HomeMy WebLinkAbout2019-05-28 Water Advisory Committee Agenda PacketASHLAND WATER. ADVISORY COMMITTEE
May 28, 2019
AGENDA
I. CALL TO ORDER: 4:00 PM, Siskiyou Room, 51 Winburn Way Ashland, OR
II. ANNOUNCEMENTS
III. APPROVAL OF MINUTES: April 23, 2019
IV. PUBLIC FORUM
V. OLD BUSINESS
A. Done
VI. NEW BUSINESS
A. RH2 Master Plan Pre sentation/Discussion
a Water System Analysis
a Capital Improvement Program
VII. ADJOURNMENT: 6 : 0 0 PM
CITY OF
ASHLAND lwwAli
ASHLAND Water Advisory Committee
MINUTES
April 23, 2019
CALL TO ORDER
Williams called the meeting to order at 4.09 PM
Committee Members Present: Pat Acklin, Joe Graf, Rich Miller, Don Morris, Donna Rhee, Alex Amarotico, Darrell
Boldt, John Williams
Committee Members Absent: Lesley Adams, Kate Jackson
Staff present: Paula Brown, Scott Fleury, Steve Walker, Michael Morrison, Kevin Caldwell, Taina Glick
ANNOUNCEMENTS
None
APPROVAL OF MINUTES
March 27, 2018 approved as presented. March 26, 2019 approved as amended.
PUBLIC FORUM
None
Old Business
A. Water Treatment Plant Update — Fleury stated that HDR is set to have 30% design completed by end of
May and Mortenson will have an updated cost of construction estimate at that time. Mortenson, HDR, and
City staff will meet to discuss/make adjustment to the plan after which HDR will finalize the basis of design
report. Initial bid package should be released in spring 2020. Construction will take approximately 2-3 years.
Basis of design package should be available to committee members at the June meeting. Solar is being
considered to offset some of electric consumption of the plant. Electric service redundancy is also being
evaluated.
Committee members and staff discussed the need or appropriateness of a public forum at this stage. It was
suggested to provide information about the project in the City Source and a press release and encourage
citizens to come to the AWAC meeting before the plan goes to City Council. Project information is available
on the CIP Storybook section of the City of Ashland website.
B. Pump Station Update — Fleury informed committee members that both stations are substantially complete.
Caldwell added that both should be operational mid -May. When the canal comes on, testing can begin at the
Terrace Street location. Brown thanked Caldwell for the management of this project and keeping the costs
within budget and time. Fleury thanked Glick for maintaining compliance with loan requirements.
C. Canal Project Update — Brown informed committee members of the City Council's request for an additional
listening session (June 17), another study session (July 1), then potentially a decision on July 16. Brown
indicated a survey may be sent out by Administration to gain citizen input. Acklin suggested seeking support
from the climate and energy action group. Williams asked if DEQ is requiring this project. Brown indicated
they are not.
Ashland Water Advisory Ad -Hoc Committee (AWAC)
April 23, 2019
Page 1 of 2
ASHLAND Water Advisory Committee
MINUTES
April 23, 2019
NP-w Rn_ginp_c;s
A. RH2 Master Plan Schedule Update/Progress Report
a Master plan development to date review
o O&M Manual development to date review
a Current Status
o Shared vision planning — removal: This task was to determine if additional climate modeling
is warranted. Committee members and staff discussed why it was originally included and if this
part of the plan is still necessary. Acklin moved to omit task 15 and the shared vision model and
summarize the City's supply strategy in the systems analysis. Graf seconded. Motion passed by
concession of the committee members.
Rachel Lannigan from RH2 presented the Water Master Plan. The presentation is attached.
Williams asked for clarification on the rate structure agenda topic. Brown informed group that rates will be discussed
at the May meeting but provided basic information about the topic. Williams reminded the group not to discuss rates
with members of the press. Brown requested that rate inquiries be forwarded to her.
FUTURE AGENDA TOPICS
May -- Capital Improvement Program/Rate Structure
June — Document review and recommendations for adoption
Next Committee meeting May 28, 2019 4:00 pm
ADJOURNMENT: at 5:24 pm
Respectfully submitted,
Tain a Glick
Public Works Administrative Assistant
Ashland Water Advisory Ad -Hoc Committee (AWAC)
April 23, 2019
Page 2 of 2
r
o
El
49
A&�
I
It
0
(A
0
10 #A"Wo
4,-)
ul
\\,
0
Ol
am"am*
4-j
M
0
C L
4-
0
4-J1
M
I
I
I
I
I
:�.
Am
V)
U
0
o
0 0 CD 0 C
0 0 CD 0 0
0 00 l0 mot'
(POW) pueuaaQ
ar
0 0 CD 0 C
0 0 CD 0 0
0 00 l0 mot'
(POW) pueuaaQ
ar
•-
Q
�aA
Q
70
O
O
�
N
�
*Mumma=
0
'a
O
Romal
�
w
woo
�Mimi
E
O1
a ammom
70
O
�
�
U
U)
01
EM
sommm
�
a
U
N
�
O
N
�
(6
�
Q
Q
U
i
(6
O
�
Q
O
Emmom
+mj
IN sommm
NMI
`a0
�
0
O
�
(D
�
�>
U
�
(DI
ri
N
I
a ,r
�r
l
wo
r
U)
0
iwmmwmoww�a
ww
wwwunw
wm
soon=
�,
mmwwnwuuwmu
�m
Sul
0
0
o"I'mami
vl,�
0
0
U)
ww
lommon"
Affiffo
samom
Z31
Iwre wwwiur
oawuts..
m�mmwww�ww
mnmum�
w�p
� rnuwww�wx
Iwo.
upawm
+—J;
a
Room=
iw
U)
�u
imm
wuw�
�wmmuuw�wwwmwrwwa
a�
i
ci
4)
000
mommmum
i
I
rod
*qr,
"It'
CO
I
0
co
uo
P%*4
CN
N
U
i
0
�0
..
1
CL
mI
E
o00%70
co
o0
vZomm
Lomus
(D
.. , .
(D
him":
(D
V'I
0()
7
.
0#00
A�
"a
co
CO
>ro
M
I'
0
i
40
".
co w
cu
i
E mom
Q0
0
lommm
w
III
Ol
77
U
cl
Mgt
N
U
�
�
U7C3
�
0
C:
Ln
�
o
�
N
Q
i
.O
i
�
cl
�
i
0',
�
mo
(1)
N
�
H
H
r-I
CN
(Y)
70
bD
�
II
E�
H
O
00
(D
II
(B
�(D
a
Q
Z �iaaaaa�;
I�WWUWW�WWmNWWWdDUDW'N!'U9
0.
CLII.
mPo
0
:5
C).
0
m
mlmmM
q�
mlummm�
Y ommmm
un�mmm
m� mII
I�
m
�§loommum
U)
m
70
10
H
W
C)i
00
z
C)
U)
4—j
C:
ww
E
valml
SEEN=
—0
C)
M
0
mumumomm
w
I
I
i
mm
�wwl
mmwmmm
wun'II�
0
LL
u �
u
i
m
I
(Ul
wmm
Woo
wuw' N-N
uuuuwuwml
06
IN MINES=
M
mwmI
0
2mm
wu
summoff=
(1)awe
>
>
(y)
(D
Wl
st000
U)
iiii
�iII
l
,e,
G,
<".�.,
.,,.r
i
,,,, , ,, ,, ,,,,,,,
i ,, ,,.. ,,.,.. ,,,,,, ,,,,,..
