.16/1,000 gal.
10,001-50,000 gal.: $2.71/1,000 gal.
>50,000 gal.: $3.03/1,000 gal.
Talent
Flat rate: $22.38
$40.68
$51.73
Volumetric rate:
Up to 3,000 gal.: Incl. in flat rate
3,001-6,000 gal.: $5.65/1,000 gal.
Page 12 of 13
�r
•'"�•� Council Study Session
6,001-9,000 gal.: $6.20/1,000 gal.
> 9,000 gal: $6.72/1,000 gal.
DISCUSSION QUESTIONS
Why has the cost estimate changed so much?
Why can't the City receive all of its water from Medford?
Why can't the existing plant be rehabilitated?
What are next steps?
What are the expected construction impacts?
SUGGESTED NEXT STEPS
Next steps are dependent on the outcome of the petition referral process. If the borrowing resolution is referred
to the voters it will be placed on the November ballot. Once the outcome of the ballot item is determined, next
steps would be discussed with Council.
REFERENCES & ATTACHMENTS
Attachment #1 - Waste Treatment Plant Project - Decision Point History Memo
Attachment #2 - 2012 Comprehensive Water Master Plan (Link)
Attachment #3 - Black and Veatch Water Treatment Plant Evaluation
Attachment #4 - HDR Plant Capacity Projections
Attachment #5 - HDR Design Criteria Update
Attachment #6 - SDWRF Fact Sheet
Page 13 of 13 IF,;&
Memo
Date: April 29, 2024
From: Scott Fleury PE, Public Works Director
To: Sabrina Cotta, Interim City Manager
RE: Water Treatment Plant Decision Points
CITY OF
-ASHLAND
Below is a list of items with specific decisions as actions through the City Council regarding
the Water Treatment Plant Project.
April 17, 2012-2012 Comprehensive Water Master Plan
Council adopted the master plan at the April 17, 2012 Business Meeting. The plan included
development of a 2.5 MGD water treatment plant and 2.6 MG storage reservoir.
2.5 MGD Plant estimated at $12 million plus one additional employee requirement.
2.6 MG storage reservoir estimated at $6.7 million.
April 17, 2012 Minutes
April 7, 2015-2015-2017 Capital Improvement Program
Council approved the 2015-2017 Capital Improvement Program at the April 7, 2015 Business
Meeting. The CIP included the 2.5 MGD water treatment plant and 2.6 MD water storage
reservoir.
2.5 MGD Plant estimated at $14.5 million plus one additional employee requirement.*
2.6 MG storage reservoir estimated at $8.13 million.*
*Numbers inflated annually from the 2011 master plan project estimate.
April 7, 2015 Minutes
June 16, 2015-2015-2017 Biennium Budget
Council approved the 2015-2017 Budget at the June 16, 2015 Business Meeting that included
appropriations for the 2.5 MGD water treatment plant and 2.6 MD water storage reservoir.
2.5 MGD Plant estimated at $14.5 million plus one additional employee requirement.
2.6 MG storage reservoir estimated at $8.13 million.
June 16, 2015 Minutes
June 7, 2016-Infrastructure Finance Authority Funding Resolution
Council approved a resolution at the June 7, 2016 Business meeting authorizing an
Infrastructure Financing Authority loan for engineering and construction of a new 2.5 MGD
water treatment plant. The terms of the loan include $14,811,865 in principal, $1,030,000 in loan
forgiveness and an interest rate of 1.79% for thirty years
June 7, 2016 Minutes
G#ub-wrks\eng\2018 Project Year\2018-20 7.5 MGD WTP\Admin\Council Items\5.6.2024 Study Session Project Update\Council Package\05 06 24 Water
Treatment Plan Project UpdateAtch1.doc
December 6, 2016-2.6 MG Storage Reservoir Reimbursement Resolution
Council approved a reimbursement resolution at the December 6, 2016 Business Meeting
associated with the 2.6 MG water storage reservoir recommended in the 2012 master plan.
The reimbursement resolution allows the City to reimburse itself via loan proceeds for all
engineering work completed prior to construction.
December 6, 2016 Minutes
March 21, 2017-2.5 MGD Water Treatment Plant Preliminary Engineering
Council approved a professional services contract with Keller Associates at the March 21, 2017
Business Meeting for the design development of a 2.5 MGD water treatment plant and 2.6 MG
water storage reservoir. The preliminary engineering included a siting study and treatment
process analysis.
Initial site costs:*
1. Concrete Pit (high) $11.6 million
2. Concrete (low) $13.5 million
3. Granite (high) $14.7 million
4. Granite (low) $11.6 million
5. Asphalt Pit $15.4 million
*The initial site costs developed by Keller Associates in the preliminary phase only account for
site work (grading/excavation), piping, pumping and electrical. Total cost was evaluated
after the Granite low site was selected. All sites evaluated are on city owned property.
Total estimated cost of construction for the Granite low site:
1. Granite Low Membrane Filtration $26.2 million
2. Granite Low Membrane Filtration + UV $24.4 million
3. Granite Low Membrane Filtration + Ozone $29.4 million
GApub-wrksleng12018 Project Year12018-20 7.5 MGD WTP1Admin\Council Items15.6.2024 Study Session Project Update\Council Package105 06 24 Water
Treatment Plan Project Update.Atch1.doc
4. Granite Low Conventional Filtration $30.7 million
March 21, 2017 Minutes
November 6, 2017-2.5 MGD Water Treatment Plant Project Review
Council received a presentation at the November 6, 2017 Study Session from the Director of
Public Works who recommended a fresh look at the proposed 2.5 MGD water treatment plant.
Options provided to Council where to analyze and compare costs and risks associated with
rehabilitation of the existing plant to provide a 20-year useful life vs. construction of a brand
new 7.5 MGD water treatment plant. The proposal was to compare the City's current water
treatment plant with a new one that would treat water in exactly the same way. At this time
the City wasn't looking at other water treatment alternatives. In addition, prior to this meeting
the Director discussed these options with the Ashland Water Advisory Ad -Hoc Committee
(AWAC) at their regular meeting on September 26, 2017. The Committee unanimously
supported the Director moving forward with the analysis.
November 6. 2017 Minutes
April 2, 2018-Water Treatment Plant Next Steps
Council received a follow up presentation at the April 2, 2018 Study Session from the Director
of Public Works regarding an analysis done by Black and Veatch and RH2 regarding
improvements to the existing plant and risk mitigation compared to building a new 7.5 MGD
facility at an alternate site.
Existing plant rehabilitation (20 year life) $5.57 million.
No feasible cost developed for risk mitigation (fire, flood, landslide, seismic).
7.5 MGD Plant (new) $22.59 million (direct filtration -same as existing plant).
April 2, 2018 Minutes
October 2, 2018-Preliminary Engineering 7.5 MGD Water Treatment Plant
Council at the October 2, 2018 Business Meeting approved a professional services contract
with HDR Engineering for the preliminary engineering phase for the new 7.5 MGD water
treatment plant.
October 2, 2018 Minutes
April 2, 2019-2019-2039 Capital Improvement Program
Council approved the 20-year CIP at the April 2, 2019 Business Meeting. The 20-year CIP
contained the proposed 7.5 MGD water treatment plant project in the water fund.
7.5 MGD water treatment plant 5% design opinion of cost $32 million.
April 2, 2019 Minutes
June 4, 2019-2019-2021 Biennium Budget
Council approved the 2019-2020 biennial budget at the June 4, 2019 Business meeting, which
included appropriations for the 7.5 MGD Water Treatment Plant.
7.5 MGD water treatment plant 5% opinion of cost $32 million.
June 4, 2019 Minutes
G:\pub-wrks\eng\2018 Project Year\2018-20 7.5 MGD WTP\Admin\Council Items\5.6.2024 Study Session Project Update\Council Package\05 06 24 Water
Treatment Plan Project Update.Atch1.doc
June 4, 2019-FY 2020 Water Rates
Council approved a 4% water rate increase at the June 4, 2019 Business meeting. Water
rates/revenues support the water fund and in turn all water capital improvement projects
including the 7.5 MGD water treatment plant.
June 4, 2019 Minutes
August 5, 2019-7.5 MGD Water Treatment Plant Progress Update
Council received a presentational update on the preliminary engineering phase for the new
plant at the August 5, 2019 Study Session.
7.5 MGD water treatment plant 30% design cost estimate $36 million.
No proposed staffing increases.
August 5, 2019 Staff Report
August 5, 2019 Minutes
In addition to Council actions staff has continuously updated AWAC during their regularly
scheduled public meetings on project status during 2019. This included a presentation by HDR
similar to the one given before Council on August 5, 2019.
October 1, 2019- Award of a Professional Services Contract; Phase 2, Final Engineering for a
New 7.5 Million Gallon per Day Water Treatment Plant
Council authorized a professional services contract with HDR Engineering for Final
Engineering. The Final Engineering contract allows HDR to proceed forward with the 60%, 90%
and 100% iterations of design and cost estimating.
October 1, 2019 Staff Report
October 1, 209 Minutes
November 19, 2019-Envision Water Treatment Plant Solar
Council clarified their position regarding expectation for solar power and the Envision
program associated with the design for the new plant.
November 19, 2019 Minutes
April 19, 2021- Water Treatment Plant Design Envision Update
Provided and comprehensive project update including potential Envision component
enhancements for energy efficiency.
Staff Report
January 3, 2022 - Water Treatment Plant Project Update
Provided an update on the project and answered questions that were developed by Council
from the April 19, 2021 Study Session.
Staff Report
May 23 & 24, 2022 - Special Meeting
G:\pub-wrks\eng\2018 Project Year\2018-20 7.5 MGD WMAdmin\Council Items\5.6.2024 Study Session Project Update\Council Package\05 06 24 Water
Treatment Plan Project Update.Atch1.doc
Provided a review of the Capital Improvement Plan with a focus on the water system and
treatment plant project.
Minutes and Staff Report Information
September 6, 2022 - Contract Amendment with HDR Engineering
Council approved a contract amendment with HDR Engineering to finalize the plans,
specifications and estimates. The Contract amendment was necessary do to additional work
required through the process.
Staff Report
September 20, 2022 - Water Bond Resolution
Council approved a water bond resolution for borrowing to support the Water Treatment
Plant Project using Environmental Protection Agency Funding.
Staff Report
December 4, 2023 - Water Rates Review
Provided update on water rates analysis performed by Hansford Economic. The updated rate
analysis used the existing biennium budget and projected water treatment plant cost along
with forecasting trend increases over the next two biennium's.
Staff Report
March 4, 2024 - Water Bond Resolution
Council approved a new water bond resolution that repealed the one approved in September
of 2022 to fund the treatment plant project. The new resolution aligned with the ability to fund
100% of the project using the WIFIA program.
Staff Report
G:Ipub-wrksleng12018 Project Year12018-20 7.5 MGD WTPIAdmin\Council Items15.6.2024 Study Session Project Update\Council Package105 06 24 Water
Treatment Plan Project Update.Atch1.doc
CITY OF ASHLAND
WATER TREATMENT PLANT
Plant Evaluation Report
FINAL
B&V PROJECT NO. 197823
City of Ashland
26 MARCH 2O18
0 BLACK&VEATCH
Building a world of difference.
City of Ashland I Water Treatment Plant
Plant Evaluation Report
Table of Contents
1.0 Executive Summary................................................................................................................................1
2.0 Introduction.............................................................................................................................................. 4
2.1
Existing Information................................................................................................................................4
2.2
Project Approach.......................................................................................................................................4
2.2.1 Treatment Plant Process Areas........................................................................................5
2.2.2 External Considerations......................................................................................................6
3.0 Plant Evaluation.......................................................................................................................................
9
3.1
Existing Water Treatment Facility.....................................................................................................9
3.1.1 Summary of Existing Plant Evaluation by Discipline...........................................10
3.1.2 Facility Evaluation..............................................................................................................12
3.1.3 Asset Life Expectancies.....................................................................................................25
3.1.4 Planning Horizon................................................................................................................26
3.2
New Water Treatment Facility.........................................................................................................26
3.2.1 Site and Hydraulics Considerations............................................................................26
3.2.2 Treatment Process Considerations.............................................................................26
3.2.3 Cost Considerations...........................................................................................................27
4.0 Cost Comparisons..................................................................................................................................28
4.1
Cost Categories........................................................................................................................................28
4.1.1 Equipment -Specific Construction Costs....................................................................28
4.1.2 Rehabilitation Costs...........................................................................................................29
4.1.3 Cost Factors and Contingencies....................................................................................29
4.2
Prioritization of Improvements.......................................................................................................30
4.3
Summary...................................................................................................................................................
