Loading...
HomeMy WebLinkAbout1999-105 CONT Chg Orders 7-8-9 - Carollo EngineersCITY OF ASHLAND Department of Public Works Administration / Director's Office MEMORANDUM DATE: TO: FROM: RE: June 7, 1999 Honorable Mayor and Members of the City Council Paula C. Brown, Public Works Director / City Engineer If WWTP - CAROLLO PROGRESS REPORT NO. 6 APRIL 1999 Carollo's Project Report No 6 is attached for your information. Work continues to progress quickly. All of the concrete around the oxidation ditches has been completed and the RAS/WAS Pump Station Building is nearing completion. To date we have issued nine change orders: 9 Minor changes; add grinder pump temp headworks Relocate the trunk line around the RAS/WAS Over-excavation and rock backfill RAS/WAS Miscellaneous improvements to the u/v building Misc changes including additional RAS/WAS fill Electrical changes to 12KV duct bank plus misc Yard Hydrants, UV Electrical changes; credits for chlorine monorail relocation and sodium hypochlorite containment drains Influent Junction Box (new requirement); revise monorail size - RAS/WAS pump station Rock Excavation (change in site conditions); gyp-board in UV Building $23,527.00 $47,500.00 $33,744.00 $14,997.00 $11,170.00 $19,868.00 $ 7,114.00 $41,978.00 prior memo prior memo prior memo prior memo prior memo prior memo !leery new $48,920.00 new TOTAL CHANGES TO DATE $248,818.00 Original Contract Amount Change Orders to Date Total Approved Contract to Date $12,374,000.00 248,818.00 $12,622,818.00 2.01% As of the end of May, the contractor is 65% complete and a little ahead of schedule. The last two monthly payments have been for over $1 million of work in place for that month. The remaining large known change order to be discussed and negotiate is the Ashland Creek Pump Station. Council approved the design and construction is expected to add up to $900,000. Mike Freeman Jill Turner Barbara Christensen 2 CAROLLO ENGINEERS, P.C. CONTRACT CHANGE ORDER NO. 7 Project No. 4411B30 OWNER: City of Ashland, Oregon PROJECT: Wastewater Treatment Plant Process Improvements SFR # 11750 CONTRACTOR: Slayden Construction, Inc. ENGINEER: Carollo Engineers, P.C. The following changes, additions to or deletions from the work described in the Contract Documents are hereby authorized: Item No. 1 2 3 4 5 6 7 8 9 Description (See attachment) RFP-3 Revisions to Walls and Handrail at Contact/UV Basin RFP-20 UV Area Lighting Panel & Electrical Changes RFP-40 Delete Chlorine Monorail Relocation RFP-41 Delete Flap Valves on Hypochlorite Containment Drains RFP-44 Fire Hydrants RFP-46 Revise RASNVAS Pump Station Doors 003 and 004b RFP-52 Operations Building Flush Wood Door Revisions RFP-63 Freezeless Yard Hydrants RFP-65 Cast Iron Soil Piping in Operations Building Cost Time (dollars) (days) 712.00 -0- 1,129.00 -0- (2,859.00) -0- (420.00) -0- 755.00 -0- -0- -0- -0- -0- 7,797.00 -0- -0- -0- Original Contract Amount Net Change by Previous Change Orders Contract Amount prior to this Change Order Net Change due to this Change Order New Contract Amount $12,374,000.00 150,806.00 12,524,806.00 7,114.00 $12,531,920.00 The Contract Time is (unchanged) (increased) (decreased) by -0- calender days. The Contract completion date will be January 14, 2001. The amounts indicated above shall be compensation in full for the work described and shall include all costs, direct and indirect, including extended overhead. Accepted by: Z/ (~Cor~ Recommended by: ',~r)/jl/~- Approved by: Date: CONTRACT CHANGE ORDER NO. 7 City of Ashland WWTP Process Improvements SRF # 11750 Description of Items in Change Order RFP-3 Revisions to Walls and Handrail at Contact/UV Basin. By letter of October 21, 1998, the Engineer informed the Contractor that revisions were desired to the concrete walls being constructed at the Contact/UV Basin, to the openings being cut in existing walls, and to the handrail being installed. By letter dated April 12, 1999, the Contractor submitted proposed costs of $1,633.00 for these revisions. Following discussions on the quantities of materials and relative amounts of work involved, the Contractor submitted revised total proposed costs of $712.00 in a letter dated April 28. After review, the Engineer informed the Contractor by letter of April 28, 1999 that this amount would be included in a forthcoming change order. RFP-20 UV Area Lighting Panel and Electrical Changes. By letter of December 22, 1998, the Engineer informed the Contractor that, due to electrical changes in the UV Building and the need to add 