,, ,: ., ,,,,,,,, ,, ;,
,. ,,,,,,,,.,., ,,,,,,,,,, ,.,. ,
���/
//�// /j
%�
/���/
��/
//�',
�;
,,,,,
..
r1�'"
���j
////jj///
��
;.. /.....
��� //��1/����jµ
:;�j//
.// I
:�
/����j
�j����
j
� jj����j
, �j�jj',..
,����1 � /
%���� �j
/� /// �
/�//���
������
�//�� j�jj�j�,
�',,
rr
1
„,
i
,,,., w..
,,,., .,,.
5 1 WATER SYSTEM ANALYSIS
INTRODUCTION
This chapter presents the capacity analysis of the City of Ashland (City) water system. Individual
water system components were analyzed to determine the ability to meet policies and design criteria
under existing and future water demand conditions (presented in Chapter 4). The policies and
criteria are summarized below for each analysis.
CHANGES SINCE LAST WATER MASTER PLAN
Since completion of the City's last Water Master Plan, several improvements have been decided
upon and implemented that influence the system analysis. These include the following:
• Construction of the Talent -Ashland -Phoenix (TAP) Supply System. This new emergency
supply provides Medford Water Commission (MWC) water to the City and makes use of the
City's Lost Creek Reservoir water rights purchased for this purpose.
• Construction of the New Park Estates Pump Station. This pump station upgrade provides
a much higher level of reliability and ire protection for customers at the highest elevations in
the City.
� Construction of the New Terrace Street Pump Station. This pump station upgrade
improves the City's ability to boost Talent Irrigation District (TID) supply to the WTP and
new WTP.
• New Water Treatment Plant Decision on Capacity and Location. The new Water
Treatment Plant (WTP) is planned to be a 7.5-million gallons per day (mgd) capacity plant
(expandable to 10 mgd). The location of the plant is at the granite quarry southwest of the
Granite Reservoir.
• Pipe Improvement Projects. Several pipe improvements have also been made related to
new development and improving distribution system capacity.
GENERAL SYSTEM CHALLENGES
Challenge 1 : Moving from a Gravity System to a Partial Gravity System
Goal: Reduce pumping to Crowson Zones
• Allow Granite Zones to expand
• Reduce/Eliminate PRVs supplying from. Crowson to Granite
Challenge 2: Granite Tank Is Aging and Is In A Poor Location
Goal: Abandon tank without compromising system hydraulics
• Confirm ability of TAP system to function without tank
■ Can. WTP Clearwells replace Granite tan1�,- functionality completely?
5-1
Z:1Botheffiata=A11016-096 WMP 2016\10 Reports12018-WMPCH5.dmx (5r=1912:33 PM)
CHAPTER 5
Challenge 3: Oversized Alsing Reservoir
Goal: Expand service area to achieve reservoir turnover
CITY of ASHLAN❑ WATER MASTER PLAN UPDATE
Challenge 4: Fire Flow Deficiencies at Highest Customers (Park Estates and South Mountain)
Goal: Now that PS is rebuilt, increase pipe sizes, expand service area to Crowson Zone 4
• Reconnect piping for high Crowson zone I customers
Challenge 3: TAP Emergency Supply Cannot Reach Crowson Zone
Coal: Identify ideal location for permanent pump station
• Could be a delayed project -- City has a temporary pump station location for this if needed.
Challenge 6: Pressure Extremes in Many Locations
Goal: Rezone where feasible.
Challenge 7: Inability to Meet Higher Fire Flow Standards
Goal: Build in distribution capacity over time.
Challenge 8: Storage Deficiency (or Not)
Goal: Revise criteria to account for redundant, reliable supply sources
Challenge 9: Many Aging, Undersized Pipes
Goal: Replace as budget allows
5-2
Z-.&the1N)ata=X1016-096 WMP 2016\10 ReportsM18-WMPCH5.docx 5i2=i 912:33 PM
WATER SYSTEM ANALYSIS CHAPTER 5
This section evaluates the City's water, supplies for, meeting existing and future demands of the water
service area.
Goal Element
Goal
Water, System
Have sufficient supply to ineet projected demands that have reduced
Capacio)
based on 5 percent additional conservation asie year 20109. However,
City will have a goal of achieving 15 petcent conservation.
Water System
Community will accept curtailments of 45 percent during a severe
Reliability
drought. The City will pi`or-t-
I I IZCI SOLINe Nvater available CLIT'ng, drought
conditions.
Water Systein,
Implement redundant sup plyper oject to restore fire pt-otection and
Redundancy
supplyfor indoor water use shortly after a treatment plant outage.
Stipply AM with, red'Undiant supply.,
Regulatoiy'
Meet or exceed all current and anticipated regulatory requirements
Requirements
HICI-Liding, cross connection prograin anproVretnents.
0 Water System Capacifty: New WTP has adequate capacity to supply 2040 Maximum Day
Demands (MDD) and beyond (see Figure 5.1).
ol The new WTP is located lower in elevation than the City's upper pressure zones
served by the Crowson Reservoir (see Figure 5.2). (The existing WTP serves the
Crowson Zone by gravity).To minimize pumping to Crowson Reservoir, the City
should consider system changes to reduce supply from the Crowson zones to zones
that can be supplied by gravity from the new WTP.
0 Water System Reliability: During water supply disruption or drought conditions, the City's
supply strategy is as follows in order of priority:
1. Supply East/West Fork Ashland Creek water as available to the New WTP (stored in
Reeder Reservoir and soon to be able to bypass Reeder Reservoir).
I Supplement Ashland Creek water with Talent Irrigation District (TID) water to the
New WTP.
3. Use the TAP Supply System to supply water from. MWC.
4. Curtail supply according to the City's Water Curtailment Plan.
N
2ABothefflatMCOX1016-096 WMP 2016klO ReportsM18-WMPCH5,docx 0212019 12:33 PM
CHAPTER 5 CITY OF ASHLAND WATER MASTER PLAN UPDATE
• Water System Redundancy-, Neither the firm or total TAP Supply System capacity is ab�le
to, meet Average Day Demands (ADD) witho�ut conservation in the case of a WTP outage
(see Fl*gure 5.3).
o The 00) plaiis to provide 3'. 0 ingd of supply capaci'o) through, Hie TAP, sj)steni.
• Regulatory Requi'remarts: The City is meeting all regulatory requirements with the,
exception of actively implementing cross -connect on control.
Figure 5-1 - New WTP Capacity vs. Maximum Day D�emanProjections
New WTP Capacity vs. Maximum Day D�emand Pro,jections
gMMM;[T4M3!=3j mnlylym
ffj
ZABothellUatACOM1016-0% WMP 2016\10 Reports' 20118VMPCH5.doa 512212099 12:33 PM
WATER SYSTEM ANALYSIS CHAPTER 5
Figure 5-3 TAP Supply Capacity vs., Average Day Demand Projections
-a
w 3.00
E
2.501
E
2.0�O
1.50,
U 1.00
01,50,
0.00
2020
ADD (No Conservation!) (mgd)
ADD (With Conservation) (mgd)
TAP BPS Firm Capacity
TAP11"BiPSTotal Capacity (3.01 mgd)
... . . ....... -
2025 2030 2035 2040
Yea r
SUPPLY RECOMMENDATIONS
Construct new 'DTP and associated projects:
• 7.5-mgd WTP (expandable to, 10.0 mgd).
