Loading...
HomeMy WebLinkAbout2000-018 CONT Chg Orders 17-19 - Carollo EngineersCAROLLO ENGINEERS, P.C. CONTRACT CHANGE ORDER NO. 17 Project No. 4411B30 FILE COPY OWNER: City of Ashland, Oregon PROJECT: Wastewater Treatment Plant Process Improvements SRF # 11750 CONTRACTOR: Slayden Construction, Inc. ENGINEER: Carollo Engineers, P.C. The following changes, additions to or deletions from the work described in the Contract Documents are hereby authorized: RFP-129 Repair Oxidation Ditch Expansion Joint Item Description Cost Time No. (See attachment) (dollars) (days) 1 RFP-57 WAS Discharge Piping Diaphragm Seals for Pressure Switches 1,900.00 -0- 2 RFP-92 Painting of Submerged Metal on ElMCO/Baker Process Equipment -0- -0- 3 RFP-101 Concrete Repairs in Grit Chamber &Channels 2,513.00 -0- 4 RFP-121 Revise Sodium Hydroxide Tank Anchorage 518.00 -0- 5 RFP-123 Anti-Scour Wall for Ashland Creek Pump Station 10,898.00 -0- 6 RFP-125 Add Check Valve on Scum Pump Discharge 752.00 -0- 7 RFP-126 Purchase Screw Centrifugal Pump for Interim Sludge Facilities 12,364.00 -0- 8 RFP-128 Provide Rebate for New Scum Sump Grating 2,240.00 -0- 9 5,592.00 -0- Original Contract Amount Net Change by Previous Change Orders Contract Amount prior to this Change Order Net Change due to this Change Order New Contract Amount $12,374,000.00 1,879,675.00 14,253,675.00 36,777.00 $14,290,452.00 The Contract Time is (unchanged) v' ', .... , ~) (,,k .....q} by -0~ calender days. The Contract completion date will be January 14, 2001. The amounts indicated above shall be compensation in full for the work described and shall include all costs, direct and indirect, including extended overhead. Accepted by , Date: (Contractor) Recommended by: ~e~'4fdf~ Date: ]/- O41/.- ~ r) Approved by: /~ -- Date: ~ X/t,/' '~ ~ Ct CONTRACT CHANGE ORDER NO. 17 City of Ashland WWTP Process Improvements SRF # 11750 Description of Items in Change Order RFP-57 WAS Discharcle Piping Diaphragm Seals for Pressure Switches. In RFI-11, the need for an isolation diaphragm seal on each of the three pressure switches on the WAS discharge piping was discussed. By letter of March 17, 1999, the Engineer confirmed that this would be extra work for pressure switches PSH 5-2, PSH 5-3 and PSL 5-6. Ashcroft Iso-Rings were called for; two of the Iso-Rings could be used as a common connection for pressure switch and adjacent pressure gauge, allowing deletion of shutoff valves, stainless steel diaphragm seals, snubbers, etc., for the two pressure gauges. The Contractor submitted proposed costs of $2,650.00 for this work in a letter dated April 26, 1999; this was discussed with the Contractor, noting that the deleted portions had not been included. In a subsequent letter dated October 4, the Contractor submitted revised proposed costs of $1,900.00 for this work. After review, the Engineer informed the Contractor by letter of October 5, 1999 that these costs were acceptable and would be included in a fodhcoming change order. RFP-92 Painting of Submercled Metal on ElMCO/Baker Process Ecluipment. In the spring of 1999, there were several discussions with the Contractor regarding the field painting vs. shop painting requirements of the Contract Documents. The Contractor proposed, in a letter dated June 3, 1999, that the requirement for blast cleaning the ElMCO/Baker Process equipment (the submerged portions of the Oxidation Ditch mixers and aerators and the secondary clarifier full and partial mechanisms) be changed to allow blast cleaning to "white metal" and priming with high-solids epoxy in the factory, thus waiving the requirement for "near-white metal" field abrasive blast cleaning before painting. By letter of June 10, the Engineer indicated that this could be acceptable, if an extended warranty of three years were granted on the entire paint "system", and if supporting correspondence were received from ElMCO/Baker Process, the painting subcontractor and the supplier of the field-applied coatings. Following further correspondence, a June 17 letter was received from the painting subcontractor, Evan House Co., providing the necessary guarantee wording, and correspondence was received from ElMCO/Baker Process confirming that all their equipment would be appropriately blast-cleaned and coated in the factory. After review, the Engineer informed the Contractor by letter of October 21, 1999 that this change was acceptable and would be included in a forthcoming change order as a "no-cost" change. RFP-101 Concrete Repairs in Grit Chamber & Channels. Following discussions in the field for the need to undertake repairs to the walls of the grit chamber and channels in the Headworks, prior to applying a coal-tar epoxy coating, the Contractor submitted proposed costs of $2,513.00 for this work in a letter dated June 23, 1999. By subsequent letter of July 15, the Engineer confirmed the need for repairs and indicated that further discussions would clarify the extent and method of repairs. Over the next several months, discussions with the Contractor and with the supplier/expert in concrete repairs and with the painting subcontractor indicated that the proposed work would suffice; it was then completed. By letter of October 12, the Engineer informed the Contractor that the proposed costs of $2,513.00 were acceptable and would be included in a forthcoming change order. 