120-volt circuits, a new lighting panel should be installed in the UV Building, subfed from the RASNVAS Pump Station, to supply the various circuits in the UV Building. This results in deletion of a number of conduits and concomitant wiring from the RAS/WAS Pump Station. By letter dated January 5, 1999, the Contractor submitted proposed total costs of $1,818.00 for this work. Following discussions, a revised total cost of $1,129.00 was submitted in an April 28 letter. After review, the Engineer informed the Contractor by letter of April 28, 1999 that this amount would be included in a forthcoming change order. RFP-40 Delete Chlorine Monorail Relocation. By letter of February 16, 1999, the Engineer informed the Contractor that the relocation of the existing chlorine monorail was no longer required. By letter dated March 29, the Contractor submitted proposed total credits of ($2,670.00) for this revision. Following discussions, the Contractor submitted revised total credits of ($2,859.00) with a letter of May 7. After review, the Engineer informed the Contractor by letter of May 7, 1999 that this amount would be included in a forthcoming change order. RFP-41 Delete Flap Valves on Hypochlorite Containment Drains. By letter of February 22, 1999, the Engineer informed the Contractor that the flap valves on the ends of drains from two sodium hypochlorite containment areas could be deleted. In a letter dated April 8, the Contractor proposed total credits of ($250.00); following several discussions, the Contractor submitted revised total credits of ($420.00) for this revision. After review, the Engineer informed the Contractor by letter of April 28, 1999 that this amount would be included in a forthcoming change order. RFP-44 Fire Hydrants. By letter of February 24, 1999, the Engineer informed the Contractor that the six hose valve fire hydrants shown on the Drawings should be revised to three AWWA fire hydrants; this also revised the length and size of piping necessary. Two existing fire hydrants could be relocated and reused. In a letter dated April 5, the Contractor submitted proposed total costs of $3,147.00 for this work. Following several discussions on the quantities of materials and relative amounts of work involved, agreement was reached on a revised total cost of $755.00. The Engineer informed the Contractor by letter of April 9, 1999 that this amount would be included in a forthcoming change order. RFP-46 Revise RAS/WAS Pump Station Doors 003 and 004b. By letter of February 25, 1999, the Engineer informed the Contractor that two doors in the RAS/WAS Pump Station should be revised from Type G (with half-lite) to Type F (solid); it was proposed that this revision be an exchange for some hardware revisions on various doors. In an April 9, 1999 letter the Contractor proposed that this be a "no-cost" change. After review, the Engineer informed the Contractor by letter of April 13, 1999 that this would be included in a forthcoming change order as such. RFP-52 Operations Building Flush Wood Door Revisions. By letter of March 11, 1999, the Engineer informed the Contractor that three flush wood doors in the Operations Building, numbers 006, 007 and 012, be revised from Type B (full lite) to Type G (half lite). In an April 13, 1999 letter the Contractor proposed that this be a "no-cost" change. After review, the Engineer informed the Contractor by letter of April 13, 1999 that this would be included in a forthcoming change order as such. RFP-63 Freezeless Yard Hydrants. By letter of March 29, 1999, the Engineer informed the Contractor that the various exterior hose valves shown on the Drawings needed to be changed to freezeless yard hydrants, due to the cold weather possible in southern Oregon. By letter dated April 12, the Contractor indicated there were 27 hose valves, and proposed total costs of $7,318.00 for this revision. In a subsequent letter of April 16, the Engineer noted that two hose valve installations were being deleted near the headworks, and that there were a total of 28 remaining units. Some of these, installed in the ground, require installation of rigid, threaded brass pipe below the freezeless yard hydrant. By letter dated April 28, the Contractor submitted revised total proposed costs of $7,797.00. After review, the Engineer informed the Contractor by letter of April 28, 1999 that this amount would be included in a forthcoming change order. RFP-65 Cast Iron Soil Piping in Operations Building. By letter of April 5, 1999, the Engineer confirmed field