• Two (2) 0.85-MG Cleat -wells for storage.
• Pump Station to boost water from the new WTP to the Crowson Reservoir (see pump
station analysis below).
• Piping and Valving to, supply Granite Zones.
• Emergency Ashland Creek Intake.
• SCAD,A System Upgrades.
49 TAP Supply Expand to 3.0 mgd
o Additional pump at Ashland TAP BPS
cal Expansion of the Talent TAP BPS
of Potential expansion of the Regional TAP BPS
o TAP System Transmission Capacity Improvements
0 Transmission piping improvements and rezoning to minimize pumping to Crowson Reservoir
and associated pressure zones (see pipe projects below).
M
ZABothefflata=A\1016-006 WMP 20W10 RepoftSVO18-WMPGH5.docx 512212019 12,33 Phi
CHAPTER 5 CITY of ASHLAND WATER MASTER PLAN UPDATE
STORAGE FACILITIES
This section evaluates the capacity of the City's existing water storage tanks to meet the existing and
future storage requirements of the system.
Water storage is typically made up of the following components: operational storage; emergency
storage; and fire flow storage. Each storage component serves a different purpose and will vary from
system to system. A definition of each storage component and the criteria used to evaluate the
capacity of the City's storage tanks is provided below.
Operational Storage — Volume of the reservoir used to supply the water system under peak demand
conditions when the system demand exceeds the total rate of supply of the sources. In the past, the
City has calculated operational storage as 25 percent of MDD for the zone it serves. Another
criterion is to calculate the volume needed to meet peak hour demands that supplies to the zone are
unable to meet. Also called "Equalization Storage."
Emergency Storage -- Volume of the reservoir used to supply the water system under emergency
conditions when supply facilities are out of service due to equipment failures, power outages, loss of
supply, transmission main breaks, and any other situation that disrupts the supply source. Common
emergency criteria in the state of Oregon is to assume emergency storage as two times ADD
(approximately equivalent to one times MDD). The City's previous criteria assumed 25 percent of
MDD for emergency storage. This lower criteria correlates to the City constructing a new reliable
WTP.
Fire Flojv Storage — Volume of the reservoir used to supply water to the system at the maximum
rate and duration required to extinguish a fire at the building with the highest fire flow requirement
in the zone. The magnitude of the fire flow storage is the product of the fire flow rate and duration of
the operating area's highest fire flow needs. These fire flow planning goals were presented in
Chapter 4.
.Testing of Storage — Some water systems allow for "nesting" of fire flog and emergency storage,
meaning that it is assumed that a fire and a supply disruption would not happen at the same time and
therefore only the greater of the two storage volumes is used in the storage analysis.
5-5
ZABothefflata100A11016-096 WMP 20*10 Reporfsl2018-WMPCH5.docx 5f22t201912.33 PM
WATER SSTEM ANALYSI-S
fFtl #I
Parameter
CritcHOR
Operational
0'.25 x Maximum Day Demand of the area served by each reservoir
Storage
Or
(PHI) — Qs)('1501 mlliutes), but i'll tio case less thati. zero
Where-,
ES=Equall'zation Storage iti Gallons
P'HD = Peak Hour Deniand,,11.1 gpm
Qs = Stim of all itistalled, and active sources, except emergeticy supply, in gpin,
Fire Storage
Provide volume for shigle most severe requiredfire flow wid durationfor each
t',eser-voir service area.
System -wide, provide volumejor two largestfires.
Emergeiicy
0. 5 x Maximum Day Demand of the area se�rved by each reservoir
Storage
Or
ES = 011L)D — 1-f"irm Sup ply Cal),acitj) (I daj), or 200, gj,.,)d,per ERU
The total combined storage capacity of the City's reservoirs is 6.7 million gallons. The City's
original criteria �for storage requirements for operatioinal, emergency, and fire flow are, compared to
the existing storage to determine storage adequacy for the planning periods, as summarized in Table
5-31 The table includes the storage surplus/deficiency. As seen at the end of the table, under the
City's original criteria, the City would have an exist-Ing storage deficit of 037 MG and a 2040 deficit
of 1.34 MG.,
M
ZABothelMatakCOAM16a6 WMP MUM ReportsVO18-Wh1PCH5,do cx 5/22)2019 12:33 PM
Existime' a Store a Evluation,
Q1 9
we"
Z.,)Bothe,IIUaWCOA\I 016-096 WKIP 2016M ReportsQ018-WMPCH5.docx 512212019 12,:33 PM
WATER SYSTEM ANALYSIS
Table 5-4 presents the revised storage analysis using the adjusted criteria, the expanded Alsing
Reservoir service area, and reduced demand due to conservation.
we
ZABothelMaWCOM1016-096 WNIP 2016110 ReporW2018-WMPCH5.docx 5/221201g 12:33 PM
Table 5-4
Storage Evaluation — Revision 1
2020, I
20:30,
2040
CROWSON
0'.3,7
0.42
0.38
GRAN ITE
0.54
0.67
01.517
ALSING
0.43
0.51
0.48
FALLON
0.29
0.29
0.29
Total System
1.63
1.89
1.72
Granite Reservoir is in major need of replacement or removal. A recent estimate for improvements
was $560,000. To replace the Granite Reservoir, the design for the new WTP is plannmg on
including two (2) 0.85-MG clearwells that will serve as system storage. The first cleat -well will be
built with the W'TP. The second is planned for when Granite is abandoned. Table 5-5 presents the
final storage evaluation considering, the removal of the Granite Reservoir and addition of the two
0.8�5-MG clearwells at the new ,
Table 5-5
1
Storage Evaluation — Rernoval of Granite Reservoir
Storage Excess/(Deflcit) (MG)
.. ...... ....
2020
2030
2040
CROWSON
037
0.42
038
GRA�NITF 0. 14
01�0 27
0.17'
ALSI
0.4
0,51
FALLON
0.29
0,29i
0.29
Total System
1.23
1,.49
1.32
FIMI"IZIMF4 V1,11-14*1 :41,19 MID
Figure 54 shows, the recommended Alsing Zone Expansi , on, and other potential �rezoning Specific
locations of valve reconnections should be confirmed with City staff.
IM
11M
0 Revise storage criteria to account for redundant system supplies.
Z-Moth ell\Da WCOMI 0 16-096 WMP 20161101 Reports= 8-WMPCH 5.docx 5/22/201912.33 PM
WATER SYSTEM AN,
• Expand the Alsing Reservoir Service Area
o New PRV on Tolman Creek Road and Sis,kiyou Blvd.
• Construct two (2) 0.85-MG clearwells, at the New WTP to serve the Granite and Crowson
Zones.,
I r�
o As long as PRVs, from Crowson to Granite are set to provide tire protection pressures,
fire volume for Granite can be stored in the, Crowson Resei voir.
N&MIZ ��Mi 111`1"I
liq 111 111111111 111111111 !!!111 F
M' 1141rair, I . I I
V=A W
0 , 0
Plar:ametei- Criterion
Capacity for service levels with storage, Supply Maximum Day Demand to service zone
facilities assuming the single largest capacity purn is
firm capacity)
Capacity for service levels with no Supply Peak Hour Demand and fire flow assuming the
storage facilities single largest capacity pump is offline (i.e., firm
capacity).
