Loading...
HomeMy WebLinkAbout1999-101 CONT Chg Order 5-6 - Carollo EngineersCAROLLO ENGINEERS, P.C. CONTRACT CHANGE ORDER NO. 5 Project No. 4411 B30 OWNER: City of Ashland, Oregon PROJECT: Wastewater Treatment Plant Process Improvements SFR # 11750 CONTRACTOR: Slayden Construction, Inc. ENGINEER: Carollo Engineers, P.C. The following changes, additions to or deletions from the work described in the Contract Documents are hereby authorized: Item No. 1 2 3 4 5 6 7 8 9 Description (See attachment) RFP-22 Single-Speed Motor for Exhaust Fan EF-R1 RFP-23 Additional Embankment Fill at RASANAS Pump Station RFP-30 Delete Headworks Stop Plates RFP-33 Drain Line Revisions, RASANAS Pump Station RFP-36 Relocate Utility Power Manhole at RASANAS Pump Station RFP-37 Oxidation Ditch Inlet Box & Metering Box RFP-49 Conduit for Future Radio System RFP-53 120VAC Power to SCADA Remote I/O Panel No. 2 RFP-54 Repair Sinkhole in Entrance Roadway ' Cost Time (dollars) (days) (399.00) ' -0- 10,468.00 i -0- (190.00) -0- -0- -0- (2,659.00) -0- -0- -0- 914.00 -0- 1,857.00 -0- 1,179.00 -0- Original Contract Amount Net Change by Previous Change Orders Contract Amount prior to this Change Order Net Change due to this Change Order New Contract Amount $12,374,000.00 119,768.00 12,493,768.00 11,170.00 $12,504,938.00 The Contract Time is (unchanged) (~norr,e~r,n) (oec','te~eo~) by -0- calender days. The Contract completion date will be January 14, 2001. The amounts indicated above shall be compensation in full for the work described and shall include all costs, direct and indirect, including extended overhead. Accepted by: Recommended by: Approved by: CONTRACTCHANGE ORDER NO. 5 City of Ashland WVVTP Process Improvements SRF # 11750 Description of Items in Change Order RFP-22 Single-Speed Motor for Exhaust Fan EF-R1. By letter of December 23, 1998, the Engineer noted that the supply and exhaust fans for the lower level in the RASANAS Pump Station needed only single-speed motors, not dual speed. The exhaust fan, EF-R1, needed to be changed to a single-speed motor. The Contractor submitted a proposed credit of ($399.00) in a March 16, 1999 letter. After review, the Engineer informed the Contractor by letter of March 17, 1999 that this credit would be included in a forthcoming change order. RFP-23 Additional Embankment Fill at RAS/VVAS Pump Station. Following discussions with the City, the Engineer informed the Contractor by letter of December 29, 1998 that additional embankment fill was needed west and northwest of the RAS/VVAS Pump Station, to permit access around the building when complete, and to allow construction of electrical duct banks and manholes in a non-flooding area in that corner of the site. A revised grading plan was sent the Contractor. The Contractor submitted proposed costs of $10,916.00 in a letter dated January 22, 1999; the Engineer queried some of the costs, which were discussed in a February 25 meeting. In a letter received March 16, the Contractor submitted revised costs of $10,468.00. After review, the Engineer informed the Contractor by letter of March 16, 1999 that this amount would be included in a forthcoming change order. RFP-30 Delete Headworks Stop Plates. Due to conflicts in installation of new stop plates and slide gates in the bar screen channel area of the Headworks, the Engineer informed the Contractor by letter dated January 11, 1999 that the stop plates should be deleted. By letter of March 29, the Contractor offered a credit of ($190.00) for this revision. After review, the Engineer informed the Contractor by letter of April 2, 1999 that this credit would be included in a forthcoming change order. RFP-33 Drain Line Revisions, RAS/VVAS Pump Station. By letters dated January 13 and January 14, 1999, the Engineer notified the Contractor of necessary changes in the drain piping beneath the lower level slab of the RAS/VVAS Pump Station, including some deletions and some additions. Installation of the drain piping required slight lowering of the RAS piping beneath the floor slab. In a March 29 letter the Contractor proposed that this be a 'no-cost' change. After