discussions that use of No-Hub cast iron soil pipe (CISP) was desired in the Operations Building, in lieu of bell and spigot CISP. In an April 7, 1999 letter the Contractor proposed that this be a "no-cost" change. After review, the Engineer informed the Contractor by Fetter of April 7, 1999 that this would be included in a forthcoming change order as such. CAROLLO ENGINEERS, P.C. CONTRACT CHANGE ORDER NO. 8 Project No. 4411B30 OWNER: City of Ashland, Oregon PROJECT: Wastewater Treatment Plant Process Improvements SFR # 11750 CONTRACTOR: Slayden Construction, Inc. ENGINEER: Carollo Engineers, P.C. The following changes, additions to or deletions from the work described in the Contract Documents are hereby authorized: Item No. 1 2 3 Description (See attachment) RFP-50 Infiuent Junction Box RFP-66 Revise Monorail Rail Size RFP-67 Delete Thermostat in RASNVAS Pump Station Lower Level Cost (dollars) 40,799.00 1,179.00 Time (days) -0- -0- -0- Original Contract Amount Net Change by Previous Change Orders Contract Amount prior to this Change Order Net Change due to this Change Order New Contract Amount $12,374,000.00 157,920.00 12,531,920.00 41,978.00 $12,573,898.00 The Contract Time is (unchanged)'(~ ..... ~-~. ~ ~2, ~ ....-,,-. ;~ by -0- calender days. The Contract completion date wilt be January 14, 2001. The amounts indicated above shall be compensation in full for the work described and shall include all costs, direct and indirect, including extended overhead. r) Approved by: Date: Recommended by: D ate: CONTRACTCHANGE ORDERNO. 8 City of Ashland WWTP Process Improvements SRF # 11750 Description of Items in Change Order RFP-50 Influent Junction Box. By letter of March 11, 1999, the Engineer informed the Contractor of the need to construct an influent junction box at the Headworks, to provide a common meeting point for incoming raw sewage gravity lines and force mains, and to allow easier connection of any future pipelines. By letter dated April 5, the Contractor submitted proposed costs of $52,055.00. In a subsequent letter dated May 5, the Engineer modified the proposed work to lower the costs. The Contractor submitted revised proposed costs of $41,758.00 in a May 21 letter. After discussions, the Contractor's costs were further revised to $40,799.00; by letter of May 25, the Engineer informed the Contractor that this amount would be included in a forthcoming change order. RFP-66 Revise Monorail Rail Size. By letter of April 6, 1999, the Engineer informed the Contractor that the size of the monorail system rail in the RAS/WAS Pump Station needed to be increased. In a letter dated April 13, 1999, the Contractor submitted proposed costs of $1,237.00 for this revision. Following discussions, the Contractor revised his proposed costs to $1,179.00; by letter of April 28, the Engineer informed the Contractor that this amount would be included in a forthcoming change order. RFP-67 Delete Thermostat in RAS/WAS Pump Station Lower Level. By letter of April 6, 1999, the Engineer informed the Contractor that a thermostat for the supply and exhaust fans in the lower level of the RASANAS Pump Station was incorrectly shown and should be deleted. In an April 9, 1999 letter the Contractor proposed that this be a "no-cost" change. After review, the Engineer informed the Contractor by letter of April 9, 1999 that this would be included in a forthcoming change order as such. CAROLLO ENGINEERS, P.C. CONTRACT CHANGE ORDER NO. 9 Project No. 4411B30 OWNER: City of Ashland, Oregon PROJECT: Wastewater Treatment Plant Process Improvements SFR # 11750 CONTRACTOR: Slayden Construction, Inc. ENGINEER: Carollo Engineers, P.C. The following changes, additions to or deletions from the work described in the Contract Documents are hereby authorized: Item No. 1 2 3 4 Description (See attachment) RFP-61 Delete Plant Drain Pump Station RFP-70 Revision to Embankment on West Side of Plant RFP-79.1 Rock Excavation RFP-90 Insulation & Gypsum Board in UV Building Cost Time (dollars) (days) 45,920.00 -0- 3,000.00 -0- Original Contract Amount Net Change by Previous Change Orders Contract Amount prior to this Change Order Net Change due to this Change Order New Contract Amount $12,374,000.00 199,898.00 12,573,898.00 48,920.00 $12,622,818.00 The Contract Time is (unchanged) (~Rf,.rf,.r~n,'1) (dr>nrnn~n. tl,) by -0- calender days. The Contract completion date will be January 14, 2001. The amounts indicated above shall be compensation in full for the work described and shall include all costs, direct and