Power Supply New pump stations require a main power source and an
emergency source.
Secondary power source for new pumps stations to be
sized to meet full pump station demands.
City will plan and design facilities, to optiniize energ,y
efficiency.
PUMP STATION ANALYSIS
Tables 5-7 and 5-8, present the required puniping capacity and pump station capacity analysis -results
respectively.
• The New WTP to Crowson Reservoir Pump Station should be sized to provide
approximately 1,8010, to 2,100 gpm to supply the Crowson and Alsing Zones.
• The Hillview Pump Station meets the City's criteria through 2040 but may be deficient in
meeting MDD if the Alsing Reservoir service area expands.
o With the planned expansion the pump station capacity should be XXX gpm.
5-11
ZABAOUXOAMIM96 WhIP 20100 Rep ortsV018-WMPCH5.docx 5122120ig 12:33 PM
o The H llview Pump Station is aging almost 40 years o1 and warrants replacement
in the next 10 years,
., erry Pump Stations et the "1
Souths criteria through 200,
The Pump
Stationocurrently
..
Table e.e
Pump Station Capac'fty RequiremenI
li
VI 0 I 111 . •
Largest
Pump Station Zonesr
�Fire Flow
Required
Required
SU ply
Supply
Purnping Zones With Storage (Criteria MDD)
New \/VTP to
1«
Crowson Zones 1-8, Alsing Zones,
Crowson PS
'" onCrowson w ■
�
� MIS IIM
Pumping ones Without _ Storage'"
South Mountain
Crowson
Park Estates;
me
mmm�
Table 5-8 Pump Station Capacity Evaluatioll
aTotal2040
. N
�"
ump
2020 "` ss
I
Required
Required
•Station Zones
1
Supply
N
. N
*' •
i 'i
1--------------------------------------
Purnping Zones Without Storage e. P
South
u Moiuntain
Crowson
o Zone
e 4
I
Park Estates
Crowson '"s 7 a'
The New WTP to Crowson Reservoir Pump Station should have firm capacity of
approximately 2, 100 gpm to su/ i
Z %othefiVakaICOXI018 MP 2010110 Repor 018-W%IP H .fix 122/201912:33 P
WATER SYSTEM ANALYSIS
t
o The required capacity may be as low as 1,800 gpm, if the City is, able to rezone low
elevation customers in Crowson Zones 2 and 6 to be supplied by Granite Zone 1.
Hillview Pump Station Replacement. Replace the Hillview Pump Station to bring, this pump
station to current design standards and avoid high maintenance costs.
The ideal static pressure of water: supplied to customers is between 40 and 80 pounds per square inc
Pressures, within a water distribution system are commonly as high as 120!requiring
pressure regulators on individual service lines to, reduce the pressure to 80 psi or less., It is difficult
for the City"s water system (and most others) to maintain, distribution pressures between 4,0 and
80 psi, primarily due to the, topography of the water service area. I
The City has adopted the following service pressure criteria:
* Minimum Pressure (during Peak Hour Demand): 30 psi
• Minimum Pressure (during Fire Flolw): 20 p
• Maximum Pressure-. 120 psi I
Table 5-9 lists each of the City's pressure zones, the highest and lowest elevation served 'in each
zone, and the minimum and maximum distribution system pressures within each zone based on
maximum static water conditions (full reservoirs with no demand). While this table presents the
results of the pressure evaluations based on the adequacy of the pressure zones under static
conditions, the hydraulic analysis section later in this chapter presents the results, of the pressure
evaluations based on the adequacy of the water mains under dynamic conditions.,
As seen in the table, .any pressure zones, exceed the maximum pressure to customers. This, is due to
the complex topography and pipe networldng within the City.
Table 5-9 Minimium and Maximum Distribution System Static ---Pressures
Highest Elevation Served, Lowest Elevation Served
Pressure Zone
Elevation (ft)
Static Pressure sl
Elevation t................
_ Static Pressure (psi)
Granite Zone 1 (2170)
2024
63
1788
165
Granite Zone 2 (2060)
1846
58
1724
110,
Granite Zone 3 (1980)
1852
90
1757
131
Crowson Zone 1 (2420)
23,59
145
1884
35
Crowson Zone 2 (22001)
213;8
35
1884
145
Crowson Zone 3 (2270)
2153
51
1955
136
ZABothefflatXOM1016-096 WMP 2,016114 ReportsVO18-WMPCH5,dOGx 5122/2,019 12M Phi
CHAPTER 5
CITY of ASHLAND WATER MASTER PLAN UPDATE
Crowson Zone 4 (2640)
2476
71
2341
130
Crowson Zone 5 (2270)
2058
92
2043
98
Crowson Zone 6 (2290)
2100
82
1911
164
Crowson Zone 7 (2570)
2371
86
2370
86
Crowson Zone 8 (2570)
2578
14
2382
98
Fallon Zone 1 (2586)
2431
67
2248
146
Fallon Zone 2 (2470)
2396
32
2224
107
Alsing Zone 1 (2552)
2336
94
2165
168
PRESSURE ZONE RECOMMENDATIONS
Granite Zone I
• Perform a rezoning study to lower pressures to low elevation customers.
o Rezone customers north of Siskiyou Blvd from Normal Ave to Crowson Road to be
Crowson Zone 6. (This is assumed as part of the Alsing Storage Area expansion).
o Possibly rezone customers south of Siskiyou Blvd from Normal Ave to Crowson
Road to reduce high pressure customers.
• Rezone customers in Normal Avenue, Ray Lane, and Lit Lame between Ashland Street and
Siskiyou Blvd to be served by the Crowson 6 zone.
Granite Zone 3
• Reduce PRAT settings to lower overall zone pressure.
Crowson Zone I
• Perform a rezoning study to lower pressures to low elevation customers.
• For high elevation customers on Emma Street, reconnect piping to supply customers from
Crowson zone 4.
Crowson Zone 2
• Extend Granite Zone 1 to supply lower elevation customers in this zone. This
recommendation also reduces the required pumping from the WTP to the Crowson
Reservoir.
■ New Transmission Pipe in East Main Street. Install a new 12-inch transmission
supply pipe from Walker Road across Interstate 5 (1-5) to connect to Crowson
Zone 2.
• This project could be implemented as part of development of undeveloped
lands in the north east areas of the City.
■ This project will also serve lower elevation customers in Crowson Zone 6.
■ Rezone Crowson Zone 2: Identify the correct valve locations to isolate the lower
elevation customers in Crowson Zone 2 and supply them from Granite zone 1.
* Allow Alsing Reservoir to supply emergency supply to the zone by
installing/setting PRVs to meet reduced pressures for fire flow only.
5- 4
BBotheffiatMCOA11416-M WMP 2016\10 Reports12818-WMPCH5.aocx 5122I241912:33 Phi
WATER SYSTEM ANALYSIS
Crowson Zone 3
• Reduce PRV settings to lower overall zone pressure.
Crowson Zone 4
CHAPTER 5
• Extend supply from Crowson Zone 7 (supplied by the new Park Estates Pump Station and
reduced in pressure by PRV 12) to supply customers in Crowson Zone 4.
■ Install piping from Morton Street to Ivy Lane.
■ Abandon South Mountain Pump Station.
■ Expand to supply high elevation customers from Crowson Zone 1.
Crowson Zone 5
• While this zone has no identified pressure issues, the zone could be connected to Crowson
.Zone 6.