review, the Engineer informed the Contractor by letter of April 2, 1999 that this would be included in a forthcoming change order as such. RFP-36 Relocate Utility Power Manhole at RASANAS Pump Station. By letter of February 12, 1999, the Engineer informed the Contractor of a need to move the utility power manhole on the north side of the RASNVAS Pump Station approximately 20 feet to the east along the wall. This move would coordinate with a planned relocation of the electrical substation and would also reduce the length of conduits and conduit rack in the lower level required to reach the main switchgear. In a subsequent letter dated March 30, the Contractor proposed a credit of ($2,570.00) for this change. After review, the Engineer informed the Contractor by letter of April 2, 1999 of a necessary slight revision in the credit, to ($2,659.00), and that this credit would be included in a forthcoming change order. 2 RFP-37 Oxidation Ditch Inlet Box & Metering Box. In RFI 1026, the Contractor was notified of revised coordinates for the SE corner of the inlet splitter box on the Oxidation Ditch structure as well as the adjacent metering vault, to allow the Contractor to revise the forming and pouring of splitter box wall sections. By letter dated February 15, 1999, the Engineer confirmed these coordinates and made minor changes to the inlet splitter box pipe connections, including raising the raw sewage (RS) pipeline and revising the arrangement and elevation of the drain (D) and pumped drain (PD) piping. In a subsequent letter of April 8, 1999, the Contractor proposed that this be a 'no-cosr change. After review, the Engineer informed the Contractor by letter of April 8, 1999 that this would be included in a forthcoming change order as such. RFP-49 Conduit for Future Radio System. The Engineer informed the Contractor by letter of March 8, 1999 of the need to add a 2-inch electrical conduit within the RASNVAS Pump Station to allow the future installation of a proposed radio system to receive telemetry signals from the proposed Biosolids and Effluent Reuse project and Bear Creek flow signals. In a letter dated March 31, 1999, the Contractor submitted proposed costs of $914.00 for this work. After review, the Engineer informed the Contractor by letter of April 2, 1999 that this amount would be included in a forthcoming change order. RFP-53 120VAC Power to SCADA Remote I/O Panel No. 2. In RFI's 43 and 73, the need for a 120-volt power supply to the UPS in SCADA Remote I/O Panel No. 2 at the Headworks was raised. By letter dated March 15, 1999, the Engineer informed the Contractor that two circuits should be brought to the SCADA panel, one for the UPS and one for a strip heater to avoid freezing and moisture condensation. The Contractor submitted costs of $1,857.00 for this work, by letter of March 31, as revised on April 6. After review, the Engineer informed the Contractor by letter of April 6, 1999 that this amount would be included in a forthcoming change order. RFP-54 Repair Sinkhole in Entrance Roadway. In mid-March, an existing drain line from the main gate area to Ashland Creek was cleaned and jet-rodded by the City to alleviate standing water at the main gate after rain events. A day or two later, on March 15, WWTP staff noted a sinkhole in the plant's entrance roadway, east of the Ashland Creek Pump Station. The Engineer asked the Contractor to open the hole for repairs, and it was found that the drain line had been broken out and not repaired during installation of an effluent pipeline from the demonstration wetlands. This had caused the drain line to not work properly for some time; the jet-rodding washed material on down the drain to the creek, creating the cavity under the paving. By letter of March 16, the Engineer requested the Contractor prepare an estimate of costs incurred in the repair work. By letter that same day, the Contractor submitted costs of $1,179.00. After review, the Engineer informed the Contractor by letter of March 16, 1999 that this amount would be included in a forthcoming change order. 