HomeMy WebLinkAbout2000-30 Wastewater Exempt BidsRESOLUTION NO. 2000-
BEFORE THE CITY OF ASHLAND LOCAL CONTRACT REVIEW BOARD
RESOLUTION EXEMPTING FROM COMPETITIVE
BIDDING THE REMAINING CONSTRUCTION WORK LCRB RESOLUTION
ON THE WASTEWATER TREATMENT PLANT SITE
Recitals:
A. ORS 279.015 and AMC § 2.50.030.B permits the Ashland City Council sitting as
the Local Contract Review Board to exempt contracts from competitive bidding if it finds:
1. The lack of bids will not result in favoritism or substantially diminish
competition in awarding the contract; and
2. The exemption will result in substantial cost savings.
B. This statute and ordinance provide that in making such findings, the Board may
consider the type, cost, amount of the contract, number of persons available to bid, and
such other factors as the Board may deem appropriate. Where appropriate, the Board
shall direct the use of alternate contracting and pumhasing practices that take account of
market realities and modern or innovative contracting and purchasing methods, which are
also consistent with the public policy of encouraging competition.
C. In order to exempt a public contract from competitive bidding, the Board must
adopt written findings that support the awarding of a particular public contract or a class of
public contracts without competitive bidding. The findings must show that the exemption of
a contract or class of contracts complies with the requirements of AMC § 2.50.030.B.
The Board adopts the attached findings contained in the council communication from
Paula Brown dated November 21,2000, as findings justifying the exemption. The Board
finds that this exemption will not result in favoritism or substantially diminish competition in
awarding the contract and the exemption will result in substantial cost savings.
The Board resolves that an exemption be granted as follows:
Remaining Construction Work on The Wastewater Treatment Plant Site. This project,
including the new membrane filtration facilities and the biosolids handling portions to be
constructed and operated at the existing wastewater treatment plant site, is exempted
from competitive bidding.
This resolution was read by title only in accordance with Ashland Municipal Code
BArbara Christensen, City Recorder
SIGNED and APPROVED this ,~ day of
Paul Nolte, City Attorney
/~-~"~'- ,2000.
~haw, Mayor
PAGE 1-LCBR EXEMPTION (G:\IegaI\PAUL\ORD\LCRB\WWTP exemption res .wpd)
Findings in Support of Competitive Bidding Exemption
Membrane Filtration and Remaining On-Site Process Improvements
Ashland Wastewater Treatment Plant
INTRODUCTION
The City has been constructing major improvements to the Wastewater Treatment Plant facility
under a contract with Slayden Construction (Slayden) since September 1998. Originally the
wastewater treatment plant improvements were designed as two distinct pieces; the initial phase
as process improvements at the wastewater treatment plant site (Project A), and the second phase
(Project B) for facilities to be constructed on the City's hillside farmland for effluent reuse and
biosolids application.
The City has determined not to continue with the second phase and will continue on-site with a
tertiary system. All of the process improvements, including the new membrane filtration
facilities and the biosolids handling portions will be constructed and operational at the existing
wastewater treatment plant site and nothing will be constructed on a differing site. Through a
Mutual Agreement and Order (MAO), the Department of Environmental Quality (DEQ)
mandates timing of completion for these new improvements, and for the remaining process
improvements which are under the existing contract. As such, this requires an evaluation of
construction timing opportunities.
The term of the original contract with Slayden was for construction and modifications to the
process improvements on the treatment plant site, the original "Project A". The initial contract
award was for $12,374,000 with a completion date of December 29, 2000. Slayden's contract
has had numerous change orders to resolve differing site conditions, clarifications of the plans
and specifications, adding reconstruction of the Ashland Creek Pump Station, adding provisions
for interim sludge handling modifications, and recently the addition of significant piping to
accommodate the expected membrane filters and biosolids handling within the middle of the
plant site. As of this date, 31 change orders have been authorized bringing the total contract
authorization to $15,791,461. Although the City has not negotiated a final change to the contract
length, it is understood that Slayden is not expected to be complete with all of the original
contract items by the December 2000 deadline.