Crowson Zone 6
• Extend Granite Zone I to supply lower elevation customers in these zones. This
recommendation also reduces the required pumping from the wTP to the Crowson
Reservoir.
o New Transmission Pipe in East Main Street, Install a new 1 Z--inch transmission
supply pipe from Walker Road across Interstate 5 (I-5) to Crocker Street.
o Rezone Crowson Zone 6: Isolate the lower elevation customers in Crowson Zone 6
north of Ashland Street and supply from Granite zone 1.
■ Allow Alsing Reservoir to supply operational supply to the zone by
installing/setting PRVs to meet normal pressures.
Crowson Zone 7
• Extend to Crowson Zone 4 (see Crowson Zone 4 above).
Crowson Zone S
• None
DISTRIBUTION AND TRANSMISSION SYSTEM
This section evaluates the City's existing distribution and transmission system (i.e., water mains) to
determine if they are adequately sized and looped to provide the necessary flow rates and pressures
to meet the existing and future requirements of the system.
DISTRIBUTION SYSTEM ANALYSIS CRITERIA
Distribution and transmission mains must be capable of adequately and reliably conveying water
throughout the system at acceptable flow rates and pressures. Hydraulic analyses of the existing
system were performed under PHD conditions to evaluate its pressure capabilities and identify
system deficiencies. The existing system was also analyzed under MDD conditions with fire flow
demands to evaluate the fire flow capabilities. Additional hydraulic analyses were then performed
with the same hydraulic model under future PHD and MDD conditions and with the proposed
5-5
2-ABothe1WaWC4Al1016-096 WMP 291W0 Reports12418-WMPCCH5.docx 021241912:33 PM
CHAPTER 5 CITY OF ASHLAND WATER MASTER PLAN UPDATE
improvements to demonstrate that the identified improvements will eliminate the deficiencies and
meet the requirements far into the future. The following is a description of the hydraulic model, the
operational conditions, and facility settings used in the analyses.
As discussed in the Pressure Zones section of this chapter, ideal water pressures delivered to
customers are in the range of 40 to 80 psi and the City's criteria is to deliver pressures between 30
and 120 psi.
� 40MIMAMIR411
Description
A computer -based hydraulic model of the existing water system was updated to version 81 of the
waterGEMSO program (developed by Bentley Systems, Inca with the City's most recent GIS
shapefile, to reflect the best --known information on distribution system geometry and pipe
characteristics, including diameter, material, and installation year. This was further refined to
include the latest construction projects and changes to the system.
Hydraulic model pipe roughness coefficients were initialized with computed estimates based on the
water main material and age information from the City's water main GIS shapefile. Based on the
premise that the internal surface of water mains become rougher as they get older, older water mains
were assigned higher roughness coefficients than newer water mains.
Demand Data
The hydraulic model of the existing system contains demands based on 2014 individual customer
meter water demand data provided by the City. Demand data for each parcel was distributed to the
closest representative junction node of the model based on the recorded usage. These demands were
increased to represent 2020 demands. The pealing factors shown in Chapter 4 were used to analyze
the system under PHD and MDD conditions.
Facilities
The hydraulic model of the existing system contains all active existing system facilities. The facility
settings for the pressure analyses corresponded to a PHD event in the water system. All sources of
supply were set to operate at constant rates (i.e. MDD). Reservoir levels were modeled to reflect full
utilization of operational storage.
The hydraulic model for the fire flow analyses contained settings that correspond to MDD events.
All sources of supply were set to operate at constant MDD rates, and the reservoir levels were
modeled to reflect full utilization of operational, emergency, and fire flow storage based on the
maximum planning --level fire flow requirement.
Calibration
The model was calibrated as part of this Plan. Calibration is achieved by adjusting the roughness
coefficients of the water mains in the model so the resulting pressures and flows from the hydraulic
analyses closely match the pressures and flows from actual field tests under similar demand and
operating conditions. Initial Darcy-Weisbach roughness coefficients were entered in the model based
5-6
ZABothefMata\COX1416-096 WMP 2416M Repodsl201$-WMPCH5.doa 512201912:33 PM
WATER SYSTEM ANALYSIS
CHAPTER 5
on computed estimates of the coefficients from available pipe age and material data. For example,
older water mains were assigned higher roughness coefficients than new water mains; thereby
assuming that the internal surface of water pipe becomes rougher as it gets older.
The model was calibrated using twenty-five hydrant flow tests performed in the system in the spring
of 2016. The model is considered calibrated when model results are within 10 percent of the field
results. After identifying a few closed/partially closed valves in the system, and adjusting roughness
coefficients, the modeled results closely match (within 10 percent) the field results for all 25 tests,
thus the model is considered adequately calibrated for use in the following system analyses.
HYDRAULIC ANALYSIS
Pressure and fire flow analyses of the existing system were performed using the model for 2020,
2030, and 2040.
Pressure Analysis
Figure 5-5 presents a map of system pressures color coded by pressure range during Peak Hour
Demands.
• Low pressures at high elevation customers within a zone.
• Many locations of high pressures exceeding 120 psi at low elevation customers within a
zone.
Crowson Zones are supplying Granite zones over 2 mgd through PRv stations.
Fire Flow Analysis
Fire flow demands were assigned to the water system based on land use and the City's fire criteria
presented in Chapter 4 and are shown in Figure 5-6. Maps of fire flow results are shown in Figure
5-7. The maps are color coded to show if each junction in the system satisfies, does not satisfy, or is
within 10 percent of delivering assigned fire flows (10 percent is within the error of the model).
■ Deficiencies where fire is unavailable while trying to maintain 20 psi at highest elevation
customers.
Deficiencies where neighborhood pipes were built before more stringent fire codes were
adopted. Fire districts commonly classify these buildings as "existing non -conforming" and
since they met previous fire code requirements when they were constructed, improvements to
these areas are considered a low priority.
o Several locations of fire flow below 750 gpm.
Several more deficiencies than the previous master plan because fire flows were assigned at
every hydrant in the current system.
DISTRIBUTION SYSTEM RECOMMENDATIONS
• Rezone as described above in Pressure zone Recommendations.
■ Increase transmission capacity across Granite zone 1.
a-7
ZABotheJMata\C0A\10i6-096 WMP 201W0 Repodss12418-WMPCH5.docx 51221201912:33 PM
CHAPTER 5
CITY of ASHLAND WATER MASTER PLAN UPDATE
o Reconnect Granite Zone 1 and Crowson Zone 1 pipelines in Granite Street to make
the larger pipe available to Granite Zone 1.
o Replace upper section of Granite Zone 1 transmission main (from new WTP to
connection to 24-inch pipe).
o other transmission improvements.
Set PRVs from Crowson and Alsing Zones to Granite Zones to only supply fire flow.
o Abandon PRV 9.
■ Extend transmission capacity of Granite .Zone 1 in East Main Street to serve low elevation
customers and new growth to the east of the system.
• Local pipe upsizing from 4- and 6-inch pipes to 8-inch pipes and larger.
Recommended pipe improvements are presented in Chapter 6 —Capital Improvement Plan to
address pressure and fire deficiencies (see Table 6-3).
Maintenance Recommendations
Annual Pipe Replacement
o Many aging and undersized pipes throughout system.
• Hydrant Replacement
o Many hydrants do not meet current standards for hydrants.