3 CAROLLO ENGINEERS, P.C. CONTRACT CHANGE ORDER NO. 6 Project No. 4411B30 OWNER: City of Ashland, Oregon PROJECT: Wastewater Treatment Plant Process Improvements SFR # 11750 CONTRACTOR: Slayden Construction, Inc. ENGINEER: Carollo Engineers, P.C. The following changes, additions to or deletions from the work described in the Contract Documents are hereby authorized: Item No. 1 2 3 4 5 6 7 8 9 Original Contract Amount Net Change by Previous Change Orders Contract Amount prior to this Change Order Net Change due to this Change Order New Contract Amount Description (See attachment) RFP-25 12 KV Duct Bank RFP-38 Modification of Typical Detail E104 RFP-39 RASANAS Pump Station Perimeter Drain Revision RFP-43 Grit Chamber Drain Cleanout RFP-48 Door for UV Building Lower Area RFP-51 Headworks Revisions for Improved Electrical Installation RFP-56 Metering Vault Top Revisions RFP-60 Oxidation Ditch Elevated Slab Construction joints RFP-64 Oxidation Ditch Stair and Ladder Platform Elevations $12,374,000.00 130,938.00 12,504,938.00 19,868.00 $12,524,806.00 Cost Time (dollars) (days) 17,845.00 , -0- -0- -0- -0- -0- 786.00 -0- -0- -0- -0- -0- -0- ' -0- -0- -0- 1,237.00 -0- The Contract Time is (unchanged) (lnnrr~nc, r~) (,nnnrnnnndj by -0- calender days. The Contract completion date will be January 14, 2001. direct and indirect, including extended overhead. Accepted by: ~ ~ ~-~ (Contractor) Recommended by: Approved by: · y) The amounts indicated above shall be compensation in full for the work described and shall include all costs, Date: Date: CONTRACTCHANGE ORDER NO. 6 City of Ashland WWTP Process Improvements SRF # 11750 Description of Items in Change Order RFP-25 12 KV Duct Bank. By letter dated January 5, 1999, the Engineer informed that Contractor that a concrete-encased duct bank was needed for the 12 KV main electrical service conductors from the City's recently-installed underground conduit and conductors along the east side of the WWTP. This duct bank would extend from a City pull-box adjacent to the entrance gate to the proposed utility substation pad north of the RASNVAS Pump Station; when completed, the City Electrical Department will install the 12 KV conductors. By letter of January 29, the Contractor submitted proposed costs of $28,154.00 for this work. In a subsequent letter dated February 5, the Engineer modified the route of the proposed duct bank to shorten the distance and reduce costs. The Contractor submitted revised proposed costs of $17,845.00 in a March 30 letter. After review, the Engineer informed the Contractor by letter of April 5, 1999 that this amount would be included in a forthcoming change order. RFP-38 Modification of Typical Detail E104. By letter dated February 16, 1999, the Engineer notified the Contractor that Typical Detail E104, for connection of electrical duct banks to structures, could be modified. In an April 8, 1999 letter the Contractor proposed that this be a "no-cost" change. After review, the Engineer informed the Contractor by letter of April 9, 1999 that this would be included in a forthcoming change order as such. RFP-39 RASNVAS Pump Station Perimeter Drain Revision. By letter of February 16, the Engineer informed the Contractor that the perimeter drain around the exterior of the RASNVAS Pump Station should be modified slightly to facilitate installation of the drain around the electrical manholes being constructed along the outside walls of the pump station. In a March 29, 1999 letter the Contractor proposed that this be a "no-cost" change. After review, the Engineer informed the Contractor by letter of April 2, 1999 that this would be included in a forthcoming change order as such. RFP-43 Grit Chamber Drain Cleanout. By letter of February 23, 1999, the Engineer informed the Contractor that WWTP staff had recommended installation of a cleanout in the new drain piping for the grit chamber, to allow the grit drain line connection to be cleaned if it plugs; this has been a problem in the past. By letter dated April 5, 1999, the Contractor submitted proposed costs of $786.00 for this work. After review, the Engineer informed the Contractor by letter of April 5, 1999 that this amount