31
4.3.1 Additional Considerations...............................................................................................33
4.4
Conclusions...............................................................................................................................................37
LIST OF TABLES
Table 1-1
Capital Cost Comparisons (Level 5 AACE Cost Estimate)........................................................3
Table2-1
Asset Hierarchy..........................................................................................................................................5
Table 3-1
Asset Effective Life Expectancies.....................................................................................................25
Table 4-1
Cost Factors to Develop Total Project Costs...............................................................................29
Table 4-2 Capital Cost Comparisons...................................................................................................................32
Table 4-3 Considerations with Positive/Negative Impacts...................................................................... 34
BLACK & VEATCH ( Table of Contents i
City of Ashland I Water Treatment Plant
Plant Evaluation Report
LIST OF FIGURES
Figure 2-1 Existing Water Treatment Plant Site................................................................................................4
Figure 2-2 Proposed Water Treatment Plant Flood Wall (Carollo, 2010)...............................................7
Figure 4-1 Itemization of Rehabilitation Cost Allocations Over Time .................................................... 31
LIST OF PHOTOS
Photo 2-1 - Lab in Administration Building...............................................................................................................13
Photo 2-2 -
Potable Water Storage Tank and Hydro -Pneumatic Tank...........................................................13
Photo2-3 -
Influent Weir...................................................................................................................................................14
Photo 2-4 -
Influent 36-inch Butterfly Valve.............................................................................................................14
Photo 2-5 -
Talent Irrigation District Influent Pipeline........................................................................................14
Photo2-6 -
Top of Alum Tank.........................................................................................................................................15
Photo 2-7 -
Base and Pedestal of Alum Tank............................................................................................................15
Photo2-8 -
Soda Ash Hopper...........................................................................................................................................16
Photo 2-9 -
Soda Ash Hopper, Dissolving Tank, and Metering Pumps...........................................................16
Photo 2-10
- Powdered Activated Carbon Hopper.................................................................................................17
Photo 2-11
- Filter Polymer Aid Hopper and Mixing Tank..................................................................................18
Photo 2-12
- Filter Polymer Aid Feed Tanks.............................................................................................................18
Photo2-13
- Cationic Polymer Feeder.........................................................................................................................18
Photo 2-14
- Sodium Hypochlorite Tank and Hoist................................................................................................20
Photo 2-15
- Corrosion in Chlorine Building.............................................................................................................20
Photo 2-16
- Flocculation Basin and Paddle Mixer.................................................................................................21
Photo 2-17
- Grating Above Overflow Box.................................................................................................................21
Photo2-18
- Dual Media Filters......................................................................................................................................22
Photo 2-19
- Abandoned Dual Media Filter#7.........................................................................................................22
Photo 2-20
- Air Scour Air Supply (Evident Leakage)...........................................................................................23
Photo 2-21
- Efflorescence on Exterior Dual Media Filter Wall........................................................................23
Photo2-22
- Motor Control Center................................................................................................................................24
Photo 2-23
- Potable Water Pump Disconnects.......................................................................................................24
Photo 2-24
- Dual Media Filter #1 Turbidity Meter...............................................................................................25
Photo2-25
- PLC Telemetry Unit...................................................................................................................................25
BLACK & VEATCH I Table of Contents
City of Ashland I Water Treatment Plant
Plant Evaluation Report
1.0 Executive Summary
The City of Ashland is evaluating the rehabilitation costs associated with continued operation of the
existing surface water plant as compared to the costs associated with construction of a new
treatment plant. Black & Veatch reviewed available facility information and performed a site walk
of the facility to determine the rehabilitation needed at the existing plant to maintain its operation
for a 20-year planning horizon. Costs for rehabilitation were compared to a non -site specific cost to
build a new water treatment plant similar to the existing plant.
Background
The City's primary source of raw water comes from the Ashland Creek watershed. Raw water is
supplied to the existing plant from Reeder Reservoir on Ashland Creek, located approximately two
miles southwest of the city. The existing Ashland WTP site is approximately 0.6 acres in size, and is
constrained by the Ashland Creek roughly to the east and south, and by a cliff to the north. Water is
conveyed from reservoir through a penstock from Hosler Dam to supply water to the Reeder Gulch
hydroelectric power plant. The powerhouse is located immediately upstream of the existing WTP.
After flow passes through the powerhouse, it discharges into a tailrace structure where a portion of
the water is diverted to feed the existing WTP.
Existing WTP Risks and Limitations
In its current location, the plant faces several challenges/risks to its safe operation. These include;
the risk of flooding due to rain or Dam failure, risk of a seismic event/damage due to landslide and
inability to meet future treatment requirements,. Based on the evaluation, it was determined that
mitigating these risks in a cost-effective and practical manner is not possible. Consequently, it is
not possible to develop comparable alternatives due to the inability to rehabilitate the existing plat
in a manner that mitigates these three major risks; the risk of flooding, risk of a seismic event and
the inability to meet future treatment requirements. The limitations associated with mitigating
these risks are summarized below
Flood Risk. The existing WTP is susceptible to flooding due to rain or dam failure. It has
experienced flooding three times in its last 60 years of operation. The flood risk could potentially
be mitigated by constructing a flood wall; however, its ability to withstand a major flood event is
questionable. Constructing a flood wall next to existing basins and structures along the creek is
risky because it could potentially damage the existing facilities due to vibration related to
construction activities. As such, the cost to mitigate the flood risk cannot be determined with
reasonable certainty and therefore not included in the cost comparison.
Seismic Risk and Landslide Risk. Regarding the seismic risk, a detailed structural assessment of
the existing structures is outside the scope of this document; however, a cursory review indicates
BLACK & VEATCH I
City of Ashland I Water Treatment Plant Plant Evaluation Report
that the existing structures do not meet the current seismic code requirements. Assuming that the
current loading on the existing structures remains the same, it is not required to upgrade the
existing structures to meet the current seismic codes. However, in a seismic event, these structures
could suffer significant damage and impair the ability of the plant to produce potable water. Due to
the age and condition of the facilities it is not feasible to upgrade the existing structures to current
seismic standards in a cost effective manner. Depending on the severity of a seismic event, the time
to repair and make the plant functional could range from days to months. In its current location in
the canyon, the existing plant is susceptible to damage from landslides. Similar to the seismic risk,
the extent of damage that the plant could suffer will depend on the severity of a landslide event.
Treatment Limitations. The existing plant is able to produce high quality drinking water using the
current microfloc/filtration treatment process. It is currently unknown if additional treatment
would be required by EPA as the regulations evolve in the future. However, due to lack of space, it
is not possible to construct additional treatment processes or modify existing facilities to
accommodate new treatment while keeping the plant in operation. Additionally, exposure of any
new facilities to other risks (flooding, seismic, landslide) cannot be practically mitigated. As such,
the existing plant does not have the ability to meet any additional treatment requirements such as
treatment of algal toxins, if required by future regulations. Any additional treatment would need to
be located offsite and would require associated infrastructure investment for pumps, piping, and
storage to convey to the distribution system. Since this additional offsite treatment would be
needed for both alternatives (existing and new plant configuration), it has not been included in the
cost comparison.
Capital Cost Comparison
The cost comparison presented below does not take into account the risks outlined above since
these cannot be mitigated cost-effectively. The cost purely focuses on the rehabilitation of the
existing plant in its current condition. The capital cost comparison of the two alternatives shows
the rehabilitation cost of the existing plant to be approximately 25% of the construction costs of a
new plant. The base cost comparisons are demonstrated in Table 1-1 below. It assumes that the
new plant will have the same capacity of 7.5 mgd and identical treatment processes as the existing
water treatment plant.
A cost escalation is applied for both alternatives assuming that these costs will be incurred roughly
5 years from today's date. The cost escalation for both alternatives is determined to be the same as
further explained in Section 4.1.3.
BLACK & VEATCH
City of Ashland I Water Treatment Plant Plant Evaluation Report
Table 1-1 Capital Cost Comparisons (Level 5 AACE Cost Estimate)
Facility Construction Cost $12,148,000 $3,047,500
Contractor Markups $2,915,000 $731,400
Subtotal Total Construction Cost $15,063,000 $3,778,900
Total Non -Construction Costs $5,475,000 $1,284,826
Escalation (29/o/yr. @ 5 yrs. = 10%) $2,053,000 $506,373
Total Project Cost $22,591,000 $5,570,099
Total Project Cost (Rounded to nearest $1000)"' $22,591,000 $5,570,000
1 Level of Accuracy corresponds to AACE Level 5
2 The major risk factors (Flooding, Seismic, Landslide, and Treatment) are not addressed in the cost.
*-Non-site specific estimate.
Conclusion
While it is feasible to continue operating the existing facility over the 20-year planning horizon at a
lower initial investment, the existing plant has some negative considerations that present a risk to
continued operation. The City has the opportunity to accept or mitigate these risks in the decision
process. Ultimately, the existing facility has a definitive life span and will reach a point where
continual investment is no longer financially prudent or will not achieve the desired level of service
for the City. Deferring construction of a new plant beyond the 20-year planning horizon will
impose a greater overall cost to the City.
BLACK & VEATCH 1 3
City of Ashland I Water Treatment Plant
Plant Evaluation Report
2.0 Introduction
The City of Ashland is evaluating future improvements needed at the current surface water
treatment plant (WTP) (Figure 2-1) to provide reliable service over a planning horizon of the next
20 years. The purpose of the assessment is to evaluate the costs associated with continued
operation of the existing plant as compared against the costs associated with construction of a new
treatment plant. In addition to condition related inputs, the study considers adherence to future
regulations, treatment capabilities, capacity, and external/environmental risks with continued
operation of the existing plant.
Figure 2-1 Existing Water Treatment Plant Site
2.1 EXISTING INFORMATION
Data request forms were developed with a basic questionnaire for WTP staff to complete with any
additional information and past reports. The City staff responded with relevant information for
each plant system. A hierarchy of evaluated systems was developed from the drawings provided by
the City. Information provided by the City on the various systems was incorporated as a reference
during the site evaluation.
2.2 PROJECT APPROACH
This report summarizes the key points of the evaluation with recommendations for improvements
needed at the existing plant to maintain its operation, cost opinions for a new plant construction
with features duplicating the existing plant, and further evaluation recommendations as necessary.
The findings from the existing plant evaluation are compared against a typical generic cost
(national cost) to build a new 7.5 Million Gallon/Day (mgd) water treatment plant employing
similar treatment technologies.
BLACK & VEATCH
City of Ashland I Water Treatment Plant
Plant Evaluation Report
2.2.1 Treatment Plant Process Areas
As part of the evaluation, Black & Veatch reviewed available facility information and performed a
site walk of the facility to determine the existing condition of the major process structures and
equipment. To facilitate the assessment, the WTP was subdivided into the following areas:
Administration Plant Influent 11 Chemical Feed
Pretreatment Dual Media Filters It Clearwell/Product Water
Assessments were categorized by discipline as followings:
Process Mechanical ■ Electrical
Instrumentation and Controls ■ Civil/Structural
Black & Veatch performed a walk-through condition assessment of the facilities on February 7,
2018 to document materials of construction and evaluate potential concerns and systems
performance. Visual inspections of the facilities were performed to document conditions.
Documentation of conformance with current design standards and codes were noted. The following
hierarchy represents the major facilities at the plant that were included in the assessment:
Table 2-1 Asset Hierarchy
Operations Building, building mechanical systems
Administration
Plant roadways
Fire Protection Systems
Intake/Headworks Piping and feed from the dam
Plant Influent
Talent Irrigation District Piping
Alum, Soda Ash, Carbon, Potassium Permanganate & Cationic Polymer Feed Pumps
Filter Polymer Aid Feed Pumps
Chemical Feed
Building Structure
Sodium Hypochlorite Tanks
Old Chemical Storage Building
East & West Flocculation Basin (incl. gates/valves)
Pretreatment
Flow Control Box (incl. gates/valves)
Filter Basin Structures 1 through 8
Backwash Pumps 1-3 (incl. associated valves, meters and instrumentation)
Dual Media Filters
Blower Motor
Potable Detention Tank
Hydro -pneumatic Tank
Clearwell Basin Structure
Clearwell
Potable Pumps
Finished Water Flow Meter
BLACK & VEATCH 1 5
City of Ashland I Water Treatment Plant Plant Evaluation Report
2.2.2 External Considerations
With the existing plant, there are several external considerations that have the potential to disrupt
or impact the WTP operation. Although out of scope for this project, it is recommended that the City
perform an in-depth evaluation of these potential risks to quantify their impacts to maintaining
operation of the existing WTP. The intent of this section is to describe the external factors for
further consideration and action by the City to mitigate risk.
A new plant would obviously provide provisions for increased capacity, redundancy, and improved
effluent water quality. Furthermore, an alternate location would be sited in an area that is less
susceptible to damage from periodic flooding, landslides, and wildfire. The two primary
considerations for addressing existing facility treatment constraints and addressing natural
hazards are presented below.
2.2.2.1 Treatment Constraints
A new plant could be designed to improve finished water quality by reducing taste and odor
concerns, and treating any future regulated contaminants. Although generally a seasonal issue, the
raw water occasionally contains a high concentration of algae. In previous years, the City cleaned
the upstream reservoir to remove sediment which can contribute to algae growth. City also
routinely sends algae samples to the lab for toxicity analysis.
Although historically non -toxic, the reservoir can contain algae that can produce cyanotoxins. This
potential water quality concern is something that a new plant could be designed to be able to
address through additional treatment. The existing site lacks the area to expand treatment
capabilities to mitigate algal toxins to address EPAs anticipated Algae Guidance that is currently
being developed.
