July 1,1998 Fee Increases
Attached are the new fee schedules for water connections and wastewater
connections as of July 1, 1998. In addition, the following schedules were reviewed and
were not changed at this time.
Transportation Utility Fee from July 1997
Storm Drain Utility Fee from July 1997
System Development Charges from January 1998
N:kAcctg\RATES\annual fee transmittal.wpd
EXHIBIT "B"
CITY OF ASHLAND, OREGON
SEWER CONNECTION FEE SCHEDULE
RESOLUTION NO. 96-19
EFFECTIVE DATE July 1, 1998
ENR @ 5884.41
ANNOTATED TO SHOW CHANGES. DELETIONS Ar'{E LINED TI II'{OUGIt AND ADDITIONS ARE SHADED.
A. Four-inch lateral connection from trunk line
to normal curb line.
B. Six-inch lateral connection from trunk line
to normal curb line.
C. Eight-inch lateral connection from trunk line
to normal curb line.
D. Ten-inch or larger lateral connection from
trunk line to normal curb line.
E. Manhole maximum depth of five feet.
1. Per additional foot of depth.
F. Eight-inch sanitary sewer line with one five-
foot manhole per 400 feet of eight-inch line.
G. Checking for sewer main blockages
without finding a blockage.
$1,422.00 $1,428t00
1,488.00 1,494:~00
1,510.00 1,5t::6~00
COST
1,856.00 1864~00
55.00/fi 55.00/ft
27.00/ft 28.O0/ft
$ 99.00 $ 99.00
N:\Acctg\RATES\SEWER\exhibit B.98 connections.wpd
EXHIBIT "B"
CITY OF ASHLAND, OREGON
WATER CONNECTION FEE SCHEDULE
RESOLUTION NO. 97-
EFFECTIVE DATE JULY 1, 1998
EXHIBIT B
CITY OF ASHLAND, OREGON
INSTALLATION, CONNECTION AND OTHER FEES
Effective July 1, 1998
ANNOTATED TO SHOW CHANGES. DELETIONS ARE LINED TI IROUGI I AND ADDITIONS ARE SHADED.
A. 3/4 inch service connection from main line including meter
1. If owner/builder/contractor provides trench and backfill
B. 1 inch service connection from main line including meter
1. If owner/builder/contractor provides trench and backfill
C. 1-1/2 inch service connection from main line including meter
1. If owner/builder/contractor provides trench and backfill
D. 2 inch service connection from main line including meter
1. If owner/builder/contractor provide trench and backfill
E. 3 inch or larger service connection from main line
F. 8 inch and one Fire Hydrant per 335 feet
G. First utility locate at an address
Additional locates at same address
$1,045.00 $1,053.00
..... 245 00
1,192.00 li:201
..... 330:00
1,641.00 1;653;00
..... 6:94:00
1,794.00 1,80&00
..... 904:00
Cost
........ 49:001ff
No Charge
..... 44~00
Other water related fees
Water meter re-read
Once in 12 months
Each additional re-read in 12 months
Water Meter Field Test
Water Meter Bench Test:
3/4" or 1 "Water Meter
1.5" or 2" Water Meter
Larger meters billed
Water line pressure check once in 12 months
Each additional pressure check in 12 months
Install Customer 3/4" hand valve
Install Customer 1" hand valve
No Charge
$ 22.00 $ 22:~00
.... 33:~00
~ 67:00
..... 121 00
Actual Cost
No Charge
.... 26 00
..... 83.00
$ 93.00 $ 94,00