would be included in a forthcoming change order. RFP-48 Door for UV Building Lower Area. By letter of March 3, 1999, the Engineer informed the Contractor that a door should be installed in the opening at the bottom of the stairs leading to the lower area of the UV Building. In a subsequent letter dated March 4, 1999, the Contractor submitted proposed costs of $2,393.00 for this work. During the following several weeks, other activities at the site were discussed; the Contractor wished to modify the location of construction joints and pour sequences in the elevated slabs of the Oxidation Ditch structure (RFP-60). In order to advance the schedule and benefit the project, it was agreed to install the door as a "no cost" change. By letter of March 23, 1999, the Engineer informed the Contractor that this would be included in a forthcoming change order as such. 2 4 RFP-51 Headworks Revisions for Improved Electrical Installation. By letter dated March 11, 1999, the Engineer noted two areas where revisions were needed at the Headworks to facilitate electrical system equipment installation: a ramp and a water line, hose valve and hose rack on the east side were to be moved to allow unfettered installation of the electrical switchrack; and area lights shown to be mounted on heavy aluminum brackets on the edge of the structure can be mounted on the concrete slab. In an April 9, 1999 letter the Contractor proposed that this be a "no-cost" change. After review, the Engineer informed the Contractor by letter of April 9, 1999 that this would be included in a forthcoming change order as such. RFP-56 Metering Vault Top Revisions. In RFI-76, the weight of the tread plate cover panels for the Metering Vault south of the Oxidation Ditch structure was queried. The Engineer indicated that the top of the structure would be modified to have just one, smaller hinged section and two fixed sections; this was sent to the Contractor by letter dated March 17, 1999. In a March 30, 1999 letter the Contractor proposed that this be a "no-cost" change. After review, the Engineer informed the Contractor by letter of April 5, 1999 that this would be included in a forthcoming change order as such. RFP-60 Oxidation Ditch Elevated Slab Construction Joints. In RFI-74, the Contractor requested permission to modify the location of construction joints and pour sequence in the Oxidation Ditch structure elevated slabs. The structural engineer indicated that this would not be objectionable; after discussions, it was concluded that doing so would advance the schedule for completion of concrete work for the entire structure. In return for permission to proceed, the Contractor agreed to install the door in the UV Building lower area (RFP-48), all at no cost to the Owner. By letter dated March 23, 1999, the Engineer confirmed the agreement and stated that this change would be included in a forthcoming change order. RFP-64 Oxidation Ditch Stair and Ladder Platform Elevations. By letter of March 29, 1999, the Engineer informed the Contractor that the elevations of the stairway bottom platform near the north end and the ladder platform on the north side of the mixed liquor weir box on the east side of the Oxidation Ditch structure needed to be lowered to match site finish grades. This adds several stair treads/risers on the stairway and lengthens the handrail, and lengthens the ladder. In a letter dated March 30, the Contractor submitted proposed costs of $1,237.00 for this work. After review, the Engineer informed the Contractor by letter of April 2, 1999 that this amount would be included in a forthcoming change order. 3 CITY OF ASHLAND CITY HALL ASHLAND, OREGON 97520 NOTICE OF TRANSMITTAL TO: BARBARA CHRISTENSEN CITY RECORDER DATE: PROJECT: JOB NO.: SUBJECT: APRIL21,1999 WWTPIMPROVEMENTS CAROLLO CHANGE ORDERS THE FOLLOWING ITEMS ARE BEING SENT TO YOU: 1. Original Contract Change Orders No. 5 and 6 from Carollo Engineers, P.C. ENCLOSED X UNDER SEPARATE COVER REMARKS: COPIES TO: Pat Caldwell Department of Public Works By: Paula Brown Title: Director of Public Works (G:dawn/waters/treatment plantJCarolla CNG 5&6 NOT