The algae are also the source for the seasonal taste and odor issues that the City currently
experiences. The existing plant uses powdered activated carbon (PAC) on a seasonal basis to
attempt to remove tastes and odors. The past performance of PAC has not been adequate in
removing Geosmin low enough to avoid customer taste and odor complaints. Furthermore, PAC can
be difficult to manage; it is messy to handle and feed and PAC dust can create an explosive
atmosphere around the feed equipment. PAC feed facilities are typically classified as explosive
hazard areas. A new plant could be designed to be able to address these taste and odor issues.
Furthermore, the following additional treatment considerations could be incorporated into the new
plant design:
Improved ability to remove iron and manganese
Corrosion control by supplementing alkalinity and controlling pH
Removal of color / control of disinfection byproduct formation
BLACK & VEATCH
City of Ashland I Water Treatment Plant Plant Evaluation Report
Other factors that should be considered include expanding the existing site to meet future capacity
requirements. The existing 7.5 mgd plant is located on a constrained site with limited ability to
expand. A new plant can be designed for an ultimate production capacity of 10 million gallons per
day (mgd), which would provide the water needed to meet the City's demands for the next 20 years,
and beyond.
Automation is an important consideration in the evaluation to maintain the existing plant as
compared to constructing a new plant. A new plant would likely be automated which would benefit
the City by being less labor-intensive (potentially increasing over time with facility age) to operate
and maintain the existing plant over the 20-year planning horizon. Through the use of automation,
it is anticipated that a new plant would require less operator attention than the existing plant.
2.2.2.2 Natural Hazards
The location of the existing plant places the facility at risk of flooding. Based on information from
the City, high flows in Ashland Creek during 1997 caused significant damage to the plant and
disrupted water supply to the City. The existing plant was also damaged in the flood events in 1964
and 1974. Because of its remote location within the steep walls of Reeder Gulch, it may not be
practical to completely protect the plant from periodic flooding. However, a flood wall at the
existing water treatment plant would improve reliability of the existing plant.
Construction of a flood wall at the existing water treatment plant was evaluated by Carollo
Engineers in the Water Conservation & Reuse Study (WCRS) & Comprehensive Water Master Plan
(CWMP) prepared in October 2010. The flood wall proposed by Carollo (Figure 2-2) would tie into
the slope north of the existing plant then extend between the water treatment plant and Ashland
Creek for a length of approximately 1,000 feet. The wall would have a height of 10 feet with a
thickness of 2 feet and the construction assumes that the wall would tie into existing structures at
the plant, rather than be free standing.
Figure 2-2 Proposed Water Treatment Plant Flood Wall (Carollo, 2010)
BLACK & VEATCH
City of Ashland I Water Treatment Plant Plant Evaluation Report
The existing plant is also susceptible to failure from a seismic event. The original plant was built in
1949 and has had one major renovation conducted in 1995. Considering the age of these facilities it
is uncertain if the original design approach considered both static and dynamic loads. Since the
original construction date, seismic loading design considerations have changed. Most water -
retaining structures today are designed using ACI 350, which provides increased levels of
reinforcing, closer rebar spacing, and limitations on crack width to prevent leakage. It is unlikely
that ACI 350 or any of its principles were used to design the existing plant. The existing structures
are likely unable to resist modern day seismic loads. These changes, coupled with a facility with
concrete condition that has deteriorated due to normal use, makes the existing structures
susceptible to failure from seismic activity. The plant basins and structural elements (such as walls)
should be evaluated to determine if they can resist the current seismic acceleration and
hydrodynamic forces per ACI 350. The City should consider whether existing facility should be
upgraded to meet the requirements of the current seismic code.
2.2.2.3 Redundancy/Reliability
The City has some provisions for redundancy for up to 2.1 mgd treated water supplied from the
Talent, Ashland and Phoenix (TAP) Pipeline. The TAP Pipeline benefits the City to provide supply
during a treatment plant outage. The City has water rights for TAP through Lost Creek Lake up to
2.1 mgd only, but the TAP pumps can supply up to 3.0 MGD. Currently the TAP system has the
ability to supply roughly one half of the population in the City. Additional improvements need to be
made to the pumps and piping system to convert this into a full redundant supply. Although the
City has provisions for an alternate source of finished water, the overall supply is not under the
City's control.
BLACK & VEATCH
City of Ashland I Water Treatment Plant
Plant Evaluation Report
3.0 Plant Evaluation
The following sections discuss the evaluation between the existing water treatment plant and a new
water treatment plant. This includes the condition assessment and capital improvements to the
existing plant, as well as new facility treatment assumptions and process description.
3.1 EXISTING WATER TREATMENT FACILITY
The City's primary source of raw water comes from the Ashland Creek watershed. Raw water is
supplied to the existing plant from Reeder Reservoir on Ashland Creek, located approximately two
miles southwest of the city. Water is conveyed from reservoir through a penstock from Hosler Dam
to supply water to the Reeder Gulch hydroelectric power plant. The powerhouse is located
immediately upstream of the existing WTP. After flow passes through the powerhouse, it discharges
into a tailrace structure where a portion of the water is diverted to feed the existing WTP. Average
water production is 2.9 mgd with peak summertime demands approaching 6.5 mgd. The WTP can
also be fed using raw water supplied from the Talent Irrigation District's (TID) pipeline. TID water
is used to supplement the WTP during low watershed conditions in reservoir.
The Ashland WTP site is approximately 0.6 acres in size, and is constrained by the Ashland Creek
roughly to the east and south, and by a cliff to the north. The entire plant is gravity flow. Water is
pulled from the Ashland Creek via a 36-inch raw water tailrace structure.
The treatment process consists of rapid mix, mechanical flocculation, granular media filtration, and
chlorination. The water flows through a flash mixing process, then to the flocculation basins. The
high rate filtration plant continues utilizing alum as a coagulant to aid particle agglomeration and
soda ash for alkalinity adjustment and pH control. A chlorine solution is fed immediately ahead of
the flocculation tanks. The chlorine feed is adjusted in response to the water temperature.
Following flocculation, the water flows through the filter beds and then into a 168,000-gallon
clearwell where the water is chlorinated and distributed to the system.
Alum, sodium hypochlorite, soda ash, and activated carbon can be mixed with the raw water in the
flash mixing tank as part of the treatment process to aid in the removal of solid particles and other
contaminants. Alum, soda ash, cationic polymer, and potassium permanganate are added via a
mixer and the flow is sent through flocculation basins. The powdered activated carbon is used only
seasonally when TID water is included in the system to treat any taste and odor problems or if the
color is high. Color may be the result of organic matter, manganese, copper, or iron in the water.
The activated carbon absorbs the organic material in the raw TID water, to remove the color.
The original plant construction included a previous sedimentation basin that was repurposed into
the current chemical building. A separate chlorine building is located next to the old sedimentation
basin structure. A 12.5% sodium hypochlorite solution is fed via a peristaltic pump to the influent
mixer and the clearwell. All chemical pumps are located in the building basement level near the raw
BLACK & VEATCH
City of Ashland I Water Treatment Plant Plant Evaluation Report
water pipeline and the flash mixer. Existing parallel sedimentation basins were repurposed into
flocculation basins where redwood baffles and mechanical vertical flocculators were installed to
help to grow the microfloc. Sediment from the flocculation basin and the filter backwash waste is
piped to a sludge lagoon. After flowing through a flow control box at the end of the flocculation
zone, the water is sent through one of six dual media filters that consist of sand and anthracite coal
layers. There are two additional filter basins that have been abandoned. Each filter is equipped with
automatic rate of flow controller valves. These filters remove remaining particles in the water
before it enters the clearwell. A filter backwash system of tanks and pumps is also included.
Backwash water for the filters is pumped from the clearwell. Beneath the filters, there is an air
scour system and associated equipment. Above the filter gallery, there are administration offices
and a SCADA workstation area.
Solids from the filters are routed to a pond, which is eventually sent to the sewer. After the filters,
product water is flows to the clearwell. After the clearwell, the chlorinated effluent flows to the
downstream Crowson Tank finished water reservoir located off site.
3.1.1 Summary of Existing Plant Evaluation by Discipline
From a broad perspective, the existing WTP is old with outdated facilities, is located in a hazardous
flood and seismic zone, and does not have room to expand to meet future capacity requirements or
the ability to provide additional treatment processes to address potential algal toxins or to fully
remove taste and odor issues.
The current WTP was partially re -built in 1995. From an engineering discipline perspective, the
existing plant contains electrical and control systems that will need replacement or are obsolete, as
well as mechanical equipment that is nearing the end of its useful life. City input regarding
condition, operations and maintenance issues, and recent improvements, was incorporated into
defining the rehabilitation needs. Input from plant staff regarding functional needs was also
evaluated. For example, if equipment requires replacement because it is no longer reliable or no
longer meets functional needs, the rehabilitation needs reflect this input. Since the plant will need
to continue to provide peak capacity into the foreseeable future, many components are slated for
replacement in the 20-year planning horizon.
3.1.1.1 Structural
The concrete observed at the existing plant is performing as expected given its service, usage,
surrounding environment, and age. Deteriorated and corroded concrete was observed. Minor
defects observed included localized concrete spalling, scaling, and cracking.
The structural integrity of the tanks and floors has not yet been compromised due to the
deterioration that has occurred to date. However, concrete degradation will continue to occur and
spread if left unchecked. Potential repair and rehabilitation methods and mitigation strategies
BLACK & VEATCH 1 10
City of Ashland I Water Treatment Plant
Plant Evaluation Report
recommended for further evaluation include: performing localized, partial depth concrete crack
repairs and protective coating systems.
3.1.1.2 Process Mechanical
To meet the criteria of extending the existing plant useful service life by approximately 20-years, it
is recommended that the pumps, gearboxes, and motors be replaced. Based on their assessed
condition and operability, it is recommended that process mechanical valves either be refurbished
or replaced in the 20-year planning horizon.
In general, it is assumed that replacement would be based on equipment types and sizes to match
existing. However, it may be appropriate to replace with a different type of pump, valve or other
equipment to better meet plant requirements or City staff preference. In most cases, replacement
rather than repair of pumps, valves and other equipment is recommended to achieve the objective
of extending service life by 20 years. If an asset is in good condition, and replacement parts are
readily available, refurbishment may be more cost effective than replacement. However, it is
important to also consider the amount of time the equipment can be taken out of service if it is
scheduled for refurbishment.
Process mechanical pipelines were assessed to be in varying condition states. Most piping systems
require attention and improvements. Some extent of piping protective systems, coatings and linings
will be required to extend piping system useful service life by 20-years.
3.1.1.3 Electrical
In general, it was observed that some electrical equipment is not expected to last another 20 years
and is recommended for replacement. Some of the electrical equipment that provides power to
pump motors, valves, instruments, and other process related electrical loads is considered obsolete
and is due for eventual replacement. The equipment includes:
Switchgear and motor control centers
Panelboards
Disconnects
Based on the evaluation, it was observed that the panelboards serving process -related loads had
reached the end of their useful life, with parts becoming difficult, if not impossible, to find.
Therefore, panelboards are assumed to be obsolete and are recommended for replacement.
3.1.1.4 Instrumentation and Controls
The existing equipment will not meet the targeted service life of an additional 20 years. Typical
instrument service life is 15-25 years, which is within the planning timeframe used for
instrumentation components of this assessment and subsequent improvements. Therefore, it is
BLACK & VEATCH 1 11
City of Ashland I Water Treatment Plant
Plant Evaluation Report
recommended that the equipment be replaced. Much of the existing I&C equipment is nearing the
end of its service life or does not meet the desired level of service for I&C equipment.
3.1.2 Facility Evaluation
The inspection of the Ashland Water Treatment Plant relied primarily on visual inspection of the
plant assets, with a particular focus on what it would take to maintain useful plant operation for the
next 20 years. Digital photos of the plant were taken to document asset condition. Because the plant
was in operation during the time of the inspection, the interiors of process structures were not able
to be inspected.
Prior to the inspection, the City of Ashland had sent Black & Veatch information on known
deficiencies, or desired improvements to the site. The following sections describe the observed
condition of each of the process areas of the WTP, and incorporate a description of these known
deficiencies.
3.1.2.1 Administration
The assets within Administration area were generally in good condition. This facility includes the
control room, offices, lockers, and lab, as well as other miscellaneous site civil structures, such as
facility roadways.
The offices were in good condition, with no visible defects, or known issues brought up by the WTP
staff. Within the lab, the sample sink needs to be replaced. The metal shelf stands have begun to
corrode, and the narrow sink might not effectively suit technicians' needs (Photo 3-1). It was
brought up by the City that they would like the shower facilities to be updated in the locker room.
Furthermore, the City voiced a desire to recoat the plant administration building.
BLACK & VEATCH 1 12
City of Ashland I Water Treatment Plant
Plant Evaluation Report
Photo 3-1— Lab in Administration Building Photo 3-2 — Potable Water Storage Tank and Hydro -
Pneumatic Tank
In terms of site civil assets, the plant roadways appeared in good condition, with no visible defects.
However, the City would like for the roads to be improved to accept bulk chemical deliveries. The
current chemical delivery truck is not able to provide reliable deliveries, and newer trucks might
have trouble navigating the roads on site. With geological site constraints caused by the canyon
walls, it is unlikely that the roads will be able to be enlarged enough to accommodate a larger truck.