TELEMETRY AND SUPERVISORY CONTROL SYSTEM
This section evaluates the City's existing telemetry and supervisory control system to identify
deficiencies related to its condition and current operational capability.
EVALUATION AND RECOMMENDATIONS
The City's SCADA System is headquartered at the water Treatment Plant. System facilities
including source, storage, and pumping, can be controlled with the telemetry system. At the WTP
and on remote computers, City staff can monitor and control supplies, reservoir levels, and pump
station flows. The system communicates to all facilities using radio towers. SCADA System
hardware and software require regular maintenance and occasional replacement.
There are no signficant deficiencies with the existing telemetry/SCADA system; however, some
minor changes would improve operations and management. As part of the new WTP updates, the
City is reviewing alternatives to the current SCADA software system, which requires several third -
party applications to achieve the functionality desired by staff. As a result, the City may be required
to replace the radio towers throughout the system. Further details are discussed in Chapter 6 —
Capital Improvement Plan.
5-1 8
Z:SotheiinaMCOM1416-096 W€ IP 2416M ReportsU018-WhIPCH5.docx 512=1912:33 PM
0 0
u
0
I
C:)
u
Gig
b
b
FD
b
b
b b
C>
m
C)
CD
<D
CD
*Z
o<
pp
i�Avd
I-=
llb
gg m
Cot
00a 0
rvn
04 1171
00
>
P4 NO NN'Z" ori. g
a "
o o �C4 0 a
0
U U
ONZ- 0 t- 00
Ln
4w
U L) of L) tj
1.04
0 0 0 0 0
W� LA tM V.
tn t1l
tn 7t c
li le, i 14 It'll
I 3UOZ JU31UI 17181 Off,
to�
4-0
CQ
uIf
sv
ti
ON
C to ne m 0 G
CL
"Z5
F—
ac -6 C)
al 0 1 cl U. z 0 0
z 3 c a .0 E -5 1. ?i 1C V) I
0 < q IN 44Z
Ln
0 -9-9 sde3uo 9 ua dxg al,uoZ �uisIV
e �
e__zo � _��
Lith
a
�� "
� � � ei n d
41 a5�535' arch 15 r� as
jaaq Z09C SdIJ LonoS w6aap aueldOIELS C96L CI:walsAS ajeutp ,o swej4:Alg, pm-sidaauno 6utuaaa�j pue uaisued 3 auoz 6ulsly O-c, aan6t�1��4"�51 1 Lied dW"�r'w"G I� -9LojG Vo3\ujLC7VIa41og%-.2
�7
NI
r4 v
sains 3 j IIJSIX3 OZ^Z
u
emBij f
wmt �,� m"a
A
9
C4 CPJ X
0 0
c c
N N N
AN'
0 0 N
... ... . ............ .
W C C: �= — .
LL LL
C3 ol
a C) C) a
:,jp
f- r� co (ol
N Cq CN
to (0 Lo 0 a
CA CN
'p, loe
A
4
0 0 0 0 0 0
N N N N N N C4
0 a 0 a 0 0 (11),,,//,,/ . . . . .
j g/
I ; 4 0
2 2 2 2 2 "A
ol < 0 L) 0 0
o, co a a o
N! (n u
r- CD
U-1 1 04
04 C14 04
14
06
V",
4/
C
EL
fn
40
W/ I
JI,
. ...... . ... .. ..
00 oAl
0 AUI�7
Co a If' 1111�",,�,m"ljj,,,�r��,1,1,1,f
d3 f
03
IL co �2 0 43
zo
Al I'll , IN 0 0 4,
C,2
C14 0 C3
j
di v C4 m co, A
ff
cn n/
...... . . .. . .
/ m/f
0111
7—
N,
Zlmi
IF� lk
2,
ji, Al", Wl
A
ID
j,
,�,( . . . . . .. .
(A
IIJ
Tem
. .. ..... ..... .
cn c4
C,
CL
/d/or
ra, BI
. .. . .. . . . .
:3
0
off
Vol
c 0
�(Aw Flo
di 'a
i(' 0�1,�f�, 01,11",
W/
�o
yg�'�, 0
44
W,V/ W
Inj 0
f. . .. ... . .. .... . .
14"
a 0
mgtr r WIr JI
2
.. ... . . %
C
0 00
V,
01
_7
INUM
Y"o�/ w
IN
0
f
7 J�
f LL
T, "a' c4
U) 0 4
J,
IL \�X
in
C,
\CD
mom
a. 8'�
Wn
K x".
""N
c c;
I UJ
Z, LF....... . ... P
gj
A/m,
r
if
...... . .. ..
....... . ..... N
'31
Iv
....... . .. .
f
*01
"P,
MOM)
X/ ...
le,
Al
bN&, IV
A
1 01, 1,
IF
011
Z,19)
CL
�qgjpp(
po///
YNI
M,
4j
__3 ho�o
11 , - -_ 1
W,
Ma
. ..... .
.. . ..................... . ......... . ............. ....
. ............... .... .. .. ....... ..... . .. . . ............................
Wad Z09E SdIJ 14TOS UOOWO OVEWMS CM OVN:LUD;SAS OleUIPJOOO suieppq pxursluawailnDaN moij aiij 9-S ainDizAGEVASIOMOZ d'ViM 960-%Ot\VO3ME?OlJlaL8OER:Z
Ri
solouelol a tu,045;is FjiuljslX3 OZOZ
L
.. .. .. . . .....
ej n ol
laaJ Z09C SdlJ WOS U00010 aUL-1dal21S EM (1VMWajSAS @jUUlPJWj 5UJU;q-�AE1 pxw-tiiss',)Uarjljd(j m"Ll Uj!:i WiJjtiiA!Z; UU115�XZJ UI&U6 L-S dJIIU!,
dVjM UdU-jjLU�jVUJXltZjUUUjd4juHj�L
�v 'M
7"
r- co
a 0 cq N ce)
r —
C
0 0 015,
N N
a 0
c c
N N
0 0
43 4) d)
0/1
.2 .2
0
C) U. w 0 0 0 J,
C) 0 (D a a C3 C�
fl- — CO t- f- CO CO
Im
Ln 'T (D C:�
Ln to
C14 C\l 04 N L4
CY C14
cl) Ul) to
0 0 0 0 0
N N N N N N lk/,�
"N'
r_ C: c c
0 0 0 0 0 0 And/g,
�v0 &,/ ",-/0,
w-
G 1W,31i
2 pi 2 2 R
0, o QA
0 < U 0 0 U
N 0 Ln C� a a 0 ci
LO N C3 I,- �t tl- ol
j/
to
f
ILJ
. . . . . . . . . . . .
7111
(A . . ..... .
if r I
'g-
0
(33
*J1
.... ... ..... ..... .... /
c
LL
cq�:/ 0 01
co N
wif
/ J/
e
A
. ....... ... mugof",-
Z;7- IOU'
Cn
Sj
Igo' j
4-J/
0
J,
N,
1/1, . .. ... . .... ....
i"j''as
or
sw ��l ",164,1 0,0
0-
A
�j
210
>
Well
A
W,
0"
J
-zv
oe
a
famwo /m
h
mg/gp
pomm
J
77
T",
Ile"
3
3
6 OF �l
pi
ol 0 W,
0 V
gg-
vr
�4plgm, oq
"A Im
Pi 0 0
LAIF W oj m =.
�-A
N
7 "A
wor,
....... ... . �, 0 POP,
W,
AI
60
A'j,
11' / p/
7"A 4
a.