4. RFP-121 Revise Sodium Hydroxide Tank Anchoracle. By letter of September 2, 1999, the Engineer informed the Contractor that the tie-down anchorage for the sodium hydroxide 2 = (NaOH, or caustic soda) tank needed revision. The supplier's method of hold-down, and the calculations submitted to show conformance with seismic and wind loading requirements, would not work with the concrete pedestal for the tank as detailed on the Plans. The Engineer proposed that the re-calculation of the anchorage requirements be paid for by the City, but that any costs with modifying the anchor clips, number and size of anchor bolts, etc., be the responsibility of the supplier and/or the Contractor. Following further correspondence, the issue was discussed at the September 23, 1999 monthly project meeting, and an amount of $450.00 for the engineering calculations agreed-upon. By subsequent letter of September 27, the Engineer informed the Contractor that the proposed costs of ($450.00 + 15% OH&P =) $518.00 were acceptable and would be included in a forthcoming change order. RFP-123 Anti-Scour Wall for Ashland Creek Pump Station. By letter of September 17, 1999, the Engineer informed the Contractor that an anti-scour cut-off wall should be incorporated into the construction of the main operating slab for the pump station, due to the proximity to Ashland Creek. In a letter dated October 7, 1999 the Contractor submitted proposed costs of $14,260.00 for this work. Following discussions, the Contractor submitted revised costs of $10,898.00 in a letter dated October 27. After review, the Engineer informed the Contractor by letter of October 27, 1999 that these costs were acceptable and would be included in a forthcoming change order. RFP-125 Add Check Valve on Scum Pump Discharge. By letter of September 27, 1999, the Engineer informed the Contractor that it was necessary to add a check valve on the new scum pump discharge in the existing scum sump adjacent to Secondary Clari~er No.2. In a letter dated October 4, the Contractor submitted proposed costs of $726.00 for this work. When requested written confirmation of the cost of the valve was received from the supplier, it indicated that the Contractor had used a slightly low valve cost in his estimate. After review, the Engineer informed the Contractor by letter of October 21, 1999 that a revised total cost of $752.00 would be included in a forthcoming change order. RFP-126 Purchase Screw Centrifuclal Pump for Interim Sludge Facilities. By letter of August 23, 1999, RFP-112 was established for the proposed interim sludge facilities for the wastewater treatment plant. These facilities must be "on-line" by early 2000 to handle sludge from the new secondary treatment facilities, as the biosolids disposal project has been delayed. To expedite construction of the interim sludge facilities, it is necessary to purchase certain pieces of equipment in advance. By letter of October 12, 1999, the Engineer explained this situation and supplied a specification for a screw centrifugal pump for the facilities. In a letter dated October 20, the Contractor submitted proposed costs of $12,364.00 for this pump. After review, the Engineer informed the Contractor by letter of October 20, 1999 that this amount would be included in a forthcoming change order. RFP-128 Provide Rebate for New Scum Sump GratinG. By letter of October 13, 1999, the Engineer informed the Contractor that a new rebate was needed for the grating being installed over the existing scum sump, as the old rebate was not the correct dimensions or material. In a letter dated October 21, the Contractor submitted proposed costs of $2,476.00 for this work. Following discussions, a revised estimate of $2,240.00 was submitted by the Contractor. After review, the Engineer informed the Contractor by letter of October 22, 1999 that this amount would be included in a forthcoming change order. RFP-129 Repair Oxidation Ditch Expansion Joint. By letter of October 20, 1999, the Engineer informed the Contractor of necessary repairs to the transverse