The potable detention tank is adequate and there were no observable defects. However, the hydro -
pneumatic tank will require eventual replacement in the 20-year planning horizon. A photo of the
potable water storage tank and the hydro -pneumatic tank are above (Photo 3-2). Lastly, there are
several concerns with the safety equipment installed on site. The fire protection system has an
alarm component only and it does not include any fire suppression measures. This system should
be updated to meet NFPA code. There are two emergency eyewash/shower stations on site. They
don't have freeze or scald protector valves installed, which would be recommended as a safety
provision for the WTP staff. An emergency eyewash/shower should also be installed in the chlorine
building (preferably inside the containment area). The WTP staff would currently have to exit the
building and go to the adjacent chemical building to access an emergency eyewash/shower.
The City would like intercom and video feeds throughout the site to record video when the
operators are not on site, as well as a remote controlled electric gate. This would be an optional
improvement recommendation, and not viewed as essential for plant operation for the next 20
years.
3.1.2.2 Plant Influent
The WTP tailrace structure, influent weir, and influent line were all structurally in good condition. It
was noted by the City that there is a desire to be able to actuate the influent weir electronically,
instead of manually adjusting the weir height. Furthermore, the 36-inch butterfly valve on the plant
influent line doesn't close completely or modulate effectively. This should be replaced. Lastly, the
City would like the hydroelectric generator bypass to be redesigned to eliminate vibration issues
BLACK & VEATCH 1 13
City of Ashland I Water Treatment Plant
Plant Evaluation Report
and improve flows. They are currently limited to 5 mgd with this bypass pipe. Photos of the influent
weir and 36-inch butterfly valve are below (Photo 3-3 and Photo 3-4).
Water from the Talent Irrigation District is used to supplement supply during periods of drought or
low water years. A 24-inch steel water pipe feeds the WTP from the Terrace Street Pump Station.
The pipe supports were not closely inspected; however, material under some of the supports
appears to be washing away. Furthermore, when there are high-level flows, the pipe is submerged
in the creek, subjecting it to damage from debris (Photo 3-5).
Photo 3-3 — Influent Weir
Photo 3-5 —Talent Irrigation District Influent Pipeline
3.1.2.3 Chemical Feed
Photo 3-4 — Influent 36-inch Butterfly Valve
The assets within the chemical feed process group were in fair condition. The individual chemical
feed systems are discussed in the sections below. Some of the systems were in better condition than
others, but, generally speaking, it is ultimately recommended to replace the entire Chemical
Building and the equipment inside in the next 20 years.
BLACK & VEATCH 1 14
City of Ashland I Water Treatment Plant
Plant Evaluation Report
Alum Feed
The alum feed system consists of one alum tank, two alum feed pumps, and two alum feed motors.
The new chemical building was built around the existing alum tank, with little regard given to tank
replacement or maintenance (Photo 3-6). It was reported to Black & Veatch that the transducer
located in the tank isn't functioning. However, to replace this transducer, the tank top would need
to be removed, and there is limited space within the chemical building to perform this work.
Additionally, if the tank were ever needed to be replaced, the building and second floor would likely
have to be modified to accommodate this work.
The older auto diaphragm feeder pump was replaced with a peristaltic pump 2 years ago, and the
City is very satisfied with the performance (Photo 3-7). However, the older pump can only be
manually operated and replacement should be considered.
Photo 3-6 — Top of Alum Tank Photo 3-7 — Base and Pedestal of Alum Tank
Soda Ash
The solution tank, hopper, storage tanks, feed pumps, and feed motors are all part of the soda ash
system. The soda ash is used to maintain or adjust pH for finished water, and the City has
mentioned that they would like to develop an improved caustic soda feed system to replace the
BLACK & VEATCH I 15
City of Ashland I Water Treatment Plant Plant Evaluation Report
current one. The current system is functional, and there weren't any visible defects. However, the
age and efficacy of the system should be taken into consideration, and B&V concurs with the City
that the system should be replaced in the next 10 years. The current system will be unable to meet
any future higher pH requirements. Furthermore, the lower level of the chemical building is
susceptible to flooding. Photos of the soda ash system are below (Photo 3-8 and Photo 3-9).
Photo 3-8 — Soda Ash Hopper Photo 3-9 — Soda Ash Hopper, Dissolving Tank, and
Metering Pumps
Powdered Activated Carbon (PAC)
The PAC hopper, auger feed and motor, and an educator make up the PAC feed system (Photo 3-10).
Similar to the Soda Ash system, the PAC system is susceptible to flooding since part of the hopper is
located on the lower level of the chemical building. There were no significant observable defects
with the PAC system. However, the PAC system does not meet the desired level of service, and has
not been effectively treating taste and odor during high Geosmin events. Furthermore, handling
PAC can pose a health risk. The MSDS lists that the primary concerns for occupational exposure are
skin contact and inhalation in the form of dust. The dust may cause eye irritation, slight skin
irritation, and possible respiratory tract irritation. In confined spaces, it can adsorb oxygen, and
asphyxiation may result. The dust from loading PAC can also lead to an explosive environment. It is
recommended that this system be replaced in the 10- to 1S-year timeframe.
BLACK & VEATCH 1 16
City of Ashland I Water Treatment Plant
Plant Evaluation Report
Photo 3-10 — Powdered Activated Carbon Hopper
Potassium Permanganate (KMn04)
The potassium permanganate system is comprised of the hopper, auger feeder and motor and an
educator feed system. It is located on the lower level of the new chemical building, which is prone
to flooding. It has been noted by the City that the KMn04 system does not meet the desired level of
service, and has not been effective at treating taste and odor during high geosmin events. It is
recommended to replace the potassium permanganate system altogether, either with a newer feed
system, or with a better oxidation system.
Polymer
The polymer system is comprised of two tanks, filter polymer aid (Superfloc N-300) feed pumps
and motors, and cationic polymer (Superfloc C-573) feed pumps. Overall there were no significant
visible defects detected with the polymer feed system. There are no visible defects with the LMI
Polymax feed system. However, the City is hoping to upgrade the current cationic polymer
diaphragm feed pump with a peristaltic pump. At this time, they would also like to reevaluate
alternate injection points other than mixer M015. Due to lifespan expectancy, it is recommended to
replace this system in the next 10 years. The filter polymer aid system is functional, but obsolete.
The City has also reported that it delivers polymer aid unevenly to the filter surfaces. It is
BLACK & VEATCH 1 17
City of Ashland ! Water Treatment Plant
Plant Evaluation Report
recommended to replace this system in the next 10 years. The tanks for the polymer feed and
mixing are functional and should be used until the end of their useful life. However, the City has
stated that functionally only a third (approximately 33 gallons) of the working capacity of each tank
are able to be used. In the 10- to 15-year timeframe, the current tanks should be replaced with
smaller, more adequately sized tanks. The City currently has planned replacements for both
polymer systems budgeted. Photos of the polymer system are below.
Photo 3-11— Filter Polymer Aid Hopper and Mixing
Tank
Photo 3-13 — Cationic Polymer Feeder
Photo 3-12 — Filter Polymer Aid Feed Tanks
BLACK & VEATCH 1 18
City of Ashland I Water Treatment Plant
Plant Evaluation Report
Hynochlorite
One 3,000-gallon tank and three feed pumps make up the hypochlorite system. The current tank
was installed in 2008 and is nearing the end of its life (Photo 3-14). It is recommended to replace
the tank in the next 10 years. As seen in the photo below, there is corrosion near the floor on some
of the concrete masonry unit (CMU) bracing angles, mostly likely due to sodium hypochlorite
contact (Photo 3-15). If the CMU blocks are not internally reinforced, this corrosion could
ultimately weaken the structure. For this reason, when the tank is replaced, this will trigger
removal of the containment basin and a major building demolition and renovation due to structural
and safety considerations. The City has also voiced that they would like bulk chemical delivery if
possible. This is not feasible at the existing facility. Bulk deliveries would require construction of a
transfer station on the plant access road downhill from the existing plant with pumps and piping
installed to supply the tanks at the plant.
The City has reported that there are signal issues with some of the sodium hypochlorite feed
pumps. Pump #2 has frequent operational issues, and Pump #3 has communication issues with the
SCADA. It is recommended to replace these pumps in the next 10 years.
The hoist in the Chlorine Building appeared in good condition with no observable defects. Due to its
useful life estimate, the hoist will likely require replacement in 10-15 years.
BLACK & VEATCH 1 19
City of Ashland I Water Treatment Plant
Plant Evaluation Report
Photo 3-14 — Sodium Hypochlorite Tank and Hoist Photo 3-15 — Corrosion in Chlorine Building
Miscellaneous
There are several miscellaneous components to the chemical feed process that are discussed in the
list below. All replacements are suggested to occur in the next 10 years.
Due to flooding concerns, and seismic events, the existing Chemical Building is a liability, and is
recommended to be replaced in the next 10 years.
The chemical feed piping is in good physical condition. However, reconfiguring the piping is
recommended to add more injection points.
■ The chemical feed flow indicators are not functioning correctly and require replacement.
■ It is recommended to upgrade all pumps to peristaltic pumps. This upgrade will render many of
the valves unnecessary, ultimately creating fewer assets for the City to manage.
Motor actuators for valves are recommended to be replaced.
■ The mixer appears in good physical condition. However, it is in a corrosive, continuous -duty
environment, and it is also recommended to be replaced.
Lastly, the sump pumps are currently adequate, and appear in good physical condition. However,
they will near the end of their useful life in the 10- to 15-year range, and are recommended to be
replace in that window.
BLACK & VEATCH 1 20
City of Ashland I Water Treatment Plant Plant Evaluation Report
3.1.2.4 Pretreatment
The Pretreatment process is made up primarily of the Flocculation Basins. During the inspection, it
was observed that the Flocculation Basin structures were in good condition. However, it is
recommended that they be recoated within the next 10 years to preserve concrete integrity. The
City has mentioned that they would like to upsize and relocate the drain, as it is currently not at the
bottom of the basin. Upsizing and relocating the flocculation basin drain would trigger major
structural modifications, and this recommendation should be considered optional. It was also
reported by the City that there has been hydraulic short-circuiting in the Flocculation Basins. Black
& Veatch would recommend rewiring the flocculation motors to spin in the opposite direction and
disassembling and reversing the vertical paddle mixers to improve settlement (Photo 3-16). This
should be done in the next 10 years.
The Flow Control Box Structure is in good condition structurally, but it is undersized, and it is
doubtful that it would be able to handle peak flows of 7.5 mgd (Photo 3-17). Structural
modifications to enlarge the overflow drainage box are recommended, including upsizing the drain
piping and fixing the slide gate. This is recommended to be constructed in the next 10 years. Lastly,
as an optional improvement, underwater lights could be installed in the basin for enhancing
visualization of floc flow patterns.
Photo 3-16 — Flocculation Basin and Paddle Mixer
3.1.2.5 Dual Media Filters
Photo 3-17 — Grating Above Overflow Box
The Dual Media Filters were in fair condition (Photo 3-18). There is evidence of cracking within the
filter structures, and possible leakage, visible from the efflorescence on the exterior of the filter
concrete wall and from the leakage pattern staining around the air supply line on the exterior wall
(Photo 3-20 and Photo 3-21). The coating is also failing in some areas. Concrete cracks should be
repaired, and the filter basins should be recoated in the next 10 years. The City has mentioned that
excessive debris falls into the basins during normal operation, affecting filter performance. Recent
BLACK & VEATCH 1 21
City of Ashland I Water Treatment Plant Plant Evaluation Report
removal of overhanging trees has improved this situation. While not necessary for proper operation
of the plant, a canopy structure over the Dual Media Filters would be considered an optional
improvement to the plant to prevent the debris entering the filters. Filters 7 and 8 are currently not
operational, and it is recommended to rehabilitate these filters in the 10- to 15-year timeframe to
meet future treatment process demand (Photo 3-19). Rehabilitation would require concrete crack
repair and surface restoration in addition to replacement of process mechanical equipment,
launders and piping penetrations. In the same time frame, it is expected that existing filter media
will reach the end of its useful life, and should be replaced. The filter influent pipe showed some
signs of surface corrosion, and it should be recoated in the 10- to 15-year timeframe as well. When
this effort is undertaken, it is recommended to perform a detailed condition assessment of the pipe.
The backwash pumps were in good condition, with no major observable defects detected. However,
they are near the end of their useful life, and will require a major overhaul or should be replaced in
the next 10 years. The backwash pump flow meters and instrumentation should also be replaced in
the next 10 years. The backwash piping should be recoated and inspected for integrity during this
same time. The backwash lagoon is expected to need cleaning in the next 20 years, and the
backwash water samplers will also likely need to be replaced during this time. The City would like
to remove the original steel backwash tanks on the slope above the WTP, which are no longer in
use. These tanks present a dangerous risk to the facility if they were to fall. Although not critical to
continued plant operation, removal of the steel backwash tanks should be considered.
There were no notable defects with the blower motor. However, it is subject to major overhaul or
replacement due to reaching asset life expectancy during the 20-year planning horizon. This would
occur in the 10- to 15-year timeframe. Similarly, the process air valves would need to be replaced in
this same time frame.