Lij
00
.... ... .. .
t:
9D
%
0
�'OV, /�j
C
j
T-; QD U)
V, c
A. dJ LL
r
I U, 1 Wl
0
7,
J,
V/// UJ
//Pg CL 1-5
I . . ..... .....
dg I 'O,g
's --- ......
9N
F-4
'Ir
MOR!"1
4�
jo,
or
it
"A
11/d/rO .00
e
v—,
0
W/
4
P
a
p
p/m&.1a I/////, 1�4/01'11/1'1
J
110111 CL
03
g/j,
f
m
'o,
f
" Y11,11,111
P// IN
go
2
21"
pwI,
F/I
wc, //////////,,,////////// ..........
off/
c Al I
6 I CAPITAL IMPROVEMENT PLAN
INTRODUCTION
This chapter presents the recommended Capital Improvement Plan (CIP) for meeting the City's level
of service goals of continuing to provide safe, reliable water to current and future customers. The
improvements described below were developed from the system analysis described in Chapter 5, as
well as interviews with City staff, to address current and future water demand conditions and to
sustain system reliability. The capital improvement projects are categorized as follows:
• Supply Improvements
• Storage Improvements
• Pump Station Improvements
• Pipe Improvements
• operational Improvements
• Recommended Studies
• Additional Recommendations
A summary of the recommended pipe projects is presented at the end of this chapter in Table 6-2
and the full recommended City CIP is developed and presented in Table 6-3. This summary
provides total probable costs, a brief description, and prioritizes each capital improvement based on
recommended year of implementation. Project priorities should be considered flexible in order to
accommodate concurrent construction during other street opening projects, budgetary constraints,
specific development projects, and other factors that may affect project implementation.
The following sections include the basis for the cost estimates, a brief description of each
improvement, and the recommended prioritization and schedule for implementation.
COST ESTIMATES
Planning level cost estimates were prepared for the recommended projects following the American
Association of Cost Estimators (AACE) Class 5 estimates, which assume 0 to 2 percent of project
definition as appropriate for master planning. This level of opinions of cost are assumed to be within
the range of plus 50 percent to minus 30 percent of the average of contractors' bids. The estimated
costs of the facilities should be expected to change along with the accuracy of the estimate as a
project proceeds into preliminary and final design. These opinions of probable cost are based on year
2019 dollars and no allowance has been made for inflation in future years.
Since construction costs change periodically, an indexing method to adjust present estimates in the
future is useful. The Engineering News Record (ENR) Construction. Cost Index (CCI) is a
commonly used index for this purpose. The CCI used for this study is 11230, the May 2019 20-
Cities Average. For comparison the last water Master Plan CCI for September 2011 was 9030. Thus
6-1
Z:1BOTHELLOATMCOA11016-096 WMP 2016\10 REPORT51DRAFT 2019-WMPCH6.DCCK 5/2212019 12:25 PM
CHAPTER 5
CITY OF PHOENIX WATER MASTER PLAN UPDATE
costs are assumed to be approximately 25% higher than estimated in the previous water Master
Plan.
Estimated total project costs for each project are comprised of multiple components: directly
estimated construction costs, an allowance for contingencies, and an allowance for engineering,
legal, and administrative costs. These components are described below.
CONSTRUCTION COSTS
Planning -level construction costs were estimated assuming a traditional public works procurement
process of design, bidding, award, and construction by a licensed contractor using commonly
accepted means and methods. Property easements or land acquisition and maintenance costs are not
included.
Table 6-1 presents the unit constz-uction cost assumptions for pipe improvements used in the CIP.
These are based on recent, local projects and include mobilization, materials, labor, contractor
overhead and profit, and all elements expected to be included in a contractor's bid. Pump station
costs were estimated using previous projects and comparing building square footage, total motor
power, ultimate capacity, and startup capacity.
Table 6-1
Pipe Installation Unit Costs
Diameter
Unit Construction Cost
(inches)_____201
T $1 Linear Fovt
6
$1 80
8
$225
10
$235
12
$240
16
$250
18
$260
20
$280
24
$300
CONTINGENCIES
A contingency of 30 percent was added to estimated construction costs for all projects except small
pipe improvement projects that require minimal traffic disruption. The allowance for contingencies
covers items such as variations in the project configuration, which are developed during preliminary
design and final design, unforeseen site conditions encountered during construction, and reasonable
project changes during construction. The contingency allowance does not include major project
scope additions or additional costs resulting from permit mitigation requirements (such as wetlands
enhancement) .
ENGINEERING, LEGAL, ADMINISTRATION
Total construction costs were increased by 25 percent to achieve the total project cost. This markup
accounts for engineering design, construction management, legal, and administrative project costs.
Costs shown in the CIP are estimated total project costs.
6-2
2:OOTHELUOATAICOAli016-096 WMP 2016110 REPORTSORAF 2019-WMPCH6.DOCX 50A01912:25 PM
WUNDI WEI` M Wflem WN
Projects that are required for meeting increased demands are eligible to be funded from System
Development Charges, (SDCi) and will be used to estimate an updated SDC value for the City's water
system in Chapter 7. Some projects are recommended for capacity upgrades and maintenance or
other non -growth -related reasons,. The portion eligible for SDC funding was calculated as the
adonal cost for increasing capacity only. SWIlbeh"10, t'1ev)t-,&V)e(L
6 ,
Oth
i-
er projects are identified below to serve future development areas and will be required by
developers to implement when they occur. These projects are noted in Table 6-2, CIP Summary.
As described in Chapter 5, the City's water system has several challenges to overcome.
1. Projects, that resolve significant fire flow deficiencies.
a. Projects that correct low pressure conditions causing fire flow deficiencies.
2. Projects that reduce supply from the Crowson to Granite zones (thereby reduce pumping to
Crowson).
3. Projects that correct high pressure conditionj
This section provides a general description of the recommended improvements and an overview of
the deficiencies they will resolve. Most of the improvements are necessary to resolve existing system
deficiencies. Improvements have also been identified for serving future grow th. Recommended
infrastructure improvements are show in Figure 6-1. Stdlbeitig (Ieeloj)ed.
6-3
ZABOTHELUDATMOM1016-W6 WMP 20W10 REPORT&DRAFT 2019-WMPCH6.DOCX 512212019 12:25 PM
E
0
Q11
N
k6 CL
m
ai u
E
-0
ai
vi
0
Cy
L
0
4)
OL
= a
>
14 as
C
0
.0
0
CL
E
0
;�� U)
rr—SD
CL
=3
0
CL
CL
c
2)
W
4e�
CL
ru
wo
E
cu
aj
= cn
0
=
I
La
4),
U, C-9--
0
a)
CL
C�
-0
CO
I
B
0
'Cry'CryOL
CO eri
CL
a
C3
v)
0CD
4
w
0
E
CL
co
t-- �g
0
0
cs
W > a)
....... ... . .
40
tn
w9Ff.0%
cl
Nr
V-
ate,
C�
CD
C�
LO
C� C=9
Cl
4D
tn Cl)
4^ V)
CD
CD
C:)
to
C�
<0
C)
C�
to
C3
C�
CD CO
U') m
ca 40
C3
C4
C3
A.F* V)arA
60
C> CD
to
5,
C5,
eq
to
44
C:O C3
C) C)
I=t 4cL
Ln 141
C4 eq
CD
C3
CD
to
cl
4^
CD
CD
td
4^ 409,
CD
CD
c:A
C;
to
tO
CD
C�
C�
CD
C
M
4:1
1=1
Iq
Ln
C4 N
CD
C)
Ci
Kn
401,ts34^
C� C3
CD
C,
CD
C�
C3
to
LO
m
4:0
(01
03
04
44
1R.