As briefly mentioned above, the MAO from the DEQ has imposed strict timeframes on the
completion of the membrane facilities in order to meet waste load allocations and permit limits
for effluent discharges to the creek. With the completion of the pilot study for the membrane
facilities in October 2000, final design has begun and discussions with DEQ are continuing.
Final design of the membrane system is to be complete in December and a contract for
construction of the chosen membrane system and facilities is to be in place by mid-January 2001.
Page 1 of 5
It is proposed that Slayden's contract be modified to include all of the work which will be
completed on the existing wastewater treatment plant site to maintain construction quality
control, keep current with the timing restriction placed by DEQ and allow continuity and full
coordination of the ongoing construction and plant operations during the final construction
portions.
FAVORITISM/COMPETITION
Carollo Engineers, the City's engineering design consultant will design and identify
specifications for the remaining new system and facilities. Carollo's engineering cost estimates
for the membrane filters and the final biosolids handling facilities will have an independent third
party value engineering and cost estimate completed. These estimates will be the determining
factors used in negotiating a fair price for the change order with Slayden. The final terms and
conditions of each portion of the final change orders for the wastewater treatment plant will be
evaluated by Carollo and the City, thus discouraging any favoritism in the awarding of the
contract.
Because of the existing contract with Slayden, and the unique circumstances presented with the
existing construction and site configurations, it is unlikely that an exemption authorizing these
specific change orders to Slayden will encourage favoritism in the awarding ofpublic contracts
or substantially diminish competition for public contracts. "'
COST SAVINGS
The ability of the City to provide efficient infrastructure facilities to meet the needs of its
constituents in a timely and cost-efficient manner at the lowest cost to taxpayers, will be
significantly enhanced by the continued construction efforts and successes of Slayden
Construction. Specifically, substantial cost savings will be realized by the City and by the public
as the result of the City's ability to negotiate a change order to the existing contract with Slayden
which will allow for a successful, fast-track project to meet DEQ timelines, avoids lost time from
preparing complete bid documents and bid level construction drawings and specifications (saves
60-90 days), avoids bid time (45-60 days), avoids duplicative construction efforts, thus saving
construction dollars.
In addition to the significant time saved, the specific cost savings to the City are:
a)
The City will realize a cost savings of over $250,000 in construction costs to keep the
project moving forward, eliminate any duplicate construction tasks of re-do work to have
Slayden complete the current project and the hire a subsequent contractor to come in and
remobilize and start over in an area finished by Slayden. If the City were to
competitively bid these system changes, the City is obligated to complete Slayden's
contracted work or pay a penalty for work removed from the contract so that another
Page 2 of 5
contractor could move into the site. If Slayden is required to finish their work, there is
significant site work that must be re-done for the construction of the membrane and solids
handling facilities.
b)
In addition, Slayden is familiar with the site and all utility locations and persons
responsible for the existing site conditions. That coordination will be lost and unknown
utility locations could hamper construction or add unnecessary costs.
c)
The contract change order will use a guaranteed maximum price, or fixed-priced
structure, either of which will provide the City with protection against cost overruns and
will also provide cost savings. Slayden is familiar with the City's expectations and with
Carollo's requirements and engineering inspection and specifications. The cost of the
negotiated contract char~ge will also be reviewed by an independent consultant to ensure
price competitiveness.
Cost savings to the City are further anticipated through the use of this negotiated change
order by reducing design time as detailed construction bidding level drawings and
specifications are unnecessary (savings of approximately $150,000); by eliminating
design flaws and misunderstandings through continuous discussions between the City,
design engineer (Carollo Engineers), and the contractor (Slayden); by incorporating value
engineering suggestions from all parties and the independent engineering estimator into
the design phase in a team approach; and in shortening construction time.
The award of a negotiated change order to the contract with Slayden for the construction and
installation of membrane filtration units and the biosolids handling facilities on the wastewater
treatment plant site pursuant to this exemption will result in substantial cost savings to the City.