Photo 3-18 — Dual Media Filters
Photo 3-19 —Abandoned Dual Media Filter #7
BLACK & VEATCH 1 22
City of Ashland I Water Treatment Plant
Plant Evaluation Report
Photo 3-20 — Air Scour Air Supply (Evident Leakage)
Photo 3-21— Efflorescence on Exterior Dual Media
Filter Wall
3.1.2.6 Clearwell / Product Water
The Clearwell is a concrete tank located beneath the Backwash Pump Station. It was not physically
able to be inspected, but the City informed Black & Veatch of operational issues related to the tank.
The sealing material on the cold joints within the Clearwell are deteriorating, and should be re -
caulked in the next 10 years. There are currently dead zones within the Clearwell resulting from
poor dispersion of the sodium hypochlorite. It is recommended to improve delivery piping to
improve dispersion within the Clearwell in the next 10 years. The City would like to add a drain
pipe from the Clearwell to the sludge pond or plant sewer drain. However, Black & Veatch considers
this an optional recommendation and not necessary for continued plant operation. The Clearwell
sample pump should also be changed to a peristaltic type in the next 10 years to prevent loss of
prime. It is recommended that the contact basin drain valves and slide gate be replaced, as the City
reports that they currently leak.
The plant has a potable water system to serve the plant water needs (drinking water, restrooms,
chemical feed systems etc.). Currently, the potable water pump suction line isn't accessible without
entering the Clearwell, and it is recommended to reroute the piping to be able to replace the foot
valve at some point. Furthermore, the potable water pumps will most likely have to be replaced in
the 20-year planning horizon.
BLACK & VEATCH 1 23
City of Ashland I Water Treatment Plant
Plant Evaluation Report
3.1.2.7 Electrical
Electrical equipment was visually inspected while the plant was in operation; because of safety
considerations, none of the cabinets were opened. Black & Veatch relied on information from the
plant operators to make plant improvement recommendations. The plant generators are currently
adequate, and no observable defects were detected. However, it is expected that the generators will
require a major overhaul or need to be replaced during the next 20 years. Similarly, transformers,
MCCs, breakers, cabling, and power lines were all in good condition, but will likely need to be
replaced in the next 20 years. The building and yard lighting should also be replaced with LEDs as
the existing lighting fixtures are considered to be economically obsolete. The photos of the
electrical equipment shows arc -flash related labels/stickers which would indicate that at some
point, an arc -flash analysis or study was conducted. NFPA 70-E guidelines stipulate that an arc -flash
analysis be conducted every five years. Representative photos of electrical equipment are below.
Photo 3-22 — Motor Control Center
3.1.2.8 Instrumentation & Control
Photo 3-23 — Potable Water Pump Disconnects
Similar to the electrical assets, Black & Veatch relied on the plant operators to make improvement
recommendations for I&C equipment. Instruments typically have a 10- to 20-year lifespan, so there
are many instruments that will need to be replaced in the next 20 years. Specifically, the
Flocculation Basin level sensor should be replaced in the 10- to 15-year timeframe. The following
recommendations should all be addressed in the next 10 years:
Plant -wide, the City would like to update the SCADA system and PLC telemetry to provide
pressure and flow indication for plant water supply. The telemetry unit should also be relocated.
In -line pH probes were in good condition, but will need replacement at the end of their useful life.
Recommended to move the streaming current detector to the lower chemical room for faster
response time. The instrument will also need to be replaced near the end of its life expectancy.
■ Flowmeters were in good condition, but will need replacement at the end of their useful life.
■ Turbidity meters were in good condition, but will need replacement at the end of their useful life.
■ It is recommended to add a TOC in -line analyzer.
BLACK & VEATCH 1 24
City of Ashland I Water Treatment Plant Plant Evaluation Report
Inflow meters should be replaced as they are nearing the end of their life expectancy.
The WTP finished water effluent pipe empties as it flows to Crowson Tank during filter
backwashes, resulting from inaccurate measurements. It is recommended to relocate the plant
effluent flowmeter 1000-yards farther downstream to provide more accurate information.
Upgrade Wonderware software on plant computers.
Representative photos of instruments are below.
11
Photo 3-24 — Dual Media Filter #1 Turbidity Meter
3.1.3 Asset Life Expectancies
Photo 3-25 — PLC Telemetry Unit
The age of an asset, together with its typical useful life, is an important characteristic used to assess
an asset's condition. Because the actual installation date of most of the existing facility assets is
unknown, the assumption of asset age was based on available drawings, field observations or staff
input. Where assets appeared near or beyond their expected life, this factored into developing the
rehabilitation needs. Assets that have exceeded their useful life are generally recommended for
overhaul or replacement. Table 3-1 provides guidelines on typical life expectancies for plant assets.
Table 3-1 Asset Effective Life Expectancies
Civil structures
50-75
Pressure piping
60
Gravity pipelines
100
Pumps
40
Valves
30
Mechanical Systems / Motors
25-35
Electrical Systems / Components
30
Instrumentation and Controls
15-25
Building assets 30
BLACK & VEATCH 1 25
City of Ashland I Water Treatment Plant
Plant Evaluation Report
3.1.4 Planning Horizon
This study needs to address reliable operation of the plant into the future based on a criterion set
by the City for extending the remaining useful service life of the existing facilities by an estimated
20 years. The assumption is the existing plant would be required to remain operational for the next
20 years with no significant changes in its current treatment configuration. After this time, the
existing plant may be decommissioned and replaced by a new plant. The assessment identified not
only improvements required in the near term based on current condition, but also those
improvements needed to maintain reliable operation over the 20-year planning horizon. Therefore,
forward forecasts on replacement needs were developed for those assets that may not currently
need work. For example, a motor that was very recently overhauled does not currently need work.
However, the next improvement cycle, which may be in 15 years, has been included in the cost
forecast.
3.2 NEW WATER TREATMENT FACILITY
This section presents the basis for developing a conceptual cost for constructing a 7.5 mgd new
water treatment plant. The cost presented is an AACE Level 5 construction cost (with an accuracy
range of -50% to +100%). The assumptions used to develop the conceptual cost are presented
below.
3.2.1 Site and Hydraulics Considerations
The site identified to construct a new plant is located a couple of miles downstream of the existing
plant site. The elevation of this site is lower than the existing plant site. This elevation difference
would allow gravity flow of raw water into the new plant. However, because the new site is at a
lower elevation, gravity flow of treated water into the existing downstream reservoir may not be
possible. Additional analysis is warranted to confirm that gravity flow from the plant to the
distribution system is not possible. It is envisioned that a part of the existing treated water pipeline
from the existing plant could potentially be converted to convey raw water to the new treatment
plant. Additional piping would be required to convey raw water to the plant site and treated water
from the plant site to connect to the existing pipeline feeding the downstream reservoir.
The site is relatively flat with sufficient area to house the treatment facilities and auxiliary
structures. Moderate site work would be needed construct the new treatment plant facilities.
3.2.2 Treatment Process Considerations
To provide a direct cost comparison with the existing plant, it is assumed that the new plant will
employ the same treatment processes and chemical feed systems as the existing plant. These will
include:
A microfloc filtration plant that will employ in -line rapid mixing, flocculation followed by media
filtration consisting of dual media filters
BLACK & VEATCH 1 26
City of Ashland I Water Treatment Plant Plant Evaluation Report
Chemical systems will include PAC, Alum, KMn04, soda ash, coagulant aid polymer, filter aid
polymer and chlorine (12.5% sodium hypochlorite),It is assumed that the chemical systems
(storage and feed systems) will be located indoors
Administration building will be included to house offices/laboratory, electrical switchgear, as
well as SCADA workstations
3.2.3 Cost Considerations
The conceptual costs for a new 7.5 mgd capacity plant that employs the same treatment processes
as the existing plant are presented under Section 4. It should be noted that the costs associated with
raw and finished water piping and a small filter effluent wetwell with associated high service
pumps should be considered because these components will likely be required with the operation
of the new plant. For planning purposes, it is assumed that approximately 0.25 mile of raw water
piping and 0.25 mile of treated water piping would need to be constructed.
BLACK & VEATCH 1 27
City of Ashland I Water Treatment Plant
Plant Evaluation Report
4.0 Cost Comparisons
Total life -cycle cost is evaluated based on the addition of the life -cycle 0&M to the total project cost.
The total life -cycle costs were developed for an equivalent 7.5 MGD WTP. This cost represents the
total cost of ownership of the plant at the end of 20 years normalized to today's dollars.
The estimates presented in this report are order -of -magnitude estimates as defined by the
Association for the Advancement of Cost Estimating (AACE). Typically, an order -of -magnitude
estimate is expected be accurate within plus 100% to minus 50% of the estimated cost. Cost
estimates are considered AACE Level Class 5 prepared with 0% to 2% project definition to be used
as a general guideline for more specific and detailed studies.
The developed estimates have been prepared for guidance in evaluating the cost of maintaining the
existing plant versus constructing a new plant. These cost estimates are derived from the
information available at the time of the estimate. Detailed project costs will certainly depend on
actual labor and material costs, competitive market conditions, final project costs, implementation
schedule, and other variable factors. As a result, the actual costs can be expected to vary from the
estimates presented herein.
There is a substantial amount of uncertainty in the opinions of probable construction cost,
particularly with site development. Thus, the site considerations have been removed from this
evaluation.
4.1 COST CATEGORIES
Order -of -magnitude estimates of costs (in 2018 dollars) were developed for plant rehabilitation.
The cost estimates are comprised of several components described in this section:
Equipment -specific improvement construction costs
Rehabilitation costs based on site visit, industry knowledge and previous reports
Cost allowances and contingencies
4.1.1 Equipment -Specific Construction Costs
To the extent possible, construction costs for equipment repairs, overhauls and replacements were
developed. These costs represent installed costs, including purchase of equipment and labor to
install. This methodology was implemented for expediency, as the project budget and schedule did
not allow for development of construction cost estimates for each individual asset.
Asset replacement costs from equipment inventories from other projects were used as a starting
point for determining the cost data. Typically, general equipment specifications (e.g. motor hp,
valve size, etc.) would be used to assign replacement costs to individual assets. As this information
was not readily available, replacement costs were assigned based on comparable equipment
BLACK & VEATCH 1 28
City of Ashland ( Water Treatment Plant Plant Evaluation Report
application and assumed size ranges. This approach represents a rapid means of compiling cost
estimates. A more detailed approach, such as assigning replacement costs based on nameplate data
for individual assets may be recommended for the future.
4.1.2 Rehabilitation Costs
Rehabilitation costs for the existing facility were based on results from site visit as well as Black &
Veatch's knowledge and experience with similar projects across the United States. The
rehabilitation recommendations and associated cost estimates are tabulated for reference in
Attachment A.
4.1.3 Cost Factors and Contingencies
A number of cost factors, allowances and contingencies were applied to the construction costs to
estimate an opinion for the total probable plant rehabilitation cost. These factors account for the
conceptual nature of the base construction costs, project costs such as engineering, and escalation.
The cost factors were applied consistent with industry assumptions. Table 4-1 describes the cost
factors applied.
Table 4-1 Cost Factors to Develop Total Project Costs
Site Work (misc. costs)
8%
On Constr. Cost
1.08
Yard Piping
9%
1.17
Electrical
10%
1.27
Instrumentation and Controls
2.5%
1.30
Estimating Contingency
15%
On Total Const.
1.49
Contractor Mark Up Costs (Cumulative)
24%
On Total Const.
1.85
Overhead
7%
+ Contingency
Profit
10%
Mobilization/Bonds/Insurance
3%
Contingency
4%
Planning, engineering, and const. management
48% 2.74
Permitting
1%
Environmental Review
1%
Public Outreach
1%
Engineering design
8%
Engineering costs during construction
2%
Const. management services
7%
Commissioning/Startup
3%
City costs
5%
Construction change order allowance
5%
Contingency
15%
Escalation
2% 10% 2.84
Final Factor 2.84
BLACK & VEATCH 1 29
City of Ashland I Water Treatment Plant
Plant Evaluation Report
Costs presented in this table include contingencies (30% for estimating and non -construction
related costs) and other soft costs (33% for planning, engineering, and const. management). The
final project cost factor represents the cumulative cost percentages and is useful in comparing
construction costs and overall project costs.
A cost escalation of 2% per year over year has been assumed. It is anticipated that the escalation
would be applied to represent the costs at the time of construction. It is conceivable that a new
treatment plant would be constructed within the next 10 years. Thus, a mid -point in construction
escalation of 5 years is assumed to arrive at the escalation allowance of 10%. By comparison to the
existing plant rehabilitation needs, it is estimated that many of the recommended actions are also
grouped in the 0- to10-year time frame for implementation. This is further described in the next
section (Section 4.2). Thus, the same cost escalation factor would be applied for the existing plant
rehabilitation needs.
4.2 PRIORITIZATION OF IMPROVEMENTS
Rehabilitation recommendations were organized with both short-term (immediate repair and
replacement activities) and long-term replacement needs. The City may continue to replace or
rehabilitate existing plant assets aligned with real time conditions at the plant. Refinements were
made to the rehabilitation recommendation time frames to maximize the remaining useful life of
the existing facilities.
Rehabilitation recommendations for each subsystem are assigned a timeframe for implementation
to ensure continuous and reliable operation. The timeframe considers the typical useful life of a
given asset, its current condition, the service date, and City staff input.