expansion joint in the anoxic zone of the Oxidation Ditch structure. In a letter dated October 26, the Contractor submitted proposed costs of $5,592.00 for this repair work. After review, the Engineer informed the Contractor by letter of October 26, 1999 that this amount would be included in a forthcoming change order. CAROLLO ENGINEERS, P.C. CONTRACT CHANGE ORDER NO. 18 Project No. 4411B30 OWNER: City of Ashland, Oregon PROJECT: Wastewater Treatment Plant Process Improvements SRF # 11750 CONTRACTOR: Slayden Construction, Inc. ENGINEER: Carollo Engineers, P.C. The following changes, additions to or deletions from the work described in the Contract Documents are hereby authorized: Item Description Cost Time No. (See attachment) (dollars) (days) 1 RFP-32 Revise Size of Supernatant Pipeline (9,898.00) -0- 2 RFP-69 New Weir for Grit Chamber 1,364.00 -0- 3 RFP-89 Relocate Sodium Hydroxide System 4,848.00 -0- 4 RFP-116 Additional Lockers in Operations Building Men's Locker, Area 009 2,134.00 -0- 5 RFP-122 Replace Existing Outfall Pipeline 34,501.00 -0- 6 RFP-133 Repair Leaking Water Pipeline 1,758,00 -0- Original Contract Amount Net Change b~' Previous Change Orders Contract Amount prior to this Change Order Net Change due to this Change Order New Contract Amount $12,374,000.00 1.916,452.00 14,290,452.00 34.707.00 $14,325, 159.00 The Contract Time is (unchanged) (~: .... r. rtl) (t~rrrcn-,r,-q by -0- calender days. The Contract completion date will be January 14, 2001. The amounts indicated above shall be compensation in full for the work described and shall include all costs, direct and indirect, including extended overhead. Accepted by: ~ ' ~~ ~'~:'.~ Recommended by: Approved by: Date: Date: Date: 12--' l ~,. ~' CONTRACTCHANGEORDERNO. 18 City of Ashland WWTP Process Improvements SRF # 11750 Description of Items in Change Order RFP-32 Revise Size of SuDernatant Pipeline. By letter of January 12, 1999, the Engineer informed the Contractor of the need to reduce the supernatant pipeline from 12-inch to 8-inch size, in order to conform to the final design of the Biosolids and Effluent Disposal project. This change includes all supernatant piping, valves, fittings, magnetic flow meter, couplings, etc. In a letter dated March 19, the Contractor submitted proposed credits of ($7,476.00) for this revision. Following review and discussion, the Contractor indicated concurrence with a revised total credit of ($9,898.00); this was confirmed by letter of November 18, 1999 from the Engineer that the revised total credit would be included in a forthcoming change order. RFP-69 New Weir for Grit Chamber. By letter of April 13, 1999, the Engineer informed the Contractor of the need to replace the existing metal weir in the grit chamber while the grit mechanism was being replaced. In a letter dated May 3, the Contractor submitted proposed costs of $1,453.00 for this work. The Engineer indicated that the costs seemed high, and the Contractor proposed that the work be done on a time and material basis; by letter of May 3, 1999, the Engineer authorized that the work be performed on a time and material basis with the Contractor's proposed costs as a "not-to-exceed" amount. After the work was completed, the Contractor submitted total costs of $1,364.00 in a letter dated November 16. By letter of November 16, 1999, the Engineer stated that this amount would be included in a fodhcoming change order. RFP-89 Relocate Sodium Hydroxide System. By letter of June 1, 1999, the Engineer informed the Contractor that the sodium hydroxide (NaOH, or caustic soda) system was to be relocated to the west side of the Headworks, to provide more compact and readily accessible facilities and allow better use of the area east of the Headworks for additional treatment processes. In a letter dated August 9, the Contractor submitted proposed costs of $7,722.00 for this work, The scope of work was subsequently revised by the Engineer's letter of August 24, 1999. After discussions, the Contractor submitted new proposed costs of $5,324.00 for this work; following additional discussions, the Contractor indicated concurrence with revised total costs of $4,848.00. By letter of November 18, 1999, the Engineer stated that this amount would be included in a forthcoming change order. RFP-116 Additional Lockers in Operations Building Men's Locker, Area 009. By letter of August 30, 1999, the Engineer informed the Contractor that the City had requested additional lockers in the Men's Locker room in the Operations Building; this change necessitated modest changes in stud walls, gypsum board, flooring, etc. In a letter dated September 27, the Contractor submitted proposed costs of $2,668.00 for this work. After