OPERATIONAL, BUDGET~ FINANCIAL
To accomplish the goal of designing and constructing the remaining integrated processes at the
wastewater treatment plant site while maintaining full functioning of the system and ensure that
all components are fully compatible with its existing system, it is necessary to identify a
contractor that is familiar with all operational components and the interrelationship of those
components to produce a safe, reliable operating system. Slayden Construction is familiar with
not only the design team (Carollo) but also with the City and the City's wastewater treatment
operational staff.
Slayden has a proven track record with the City in quality control, construction capabilities,
quality control, timely construction infrastructure and with both the City and Carotlo in
developing a sound, financially responsive, quality product. All parties have deliberated on
previous engineering design elements to provide a better wastewater treatment facility.
Page 3 of 5
PUBLIC BENEFIT
The public benefit to this negotiated change order will be a significant enhancement to the City's
wastewater treatment infrastructure system by providing the highest quality effluent and
improving water quality to Ashland and Bear Creeks, and by providing a fiscally responsible
biosolids handling facility. With the completion of the entire wastewater treatment plant
operational facilities in May 2001, Ashland will have the highest quality effluent in the state and
will significantly enhance the environmental quality and water quality within the Bear Creek
basin.
With a negotiated change order to the current contract, the process will allow a seamless, fast-
track construction completion date to provide the environmental quality improvements and will
save the public money as discussed in the general findings above.
VALUE ENGINEERING
Cost estimates, constructability and an independent engineering design consultant will provide
value engineering analysis during the initial design phase of design. This analysis is not
compatible in competitive bidding unless it is after the fact. The advantage of this analysis
during design is that cost savings are immediate rather than postponed as with competitive
bidding. This will ensure a competitive negotiated change order for the work being performed.
SPECIALIZED EXPERTISE
Contractors, for this type of project, must have expertise and experience managing large
complex, multi-phased construction contracts at an existing operating facility. Although there
are other competent contractors that also have the ability to perform this type of work, the timing
of this necessary negotiated change order does not permit solicitation. The specialized work of
the change order and the coordination with the remaining contract work and the operation of the
wastewater treatment plant does not allow for two contractors to work simultaneously at the site.
PUBLIC SAFETY
A negotiated change order to the current Slayden contract allows the City and the contractor to
jointly develop a construction phasing plan, current operations plan and safety plan during the
design process. This ensures that all safety provisions and temporary permanent facilities are
clearly identified and included in the contract. It also ensures that all facilities remain
operational throughout the contract period and that there is no ability to abdicate responsibility to
a second contractor on site. A negotiated contract change order also ensure that the public's
safety is met through timely completion of the contract work and no delays in the enhancement
of water quality.
Page 4 of 5
MARKET CONDITIONS
This negotiated contract will have no negative impact on the contracting or subcontracting
market in the Ashland - Medford metro area. A sufficient number of qualified firms are
available to ensure adequate competition and any subcontracted work will be competitive.
As a single contract exemption, market conditions will not be directly affected. However,
positive indirect market impact will occur by creation of jobs and investment/development
opportunities generated as a result of the contract, both as to rail construction and future PIC
development. Although the change order to Slayden's current contract will be awarded without
direct competition, a portion of the construction work will be performed by subcontractors who
will be selected through a competitive process. Much of the project work is unique and it is
highly unlikely that this procurement will have any effect on or substantially diminish
competition for future public Contracts.
TECHNICAL COMPLEXITY
The complexity of this project and especially of this portion of the project is briefly described
above in the Introduction. Existing facilities, utilities, and public dependence on the existing
facilities are needed to remain functional during the construction phase. Remodeling or adding to
existing facilities while maintaining a functional wastewater treatment plant require extensive
planning and coordination that is very difficult to sufficiently portray on competitively bid
construction documents. A negotiated change order to this contract allows the contractor to
better understand operations impacts to the construction and participate in developing the
construction phasing, construction site access, and other coordination processes required of
projects at an operating treatment plant already in the midst of construction. The addition of a
second contractor through a competitive bidding process would not offer this level of
coordination and phasing.
FUNDING SOURCES
This project will be funded from a combination of sources.
Page 5 of 5