Rehabilitation needs were developed at the asset level and summarized at the subsystem level. The
recommendations and timeframe for improvements are presented at the subsystem level with the
anticipation that improvements for all assets within a subsystem would occur within the same
timeframe for cost efficiencies and to reduce impacts to plant operations.
Recommendations are presented with a proposed timeframe for implementation such that budget
plans can be developed. Each recommendation is placed into one of three timing phases: short-term
(0 to 10 years), mid-term (10 to 15 years), and long-term (15 to 20 years). The overall summary of
the rehabilitation recommendations show that the majority of the work needs to be performed in
the short-term as demonstrated in Figure 4-1.
BLACK & VEATCH 1 30
City of Ashland I Water Treatment Plant
Plant Evaluation Report
1%
Figure 4-1 Itemization of Rehabilitation Cost Allocations Over Time
Implementation
Timeframe
■ 0-10
■ 10-15
■ 15-20
Figure 4-1 shows that approximately 72% of the rehabilitation needs are recommended to be
performed in the short-term time frame. The graphic also shows that only a very small percentage
of rehabilitation work (1%) could be performed at the end of the 20-year planning horizon. Some
realignment of the timing intervals can be considered if asset run -to -failure strategies are
employed. Although this strategy would only be viable if a new plant was ultimately decided as the
City's future direction.
4.3 SUMMARY
The cost comparisons are provided for construction of a new plant versus the rehabilitation
recommendations for the existing plant. The costs are organized in the following categories:
Administration Plant Influent Chemical Feed Flocculation Basins
Dual Media Filters Clearwell / Electrical Instrumentation
Product Water & Controls
Costs were developed for the necessary rehabilitation required for the existing plant. The
rehabilitation recommendations and associated cost estimates are provided in Attachment A. These
costs were then grouped in the respective categories outlined above. Table 4-2 shows the
comparative capital costs for the existing plant and a new 7.5 mgd capacity plant. Note the sub total
amounts have been rounded to the nearest $1,000 dollars.
BLACK & VEATCH 1 31
City of Ashland I Water Treatment Plant Plant Evaluation Report
Table 4-2 Capital Cost Comparisons
Flocculation Basins
$1,330,000
$472,000
Dual Media Filters
$3,637,000
$702,000
Chemical Feed
$923,000
$878,000
Administration
$1,000,000
$181,000
Plant Influent (Existing WTP) & Offsite Inf/Eff. Piping (New WTP)1
$550,000
$20,000
Clearwell/Product Water
$347,000
$83,000
High Service Pumps2
$400,000
Site Work
$645,000
Yard Piping
$725,000
Electrical
$806,000
$186,000
Instrumentation & Controls
$201,000
$128,000
Estimating Contingency (15%)
$1,584,000
$397,500
Total Facility Cost
$12,148,000
$3,047,500
Contractor Mark Up Costs (Cumulative)
Overhead (7%)
$850,000
$213,325
Profit (10%)
$1,214,000
$304,750
Mobilization/Bonds/Insurance (3%)
$365,000
$91,425
Contingency (4%)
$486,000
$121,900
Total Contractor Markups $2,915,000
$731,400
Subtotal Construction Cost $15,063,000
$3,778,900
Non -Construction Costs (Additive)
Permitting (1%)
$150,000
$37,789
Environmental Review (1%)
$150,000
N/A
Public Outreach (1%)
$150,000
N/A
Engineering (8%)
$1,200,000
$302,312
Legal/Administration (0.5%)
$75,000
N/A
Construction Services (7%)
$1,050,000
$264,523
Commissioning/Startup (3%)
$450,000
$113,367
Contingency (15%)
$2,250,000
$566,835
Total Non -Construction Costs
$5,475,000
$1,284,826
Escalation (2%/yr. @ 5 yrs. = 10%)
$2,053,000
$506,373
Total Project Cost
$22,591,000
$5,570,099
Total Project Cost (Rounded to nearest $1000)
$22,591,000
$5,570,000
1 Refer to Section 3.2.3. The length of influent and effluent piping used for cost estimating is 0.25 mile each.
2 A finished water pumping station for the new plant site is expected to send flow to the downstream reservoir.
BLACK & VEATCH 1 32
City of Ashland I Water Treatment Plant Plant Evaluation Report
It should be noted in the above table that some costs are not applicable to rehabilitation of the
existing plant. Non -construction related costs associated with environmental review, public
outreach and legal/administrative functions are not expected to be incurred on the existing plant.
As such these cost assumptions for non -construction are provided for reference as they apply to the
new plant for comparison purposes but have not been included in the total project cost for a new
plant.
Based on the comparison table the following trends are evident. Overall rehabilitation costs for the
existing facility are approximately 25% of the construction costs of a new plant. Within the
individual facility areas, the improvement cost for the existing chemical feed is nearly equivalent to
the construction costs of a chemical feed area in a new facility. This intuitively reinforces the results
of the existing plant evaluation as the chemical feed area was noted to require the most extensive
amount of rehabilitation. Additionally, the rehabilitation costs associated with Instrumentation &
Controls are also 64% of the new I&C plant construction cost. The City has kept up with upgrades of
I&C equipment over time and these ongoing costs are expected going forward with the 20-year
planning horizon of the existing facility as the life expectancy of these systems is shorter than other
asset types.
From a broad perspective, it is feasible to continue to utilize the existing facility over the 20-year
planning horizon at a lower initial investment than constructing a new treatment plant. For the
purposes of this analysis, all efforts have been made to provide an equivalent cost comparison
between the existing facility rehabilitation requirements to the construction costs associated with
an equivalent new facility.
4.3.1 Additional Considerations
The capital cost comparison has worked toward providing an equivalent comparison between the
two primary alternatives of rehabilitating the existing plant and constructing a new plant. However,
it is prudent to provide discussion on the additional factors that should be included for the City's
consideration. Follow up studies to further vet these considerations, including performing business
case evaluations that factor in the importance of economic and non -economic factors should be
performed. For brevity, the following table (Table 4-3) provides some of the additional
considerations that may have either positive or negative impacts associated with either alternative.
General discussions of these considerations are provided following the table. The potential impacts
of these issues can be rated by the City according to their importance in a triple bottom line analysis
that considers social, environmental and financial factors.
BLACK & VEATCH 1 33
City of Ashland I Water Treatment Plant
Plant Evaluation Report
Table 4-3 Considerations with Positive/Negative Impacts
Additional Rehabilitation Needs -
+
Flood Risks -
+
Seismic Risk -
+
Operation Costs +
-
Maintenance Costs -
+
Treatment Requirements -
+
Capacity -
+
4.3.1.1 Additional Rehabilitation Needs
It should be noted that the rehabilitation needs were based on a cursory site assessment and that
the actual extent of rehabilitation could be greater than what was identified based on visual
inspection and input from operations staff. Based on the limited extent of inspection information
available, this consideration could negatively impact the existing plant alternative as actual
rehabilitation costs could be higher than anticipated.
4.3.1.2 Flood Risks
The existing plant is subject to flooding from the adjacent Ashland Creek. The existing plant has
flooded on multiple occasions. Flooding presents a risk to the reliable operation of the existing
facility. The impacts of flooding damage to the existing plant and the cost to mitigate flooding
cannot be well quantified. It is recommended the City evaluate the acceptable risk tolerance for
flooding impacts in the decision for rehabilitating the existing facility or construction of a new
plant. A new plant would be located in an area less prone to flooding and thus has a positive
contribution as compared to that of rehabilitating the existing facility.
Costs to construct a flood wall to mitigate flooding are provided in the City's WCRS & CWMP report
prepared by Carollo. The report indicates the direct costs for construction of the flood wall are
estimated at $1 Million dollars in 2010. The present cost of the flood wall in 2018 is $1.21 Million
dollars using Engineering News Record average construction cost indices for present day
adjustments. When applying the 2.84 cost factor developed in Section 4.1.21 the total present day
project costs for the flood wall are estimated at $3.44 Million dollars.
The flood risk could potentially be mitigated by constructing a flood wall; however, its ability to
withstand a major flood event is questionable. Constructing a flood wall next to existing basins and
structures along the creek is risky because it could potentially damage the existing facilities due to
BLACK & VEATCH 1 34
City of Ashland j Water Treatment Plant
Plant Evaluation Report
vibration related to construction activities. As such, the cost to mitigate the flood risk cannot be
determined with reasonable certainty and therefore not included in the cost comparison.
4.3.1.3 Seismic and Landslide Risks
The existing plant is vulnerable to failure from a seismic event. Rehabilitation recommendations
presented in Table 4.2 do not reflect the costs to upgrade the existing facilities to current seismic
standards. The original existing structures built in 1948 are lightly reinforced compared to the
current ACI 350 requirements. Upgrades to the WTP structures have been performed since original
construction. In general, an increase in the gravity loads by more than 5 percent from the original
design would typically require a seismic upgrade to the current code standards. It is unclear if the
previous upgrades resulted in the seismic resiliency improvements. Furthermore, any vibration or
construction activity around these structures (e.g. construction of a flood wall next to the
flocculation tanks and filter cells) could potentially result in concrete cracking and leakage. A
detailed structural assessment of the existing structures is outside the scope of this document;
however, a cursory review indicates that the existing structures do not meet the current seismic
code requirements. Assuming that the current loading on the existing structures remains the same,
it is not required to upgrade the existing structures to meet the current seismic codes. However, in
a seismic event, these structures could suffer significant damage and impair the ability of the plant
to produce potable water. Due to the age and condition of the facilities it is not feasible to upgrade
the existing structures to current seismic standards in a cost effective manner. Depending on the
severity of a seismic event, the time to repair and make the plant functional could range from days
to months.
In its current location in the canyon, the existing plant is susceptible to damage from landslides.
Similar to the seismic risk, the extent of damage that the plant could suffer will depend on the
severity of a landslide event.
4.3.1.4 Operational Costs
Currently the existing plant benefits from gravity flow conditions which reduce operational costs
associated with influent or effluent pumping. Proposed locations downstream may result in a new
plant requiring some final effluent pumping to send treated water to the distribution system.
Capital costs for a final effluent high -service pumping station have been estimated at $400,000 as
presented in Table 4-2. The City would need to consider the additional operating costs of this
facility as part of the new treatment plant design.
Furthermore, increased pumping costs and operational costs can be expected with enhanced
treatment technologies (such as micro filtration, ozone or ultraviolet disinfection), should the City
decide to employ these technologies in order to fully address the current taste and odor issues,
future algal toxin treatment or other regulatory requirements. These costs are expected to be
BLACK & VEATCH 1 35
City of Ashland I Water Treatment Plant
Plant Evaluation Report
similar for both alternatives (existing plant vs new plant). Due to lack of space, it is envisioned that
these facilities would need to be located offsite.
With new treatment technologies, it can be expected that some labor costs could increase. These
may be partially offset through enhanced automation of the new facility which would require less
staff oversight and control. The lower operational costs would seem to be a benefit for continued
use of the existing plant. The possible opportunities for reducing operational costs at a new plant
may make this consideration neutral between the two alternatives. Regardless of the result,
additional financial analysis for operational costs should be undertaken as part of the pre -design
effort for a new plant and included in the decision making process for alternatives.
4.3.1.5 Maintenance Costs
As opposed to the operational costs, the reduced maintenance costs would favor the new plant.
Currently the City spends a greater extent of time and resources in maintaining the existing plant. A
new facility would diminish the maintenance costs. Initially the new plant would incur low
maintenance costs. Over time with any facility, routine maintenance is expected. The benefit for
reduced maintenance of the new facility may only extend during the initial start-up, commissioning
and warranty period of the new plant. Thus after this time, it can be expected that maintenance on
the new facility would be somewhat comparable to the existing facility. However, the existing plant
continues to age and will certainly require an increasing amount of maintenance over the 20-year
planning horizon.
Situations can occur, such as at the existing facility, where maintenance activities are deferred. This
can create a backlog of maintenance to restore the facility to suitable operating conditions. It should
be noted that if a new plant is ultimately on the horizon for the City, the City may elect to defer
maintenance in a strategy to run assets to failure. This strategy is not necessarily advisable for any
assets critical to plant operation but could potentially reduce the City's cumulative investment in
the existing plant.
4.3.1.6 Treatment Requirements
The existing plant is able to produce high quality drinking water using the current
microfloc/filtration treatment process. It is currently unknown if additional treatment would be
required by EPA as the regulations evolve in the future. However, due to lack of space, it is not
possible to construct additional treatment processes or modify existing facilities to accommodate
new treatment while keeping the plant in operation. Additionally, exposure of new facilities to
other risks (flooding, seismic, landslide) cannot be practically mitigated. As such, the existing plant
does not have the ability to meet any additional treatment requirements such as treatment of algal
toxins, if required by future regulations. Any additional treatment would need to be located offsite
and would require associated infrastructure investment for pumps, piping, and storage to convey to
the distribution system.