discussions, the Contractor submitted additional information and proposed costs of $2,455.00 for the work. Following review, the Engineer noted, by letter of December 2, 1999, that the costs need not include a revised locker room bench, thus lowering the total costs to $2,134.00, which would be included in a forthcoming change order. The Contractor concurred on December 6. RFP-122 Replace Existing Outfall Pipeline. By letter of September 10, 1999, the Engineer noted that the existing 18-inch outfall pipeline was found to be damaged near the proposed new 60-inch diameter manhole; televising the pipeline revealed a "belly" in the existing line, 2 and it was desired to replace the line with a new 24-inch PVC gravity outfall pipeline, and construct a new headwall at the side of Ashland Creek. Details of the headwall and a revision to the scope of work were sent the Contractor by letter of September 15, 1999. In the ensuing several days, the Contractor obtained necessary Corps of Engineers permit and submitted proposed total costs of $36,501.00. Following review and discussion, the Engineer and Contractor agreed to revised total costs of $34,501.00; by letter of December 2, 1999, the Engineer informed the Contractor that this amount would be included in a fodhcoming change order. RFP-133 Repair Leakincl Water Pipeline. By letter of November 16, 1999, the Engineer noted that an existing water pipeline bad been noted to be leaking the prior day; it was believed that this was caused by the Contractor's operations and was his responsibility. Upon excavation, it was discovered that the leak was in a different, deeper existing water line which had corroded and was not the Contractor's responsibility; the Contractor was asked to submit his costs for excavation and repair. By subsequent letter of November 16, the Contractor submitted proposed costs of $1,758.00 for this work. After review, the Engineer informed the Contractor by letter of November 17, 1999, that this amount would be included in a forthcoming change order. 3 CAROLLO ENGINEERS, P.C. CONTRACT CHANGE ORDER NO, 19 Project No. 4411B30 OWNER: City of Ashland, Oregon PROJECT: Wastewater Treatment Plant Process Improvements SRF # 11750 CONTRACTOR: Slayden Construction, Inc. ENGINEER: Carollo Engineers, P.C. The following changes, additions to or deletions from the work described in the Contract Documents are hereby authorized: Item Description No. (See attachment) RFP-112 Interim Sludge Stabilization Facilities Cost Time (dollars) (days) 828,914.00 -0- Original Contract Amount Net Change by Previous Change Orders Contract Amount prior to this Change Order Net Change due to this Change Order New Contract Amount $12,374,000.00 1,951,159.00 14,325,159.00 828,914.00 $15,154,063.00 The Contract Time is (unchanged) (Innrrf, nc~l',~ (d~ul ui~uud) by -0- calender days. The Contract completion date will be January 14, 2001. The amounts indicated above shall be compensation in full for the work described and shall include all costs, direct and indirect, including extended overhead. Accepted by: · $ r~- Date: ' ~ ~ (Contractor) Recommended by: Y/'~if/j, Approved by: /~/~,/~ (City) Date: IP~ -.~.~ '..~0(9 D Date: CONTRACTCHANGEORDERNO. 19 City of Ashland WWTP Process Improvements SRF # 11750 Description of Items in Change Order RFP-112 Interim Sludqe Stabilization Facilities. By letter of August 23, 1999, the Engineer notified the Contractor of the need to construct interim sludge treatment (stabilization) facilities for the new treatment processes, until the off-site disposal site could be prepared. The Engineer established this RFP to collect information on the proposed interim sludge facilities, and supplied 50% drawings with the initial letter. In subsequent correspondence, additional drawings and information were supplied to the Contractor. In late November, the Contractor prepared a cost estimate of $788,267.00 for this work. As the design evolved, the scope was revised to include retaining the existing primary clarifier as an emergency sludge holding tank, requiring additional piping, re-installation of an existing pump, etc. Final details of the design were provided the Contractor by letters of January 19 and February 8, 2000. The Contractor submitted revised proposed costs of $865,467 in an estimate dated January 31; following a negotiating meeting on February 10, it was concluded that the electrical and controls needed revision and would be handled separately. The Contractor provided revised proposed costs of $828,914.00 in an estimate dated February 23, 2000. Following review, the Engineer stated by letter of that same date that this amount would be included in a forthcoming change order. 2