C4
.
C)
C-5
to
. .... . . . ....
C)
as
CD
C)
CD
to
CD
C>
C�
CD
Cq
.. .... ... - --- ------
C:O
C)
C)
in
Ct
Ct
«xwMb
to
ll��
Z C:)
Cl
C)
C)
ca
........
. .....
to
C:)
CZ)
CD
ci,
Un
401)
4
CO
Mt
f4
L6
CD
CD
to
C� Ct
C> C),
6 =�
6%
4m, im
czk as
C� C�
C� 4=
C)
d=,
c z:�Arm
I— CD
C4
4=1
C;
Ln
C) C)
's
qD,
c; cs
4LO
r-
")
C)
6
to C)
g
to
Ct
Ln Ca
417 C=
�t I=t
4=1 CasC�
to LO
:�. lc:t
C� 00=1
to
4,f*
to Olrll
u
. .
40
.. . ........ ......
6030
ju,
6%
L)
40
40% 4*1*
44
ul7
to 40
1w
4? 4A
.4u
W
48A
ci
Wcry
0
ary
C
0
cc
CL
>*
CL
"a
=3
CL
0
CL
.=
E
a-
CL
_0
c
12
41r1:
OL
tn
T�',
Ir"',
=
13
(D
'C3
2"1
w
E
E
C:
4�
>
F
E
0
0
E
dEca )
LU
z
0
Z
An
E
FynC:
CL
CL
E
F-
0
D
CL ca
0
2
07
lu
4n
tn
(A
t
a) CL
E cn
E
-=
cu
E
m
> E
8 4)
0
:>
w
9
a)
re 0-
- E
CO
ul
aj
cry�O l
co
_0
"ca
C:L 0-
0
LL-
3
a C—
1
x ink.
2
K
E
CL
0.
=3
:3
c
4)
CL
W,
E
a)
aaw
C-1)
E
it
f
OL
0
m
CL 0
CL
U =3
m —
Im 9
0
t
ch ci
CL =
0-
N
M
con con
E
d)
(n
ca
(J)
CL
E 3�
:3 2
CL
Kn 0
W LU
4)
=$ (D
CD
CA
-pz,
E
0 w
a_
a.
CL
CU zt-
0
:3
E M
e
mi
CL
M
CU
m
Uj
W 43
w
tn
cu
cq
CrPN
;�
9
. ..............
-E
12 T
CD
<
L-
(L
. . ..... . ...
g V
IL
F
CU
E Of:
M
C13
in
(n fl-
CO
cy)
cL
M
0 0
0
1-21
0
0 0
R
.... . ...... - - -----
-,
—," "
-
,-"",
----
mr/
CL
cn
E e
a:)ueuajuieLAj
pue suoilejadoi
salpniS
0
papueWWO308
m
r4
Cp
Ln
fl-
a
v
to
U-
2
�r
LL
-0
r
Rummil
I
E
';2 rr
c a
u 7o
w CL -o
; 3
c`a ¢
0
O.
LO
O
Xcl,,
cp
12Q
a
c
c�
a,
E;
e
r
E
E
Ew c a
E r
ra
c
as
it
.... -
...__
_
-
i
S
to to
cc
�
ui r
c, cr
r
cs
cl
i
�Iesr
j
eFr ee a
64 Ub
#.0r
car c
I
cw ua
Nr
_
.. _........._.
_....
...
..... ._
_ .,...�-_.
__ _. _.
Ln
m
_.
Co
Ln
wn
ara +ra
_.
to to
....... .. .........
4n
.._,._ ...._ ..
j
CD
cv
cn
�
t
P-
N
8
wn -r
CD
I
CD
_..,....
.,.,.
_n. ,,.,..
r: Cx
'
__
c1
tea,
rra
u
y
ari, cri i
r
f
�
I
ar
�
6
"'"
`
�
Cli
Asa
C
69
f
i
.......
co CD
Cc Er m � a r r c
i iY L-L i.r. lz a z � L LL
40% bs 6% to 6 64 +ter wr ur or
O/z
. ... .........
rA
0
a
S1 odOJd
NA"' al/I
No
-9 ain6ij
com
5"NO
. . . .. .....
, . . . .........
laoij zogc sdj� qjnos UOWJO GuEldsMS C196L (IVN:MOISAS 91IRUIP1003 SUJgj4:Ag Pxw'S)3alQJd d1O PasO<3OJd L-9 ajnDi.4\aejASjE)\qLOZ dV,1M 960-9LOL\VOM:Elu(l�l�lla4loElv�2
A'�
A
t, 00
Q 4) (N
C,4
0 0 0
N N C: c 0 0 0
0 0 , s a
N N N
0 0 0 4) 1)
C_ C
�2 .2
m
Lj- LL
0 0 to C� C3 09 C3
6 w Lo 4 Cl) (m All J
N C14 C14 C14
-4
C C c r-
, pifor
4,
0
c
c c C_ c c C_ a t N
0 0 0 0 0 J
C)
C4
2 2 2 2 2 j
Cq 'a" 0',
0
Ln a C) 0 n 0
N m
JIn N C) r- v r- m
000
'CO4 C014, gi q
Q4 00
A
" . .. ....... I-11 is
;&
Eli
J/
p
si� oef
"A"01
a
E 951
O'Al
2 CL C
Now it"I f
CL
(L 4) zil 11 1 , 11 1 3 1- � 11, '), , I
0
!E
OL t
I,
- lAw,'
. . ... .. . . ........ ... .
E c
0 0
CL
v o'751 40,
0, f
J/
N
VI
A
/m/m
46
W,
—o
CL w ce o D
",M)PIT
if
v
0
M
N
R�
vvo
V
�/ . .. ... . . .
G "'k/l/Wid
A''
... I .... .. .... .
7
aIJ
L
4)
43
"M I
P
N
IC Cq
'p
0
Ad"
W
%J
N
10
P
I Plflllrlllfrlll��
00
J4
/M
2/111
7
f Oil
Tt 141
T
cii vo
. . . . . .. . . r;
0 POP///
w, CL qb
E
C4
dd
41111111111
d)
F
co,
t 0 0
o
IIIms
N
A,
P�i zo*Wl
CL
a (L a)
w
0
17 7v 77"1
u
.1 L g 2 0, 10
I wls 'Y" —
ow,
z 0 m
C
'V
LL
IF E !q oman
�g5�-- 1,4,
43
co
�C-
0 T7
4
0
A
V C) X
to) --
Off
04 C; 0",
uj 0.
N
t m
N,
LL
7� f
U�
_7
'A
01
di� f fl,
04 i; 0
OPP/Mb
od/O ry N
po 1b
MYOR
J�
J
Nu
ISII� '1/
-7'
41
Pnllgppx�
gpf- Imm,/,
"70
—M, tL
R" MINE
f/d, CL
off.
M
fof!mowplififimm/
Ip
I ... .... . ...
,1",!grp1 .... .. .. .. ......
AM
IWO
Or
'o W/a '/g,
A
OP
If, I,, ", I P /11/1111 1/1 ix
%
J