BLACK & VEATCH 1 36
City of Ashland I Water Treatment Plant
Plant Evaluation Report
4.3.1.7 Capacity Requirements
Projections for water treatment capacity needs for the City of Ashland have been prepared under
previous master planning efforts. It is beyond the scope of this study to consider future capacity
requirements. Hence, the comparison between the existing plant and the new plant only considers
the current fixed water treatment capacity of 7.5 mgd. When considering the future capacity
requirements, the existing plant may be able to be marginally expanded by rehabilitating the two
abandoned filter basins (Filters #7 and #8) and returning these to service. Additionally, the City has
redundant provisions for treated water supply from the TAP pipeline for up to 2.1 mgd (City's
current water rights). However, the current understanding is that this pipeline is for emergency use
and not intended to provide drinking water supply for an extended period of time to the City. The
benefit when considering future capacity requirements clearly favors the construction of a new
facility that by design could be made expandable to accommodate future capacity requirements.
4.4 CONCLUSIONS
A summary of cost comparisons show that rehabilitation costs for the existing facility are
approximately 25% of the construction costs of a new plant. While it is feasible to continue
operating the existing facility over the 20-year planning horizon at a lower initial investment, the
existing plant has some negative considerations that present a risk to continued operation. The City
has the opportunity to accept or mitigate these risks in the decision process. Ultimately, the existing
facility has a definitive life span and will reach a point where continual investment is no longer
financially prudent or will not achieve the desired level of service for the City. Deferring
construction of a new plant beyond the 20-year planning horizon will impose a greater overall cost
to the City.
BLACK & VEATCH 1 37
01
Memo
Date: Friday, September 18, 2020
Project: City of Ashland, OR 7.5 MGD Water Treatment Plant Final Design
To: Scott Fleury, Kevin Caldwell
From: Pierre Kwan, P.E.; Verena Winter, P.E.; Katie Walker, P.E.; Harshit Joshi, EIT
Subject: Revised Plant Capacity TM (UPDATED)
Introduction
The City of Ashland (City) is currently designing a new water treatment plant (WTP) to replace their
existing aging plant. The WTP is planned for a maximum production of 7.5 million gallons per day
(mgd) with a future expansion to 10 mgd. This memo reviews and updates the current City water
demand projections, and recommends revised initial and ultimate plant production capacities.
Revised Plant Capacity
Current Demand Projects
The City's Water Master Plan (WMP) was updated in August 2019 (City of Ashland, Water Master
Plan Update 2019, RH2 Engineering, Inc.). The WMP bases future population growth through 2065
on Portland State University's Population Research Center (PRC) estimates. Projected population
for intermediate years was calculated by assuming a uniform population growth rate between the
available PRC estimates for 2020, 2025, 2030, 2035, and 2040. Table 1 summarizes Average
Annual Growth Rate (AAGR) used for determining the future population.
Table 1. WMP Population Projections
Year
2020 to
2025
AAGR
0.680%
2026 to
2030
0.576%
2031 to
2035
0.290%
2036 to
2040
0.073%
2041 to
2050'
1 person per year
2051 to
2065`
0.140%
`Growth rate calculated from "COA Adjustable Demand Projections"
spreadsheet provided by RH2 Engineering
To forecast future water demands, the WMP used a consumption of 125 gallons per day (gpd) per
capita to calculate the average daily demand (ADD). Equation 1 presents the future water demand
calculation; population growth is based on using the AAGR in"Table 1.
Equation 1: Future Water Demand
Water Demand in Year Z = Water Demand in 2018 + (Population in Year Z — Population in Year 2018) x
125
hdrinc.com 1050 SW 6th Avenue, Suite 1800, Portland, OR 97204-1151
(503)423-3700
City of Ashland, OR 7.5 MGD Water Treatment Plant Final Design �1J�
Revised Plant Capacity
• Water Demand is in gpd
Year 2018 is used as the base year
• 2018 < Year Z
Table 2 references the peaking factors used in the WMP.
Table 2. WMP Peaking Factors
In the WMP, future demand projections were computed with and without water savings expected
from implementing conservation measures. The City's conservation program presents a goal to
reduce the system -wide ADD from projected non -conservation demand by 5 percent by 2020,
15 percent by 2030, and 20 percent by 2050. Table 3 represents the resulting demand projections
Table 3. WMP Demand Projections
Revised Demand Projections
During WMP update development, complete information was not available for the City's 2018 and
2019 water demand. To calculate revised demand projections, the City's water demand in 2019 was
used as the base year with demand projections based on the AAGR presented in Table 1. Water
demands were projected from 2066 to 2100 based on an AAGR of 0.14 percent, which was
calculated as the average population projection between 2019 and 2045, to account for a 100-year
WTP lifespan. In addition, conservation was assumed held at 20 percent per the City's goal.
Finally, additional water demands due to climate change were calculated. The Oregon Climate
Assessment Report indicates a 4 to 9 deg-F temperature increase by 2100, resulting in a climate -
related demand between 280,000 and 900,000 gpd. To account for climate change increases, the
median demand of 550,000 gpd by 2100 based on 2019 population was used to project the impact
of climate change on maximum daily demands.
Table 4 and Figure 1 present the revised demand projects through 2120.
N
N
N
N
N
N
N
N
N
O
O
O
O
O
O
O
O
O
N
O
(O
m
-1
m
CJl
.P
W
N
N
O
O
O
O
O
O
O
O
O
O
Cn
O
W
W
W
W
W
W
W
W
W
N
N
N
00
-I
Ul
-9�
N
O
O
O
CO
W
-J w
OD
N
CA
W
A
O
O
Ul
11
00
CO
W
N
N
N
N
N
N
N
N
N
N '
N
O
00
�I
M
Cn
Cn
Cn
Cn
O
U)
W
O
-1
A
N
W
O
Cn
CA
-?
4
-I
V
(n
(n
M
(n
Cn
M
cn
Cn
Cn
N
A-
00
Cn
N
O
O
O
(O
v
Cn
O
W
N
N
W
M
W
0
0
0?
Cn
rn
a)
cn
cn
cn
(n
-
(n
-
-
-
cn '
A
N
CO
O
A
N
O
O
-•
-
N
N
11
O
W
M
A
-4
O
W
O
00
00
-
-
V
Cn
4
N
00
A
O
M
W
N
-•
(O
�
�
Cn
�I
W
N
N
Cn
00
W
Cn
V
v
Cn '
•
1I
v
O)
Ul
Cn
(n
Cn
Cn
Cn
(n
Cn
W
N
N
N
IV
N
00
W
W
a
-I
N
cn
O
cn
O �
a�
a
CD
(D
N
CD
a
v
CD
3
7
a
O
CD
n
O
7
N
D
C
N
N
O
N
O
D
(N
S
N
D
a
N
fD
CD
N
:0 N!D
CD
0-
-0 (D
N
mr
V
N
City of Ashland, OR 7.5 MGD Water Treatment Plant Final Design
Revised Plant Capacity
FN
Figure 1. Comparison of WMP and Revised MDD Projections
8.5
Recommended Ultimate Plant Capacity - 8.5 mgd
8.0
7.5
/
7.0
Recommended Initial Plant Capacity - 6.5 mgd
6.5
a
5.5 • _ . _ . _ .
5.0 ,
4.5 _ -
2000 2020 2040 2060 2080 2100 2120
WMP Historic MDD Actual MDD
----WMP MDD ----Updated MDD
— • — WMP MDD with Conservation — — Updated MDD with Conservation
....... Updated MDD with Climate Change --- • Updated MDD with Climate Change + Conservation
August 2020 Recommendation
As shown in Figure 1, the revised demand projections start at approximately 0.5 mgd less capacity
than in the WMP. Based on this revised starting point, the City is projected to have an MDD of
6.26 mgd and 7.76 mgd in 2070 and 2120, respectively. Revising the WTP capacity to the following
is recommended:
• Initial Phase (50-year life) — 6.5 mgd
• Ultimate Phase (100-year life) — 8.5 mgd
While the initial WTP phase has the potential for more than a 50-year lifespan if the City achieves
conservation efforts, treatment equipment typically has a 20- to 25-year lifespan and would likely
need to be replaced at more frequent intervals. Conversely, if the City experiences increased water
demands due to climate change the initial WTP phase may have a lifespan closer to 40-years.
Forest Fire Update and Recommendation (September 2020)
During early September, southern Oregon experienced unprecendented forest fires that
significantly impacted the City's water demand. Based on water use through the week of
September 14, 2020, the demand projections were again updated. The forest fire demand
4
City of Ashland, OR 7.5 MGD Water Treatment Plant Final Design ���
Revised Plant Capacity
projections indicate maximum daily demands with climate change would exceed 6.5 MGD in
less than 30 years. To reach a 50-year lifespan based on the most recent water demand data
and incorporating the impact of climate change, it is recommended that the plant capacity
should be 7.0 MGD with an ultimate capacity of 9.0 MGD (see Table 5).
Table 5. Revised Demand Projections with Forest Fire Impacts (September 2020)
2020
MDD
5.84
Maximum Day Demand..
with Conservation with Climate Change
5.56 5.84
Change
5.56
2025
6.02
5.47
6.05
5.51
2030
6.18
5.37
6.25
5.44
2040
6.28
5.35
6.43
5.49
2050
6.28
5.24
6.51
5.46
2060
6.36
5.30
6.67
5.61
2070
6.37
5.45
6.93
5.84
2080
6.81
5.68
7.30
6.17
2090
7.10
5.92
7.70
6.51
2100
7.40
6.17
8.11
6.88
2110
7.72
6.43
8.55
7.27
2120
8.05
6.70
9.02
7.68
FN
Memo
Date: Friday, September 18, 2020
Project: City of Ashland, OR 7.5 MGD Water Treatment Plant Final Design
To: Scott Fleury, Kevin Caldwell
From: Pierre Kwan, P.E.; Verena Winter, P.E.; Katie Walker, P.E.; Harshit Joshi, EIT
Subject: Revised Plant Capacity Design Criteria TM
Introduction
The City of Ashland (City) is currently designing a new water treatment plant (WTP) to replace
their existing aging plant. The WTP is currently planned for a maximum production of 7.5 million
gallons per day (mgd) with a future expansion to 10 mgd. In a previous technical memorandum,
HDR recommended the following revisions to the WTP capacity:
• Initial Phase (50-year life) — 6.5 mgd
• Ultimate Phase (100-year life) — 8.5 mgd
The purpose of this technical memorandum is to identify changes to the current WTP design
criteria and cost estimate based on the revised recommended capacity.
Impact to WTP Design
Design Criteria
A reduction in plant capacity has a signficiant impact on the WTP design and cost. As
documented in the Basis of Design Report, several plant components are sized for the ultimate
phase due to either the cost or complexity of upsizing in the future. In general, a plant reduction
results in a decrease of the following:
• Treatment equipment sizes
• Pumping capacity
• Pipe sizes
• Basin/wet well sizes
• Chemical systems
Table 1 presents the criteria for the following design scenarios:
1. 60% Design — April 2020: original 60% design.
2. 60% Design — May 2020: revised 60% design to account for value engineering.
3. Revised Capacity Design: incorporates update to the 60% Design — May 2020 based on
a revised capacity
hdrinc.com 1050 SW 6th Avenue, Suite 1800, Portland, OR 97204-1151
(503)423-3700
FN
Table 1: WTP Design Criteria
Process/Plant Component Design Criteria 1. 60% Design — April 2020 2.64
Plant Capacity Initial; Ultimate (mgd) 7.5; 10 No c
Treatment Equipment
Strainers Number of strainers — initial; ultimate 2,3 No c
Capacity of each (gpm) 2,865 No c
Ozone Contact Pipeline
Length (feet)
665
305
Diameter (inches)
36
2; 3
48
Ballasted Flocculation
Number of trains — initial; ultimate
No c
Capacity, each (mgd)
4.5
No c'.
Number of filters — initial; ultimate
4; 5
4; 4
Filtration
Area per filter (sf); Length (ft) x Width (ft)
325; 13 x 25
No c
Filtration rate (gpm/sf) - initial; ultimate
5.5; 5.5
5.5; ,
Blower size (cfm); motor (hp)
1,300; 100
No 6
Wet well operating depth (ft)
5.25
4.4
Clearwell*
Capacity (MG)
0.85
No c�
Diameter (ft)
60
No c
Backwash Recovery Basins
Volume (gal)
340,000
320,(
Pump Stations
Number of pumps — initial; ultimate 3; 4 No c
Intermediate Pump Station Pump capacity, each (gpm) 2,865 No c.
Motor size, each (hp) 100 No c'
Number of pumps — initial; ultimate
2 small + 2 large; 4 large
3; 3
Crowson Pump Station
Pump capacity, each (gpm)
Small — 800; Large — 1,505
2,26(
Motor size, each (hp)
Small — 50; Large — 75
100
Number of pumps — initial; ultimate
2; 2
Filter to Waste Pump Station
Pump capacity, each (gpm)
1,910
Rem
Motor size, each (hp)
15
KI k— of ni.— -- ini#iol• d#imp#o
7. 7
AL...