indirect, including extended overhead. Accepted by: ~'~ ~ ~'(_- ,Z" Date: Approved by: / ' Date: (City) Recommended by: Date: 06'0F 99 CONTRACT CHANGE ORDER NO. 9 City of Ashland WWTP Process Improvements SRF # 11750 Description of Items in Change Order RFP-61 Delete Plant Drain Pump Station. By letter of March 29, 1999, the Engineer informed the Contractor that the Plant Drain Pump Station was to be deleted in its entirety; the gravity drain (D) piping and storm drain (SD) piping flowing to it were to be extended to the proposed new Ashland Creek Pump Station, and the pumped drainage (PD) piping to the Oxidation Ditch splitter box would be deleted. This change included earthwork, concrete and reinforcing steel, piping, painting, electrical power and controls, etc. As it was too late to cancel the intended submersible pumps, custom control panel, access hatch and related material furnished by the pump manufacturer, those items would be taken by the City for use elsewhere. The Contractor submitted a proposed "no-cost" change letter dated April 30; while there would be a substantial credit for the deletion of the pump station, there would be an offsetting substantial cost of extending the gravity drain and storm drain piping to the Ashland Creek Pump Station. At the monthly meeting on June 3, 1999, this and other RFPs were discussed; in return for installation of insulation and gypsum board in the ceiling of the UV Building at a reduced price (RFP-90), the City agreed that the pump station deletion should be included in a forthcoming change order at no change in Contract Price. This was confirmed by letter from the Engineer to the Contractor that same day. RFP-70 Revision to Embankment on West Side of Plant. By letter of April 13, the Engineer confirmed discussions from the April 8 progress meeting regarding the berm to be constructed west of the Oxidation Ditch and the RASANAS Pump Station. The berm shown on the Plans was to be modified from a 1:1 slope to a 2:1 slope and the geotextile fabric deleted, with compaction to 90 % max density and the upper two feet to 95% max density. By letter of April 30, the Contractor submitted proposed credits of ($1,500.00) for this change. This was felt to be low. At the monthly meeting on June 3, 1999, this and other RFPs were discussed; in return for installation of insulation and gypsum board in the ceiling of the UV Building at a reduced price (RFP-90), the City agreed that the change in the berm construction should be included in a forthcoming change order at no change in Contract Price. This was confirmed by letter from the Engineer to the Contractor that same day. RFP-79.1 Rock Excavation. During the winter of 1998/99, the Contractor indicated that rock encountered in pipe trench excavation on the site, and the hardness of the rock encountered in excavation of the Oxidation Ditch structure, was felt to be a differing site condition. This was discussed at several meetings, with exchange of views and information. By letter of May 7, the Engineer established this RFP for all related correspondence and data. By separate letter of that same day, the Engineer informed the Contractor that the hardness of the rock in the Oxidation Ditch excavation did not constitute a changed condition, but that the rock encountered in the pipe trench area between the secondary cladtiers and the UV Building was a differing condition. Following additional discussions with the Contractor, a unit cost for rock trench excavation of $224.00/CY was agreed upon and confirmed by letter dated May 24 to the Contractor. The first area to which this was to apply is the area between Secondary Clarifier No. 1 and the UV Building; by subsequent letter of May 25, the Engineer confirmed an agreed- upon quantity in this area of 205 cubic yards and indicated that a resulting total cost of $45,920.00 would be included in a forthcoming change order. RFP-90 Insulation & Gypsum Board in UV Building. As a portion of earlier RFP-35, it was proposed to install insulation and gypsum board in the ceiling of the UV Building; that RFP was canceled due to overall costs. By letter of June 3, 1999, the Engineer confirmed that it was still desired to install insulation and gypsum board in the UV Building; at the monthly meeting that day, agreement had been reached to consider RFP-61 and RFP-70 as "no-cost" changes and that the insulation and gypsum board would be installed at a reduced cost, for a total lump sum cost of $3,000.00, and that amount included in a forthcoming change order. 3