Filter Effluent Pipe
Diameter (inches)
24
No cl
Combined Finished Water Pipe
Diameter (inches)
30
No cl
Potable Water to Crowson
Diameter (inches)
16
No d
Potable Water to Granite
Diameter (inches)
16
No cl
Backwash Supply Pipe
Diameter (inches)
24
No d
Wgi
Ozone System
Average production — initial (lb/day)
72
No c
Maximum production — initial; ultimate (lb/day)
165; 219
No c
Alumuminum Chlorohydrate System
Type of storage tank
Bulk tank
No c
Storage tank capacity (gal)
6,100
5,05(
Settling Aid Polymer
Type, number of storage tank
Tote, 2
No c
Storage tank capacity, each (gal)
330
No c
Filter Aid Polymer
Type of storage tank
Tote, 1
No c'
Storage tank capacity (gal)
330
No c'
Sodium Hypochlorite System
Type of storage tank
Bulk tank
No c
Storage tank capacity (gal)
3,150
2,75(
Caustic System
Type of storage tank
Bulk tank
Tote
Storage tank capacity (gal)
1,250
330
*Clearwell size to be evaluated further; size of clearwell is dependent on disinfection requirements and backwash volume storage, which can be rE
FN
Future Ultimate Plant Expansion
To expand from the revised initial plant capacity of 6.5 mgd to the ultimate plant capacity of 8.5
mgd, the following will be required:
• Filters re -rated from an initial capacity of 5.5 gpm/sf to 7.1 gpm/sf
• Add ozone generation/addition capacity
• Increase ozone contact pipeline from approximately 264 feet to 380 feet
• Add pumping capacity at the intermediate pump station and Crowson pump station
Unlike the 60% Design - May 2020, the revised plant capacity design would not require the
treatment building to be expanded for a third ballasted flocculation system.
Revised Cost Estimate
Appendix A presents the revised cost estimate prepared by Mortenson. The total construction
without Owner Contingency is now approximately $32.8M, which represents a reduction of
$2.5M from the previous cost estimate of $35.3M.
Following the forest fires in early September, the recommended capacity was revisited. A new
recommendation was developed based on maximum daily demand with climate change
impacts:
• Initial Phase (50-year life) — 7.0 mgd
• Ultimate Phase (100-year life) — 9.0 mgd
Linearly scaling the $2.5M cost savings between the 60% Design — May 2020 (7.5 mgd
capacity) and the Revised Capacity Design (6.5 mgd capacity), a 7.0 mgd WTP is expected to
be approximately $34.1 M, which represents a reduction of $1.25M.
hdrinc.com 1050 SW 6th Avenue, Suite 1800, Portland, OR 97204-1151
(503)423-3700
City of Ashland, OR 7.5 MGD Water Treatment Plant Final Design ���
Revised Plant Capacity Design Criteria TM
Appendix A —
Revised Cost Estimate (Mortenson)
Ashland Water Treatment Plant
City of Ashland
Ashland, OR
60% Design Estimate - Rev 3 - Reduced Capacity
Estimate Date: September 10, 2020
131
Superstructure
$
3,418,646
B2
Exterior Enclosure
$
219,453
63
Roofing
$
14,033
C1
Interior Construction
$
348,920
C2
Stairs
$
148,545
C3
Interior Finishes
$
268,023
D1
Elevator
$
103,500
D2
Mechanical Systems
$
6,941,106
D3
HVAC
$
147,600
D4
Fire Protection
$
97,465
D5
Electrical and I&C Systems
$
6,063,251
E1
Equipment
$
-
E2
Furnishings
$
1,200
F1
Special Construction
$
601,476
G1
Site Preparation
$
1,623,313
G2
Site Improvements
$
845,062
G3
Site Civil / Mechanical Utilities
$
4,235,615
G4
Site Electrical Utilities
$
768,242
Z1
General Requirements
$
2,823,500
Z3
Plant Startup & Testing
$
350,000
Subtotal Direct Construction Price
15
'9 ) , 81 5 0
Cost Escalation to 2nd Qrtr 2021
0.000°%
$
-
Estimating/Design Contingency
5.500%
$
1,596,042
Subtotal
$
30,614,992
Design/Engineering
by others
0.000%
$
-
Contractor Design Phase Services
by others
0.000%
$
Bldg Permits/Plan Check Fees
by others
0.000%
$
Testing/Inspection
by others
0.000%
$
MEN,,
Mortenson
$ 3,524,347
$
$ 219,453
$
$ 14,033
$
$ 348,920
$
$ 148,545
$
$ 268,023
$
$ 103,500
$
$ 7,241,032
$
$ 147,600
$
$ 97,465
$
$ 6,413,251
$
$ 1,200
$
$ 669,184
$
$ 1,778,115
$
$ 878,522
$
$ 4,809,910
$
$ 768,642
$
$ 2,823,500
$
$ 350,000
$
$ 30,605,242
$
$ 612,105
$
$ 1,716.954
$
$ 32,934,301
$
$
$
S
$
S
Subtotal $ 30,614,992
Sub Bonds 0.500% $ 153.075
$ 32,934,301 $
$ 164.672 5
Ashland Water Treatment Plant
City of Ashland
Ashland, OR
60% Design Estimate - Rev 3 - Reduced Capacity
Estimate Date: September 10, 2020
Bt
Superstructure
$
3,418,646
62
Exterior Enclosure
$
219,453
B3
Roofing
$
14,033
C1
Interior Construction
$
348,920
C2
Stairs
$
148,545
C3
Interior Finishes
$
268,023
D1
Elevator
$
103,500
D2
Mechanical Systems
$
6,941,106
D3
HVAC
$
147,600
D4
Fire Protection
$
97,465
D5
Electrical and I&C Systems
$
6,063,251
E1
Equipment
$
-
E2
Furnishings
$
1,200
F1
Special Construction
$
601,476
G1
Site Preparation
$
1,623,313
G2
Site Improvements
$
845,062
G3
Site Civil / Mechanical Utilities
$
4,235,615
G4
Site Electrical Utilities
$
768,242
z1
General Requirements
$
2,823,500
Z3
Plant Startup & Testing
$
350,000
Subtotal Direct Construction Price
$
29.0 18,950
Cost Escalation to 2nd Qrtr 2021
0.000%
$
-
Estimating/Design Contingency
5.500%
$
1,596,042
Subtotal
$
30,614,992
Design/Engineering
by others
0.000%
$
-
Contractor Design Phase Services
by others
0.000%
$
Bldg PermitsyPlan Check Fees
by others
0.000%
$
Testing/Inspection
by others
0.000%
$
-
Subtotal
$
30,614,992
Sub Bonds
0.500%
$
153,075
Contractor's Liability Insurances
0.750%
$
246,161
Builder's Risk Insurances
0.500%
$
164,107
Payment/Performance Bond
0.700%
$
229,750
Subtotal
$
31,408,085
Contractor's Fee including CAT
TOTAL CONSTRUCTION
COST
4.500%
$
1,413,364
C;•:
10.000%
$
3,282,145
Total I Total I Total , Total ' Total I
Total I
Total
Price Price Price Price Price Price Price
$
3,418,646
$ 3,418,646
$ -
$
-
$
-
$
- $
$
219,453
$ 219,453
$ -
$
-
$
-
$
- $
$
14,033
$ 14,033
$ -
$
-
$
-
$
- $
$
348,920
$ 348,920
$ -
$
-
$
-
$
ed
- $
$
148,545
$ 148,545
$ -
$
-
$
-
$
- $
$
268,023
$ 268,023
$ -
$
-
$
$
- $
$
103,500
$ 103,500
$ -
$
$
-
$
$
$
6,880,042
$ 6,880,042
$ -
$
28,656
$
32,408
$
- $
$
147,600
$ 147,600
$ -
$
-
$
-
$
$
$
97,455
$ 97,465
$ -
$
-
$
$
- $
$
5,999,568
$ 5,454,445
$ 545,123
$
57,387
$
6,296
$
- $
$
-
$ -
$ -
$
-
$
-
$
- $
$
1,200
$ 1,200
$ -
$
-
$
-
$
- $
$
481,476
$ 481,476
$ -
$
120,000
$
-
$
- $
$
635,830
$ -
$ 635,830
$
169,056
$
86,142
$
- $
$
B30,302
$ 108,660
$ 721,642
$
14,760
$
-
$
- $
$
$ -
$ -
$
910,000
$
424,400
$
- $
2,331,21E
$
768,242
$ -
$ 768,242
$
-
$
-
$
- $
$
2,171,995
S 1,948,420
$ 223.575
$
135,887
$
149,271
$
- $
252,50(
$
22,534,840
$ 19,640,428
$ 2,894,412
$
1,435,746
$
698,517
$
$
2,583,715
$
1,239,416
$ 1,080,224
$ 159,193
$
78.966.03
$
38,418
$
-
$
142,104
$
23,774,256
$ 20,720,652
$ 3,053,605
$
1,514,712
$
736,935
$
$
2,725,819
$
23,774,256
$ 20,720,652
$ 3,053,605
$
1,514,712
$
736,935
$
$
2,725,819
$
118,871
$ 103,603
$ 15,268
$
7,574
$
3,685
$
- $
13,62E
$
191,158
$ 166.605
$ 24,553
$
12,179
$
5.925
$
- $
21,911
$
127,438
$ 111.070
$ 16,368
$
8,119
$
3,950
$
- $
14,611
$
178,414
$ 155,498
$ 22,916
$
11,367
$
5,530
$
- $
20,45E
$
24,390,138
$ 21,257,428
$ 3,132,709
$
1,553,951
$
756,026
$
$
2,796,433
$
1,09T,556
$ 956,584
$ 140.972
$
69,928
$
34.021
$
- $
125,83E
0
Bringing safe drinking water to Oregon communities...
The Safe Drinking Water Revolving Loan Fund provides low-cost
financing to eligible water systems for planning, design, engineering, and
construction of drinking water facilities. Water systems may submit a
Letter of Interest (LOI) at any time to begin the process. Once submitted,
LOIs are rated and ranked by the Oregon Health Authority (OHA) before
being listed on the project priority list (PPL). Only projects that are listed on
the PPL and are ready to proceed may be invited to apply for funding.
ELIGIBLE WATER SYSTEMS
Public and privately owned community and non-profit non -community
water systems are eligible applicants. Federally -owned water systems are
not eligible.
ELIGIBLE PROJECTS
Sustainable Infrastructure Planning Projects (SIPP) - activities that
promote sustainable water infrastructure may receive 100% forgivable
loan funding up to a maximum of $20,000 per project. Priority is given to
systems less than 300 connections. Eligible planning activities include:
• Feasibility Studies to evaluate infrastructure project feasibility
• Asset Management Planning for managing water system infrastructure
assets
• System Partnership Studies to evaluate potential for system
consolidation or regionalization
• Resilience Planning for improving system resiliency and identifying
infrastructure projects
• Water Rate Analysis of water system rate charges, structure, and
adequacy
• Leak Detection Studies to detect system leakage and identify possible
solutions
• Water System Master Plans for long-range system needs (less than 300
connections only)
biz.oregon.gov
Design, Engineering, and Construction Projects - activities that create or
improve drinking water system facilities. Eligible design, engineering, and
construction projects include:
• New, repair or replacement of water sources, treatment, finished water
reservoirs, pumping and transmission/distribution mains, including
associated appurtenances, land/easement acquisition and control
buildings
• Aquifer Storage and Recovery (ASR)
• Instrumentation, telemetry, water meter, AMR/AMI, backflow device and
pressure reducing valve (PRV) installation or replacement
• Safety, seismic, and security improvements
• Improvements to critical water system assets that increase redundancy
and reliability
• Water system restructuring and/or consolidation to resolve
noncompliance or technical, managerial, and financial problems
CIRCUIT RIDERS
Free technical assistance is available from drinking water Circuit Riders to
provide on -site services for community water systems serving populations
under 10,000 and Non -Transient Non -Community non-profit schools. Services
include various water system testing, instruction, reporting, monitoring
adjustments, research, financing strategies, and funding application
assistance
INELIGIBLE PROJECTS
Ineligible projects include dams or rehabilitation of dams, water rights, raw water reservoirs or rehabilitation of raw
water reservoirs, projects primarily for fire protection, and projects primarily to serve future population growth.
FUNDING
Loan funding is available for financing small and large projects with interest rates as low as 60% of market rates and
terms up to 20 years. A limited amount of principal forgiveness maybe available for all eligible projects, with priority
funding and greater financial incentives for projects that resolve current health and/or compliance issues, or address
technical, managerial or financial problems through consolidation. Disadvantaged communities may receive additional
principal forgiveness, loan interest rates as low as 1%, and loan terms extending up to 30 years. Principal forgiveness is
also available to assist with proiect management and labor standards compliance.
SPEAKER REQUEST FORM
Submit this form to the meeting Secretary prior
to the discussion item.
1)You will be called forward when it is your turn to speak
2) State your name and speak clearly into the microphone
3) Limit your comments to the time allotted
4) Provide any written materials to the meeting Secretary
5) Speakers are solely responsible for the content of their statement
Date:
Name: (Please Print) a
Pe� L-'t 14 6 2—
;rsT
ent:
NO City:
Agenda Topic/Item Number:
0 VI
Public Forum Topic (Non -agenda Item):
Please respect the order of proceedings and strictly follow the
directions of the presiding officer. Behavior or actions which are loud
or disruptive are disrespectful and offenders will be requested to leave.
Disclaimer: By submitting this request to address the Public Body, I
agree that I will refrain from the use of any obscene, vulgar, or
profane language. I understand that if I do not follow procedure my
speaking time may be terminated, and I may be requested to sit down
or leave the building.