HomeMy WebLinkAbout1992-062 Contract-BrownCaldwellBI]
Brown and Caldwell
Consultants
2300 0akmon! Way
Suite 100
Eugene
Oregon 97401-5556
(503) 686-9915
FAX (503) 686-1417
May 7, 1992
Mr. Paul Nolte
City Attorney
City of Ashland
20 East Main Street
Ashland, Oregon 97520
3 992
13-6876-02
Dear Mr. Nolte:
Thank you for your assistance in reviewing and revising the form for the
engineering services contract between the City of Ashland and Brown and
Caldwell Consultants. Enclosed is a signed copy of the contract for execution by
the City.
Note that we have attached our letter to Mr. Steve Hall dated April 16, 1992, to
the contract as Exhibit 2. This Exhibit defines the scope of engineering services
for the Digester Improvements Project at the Ashland Wastewater Treatment
Plant. If you concur with this approach, please pass the contract along to Steve
for execution. Please have Steve initial the Exhibit during execution to confirm
inclusion in the contract.
Once again, we appreciate your assistance wii~h the contract and the opportunity
to serve the City of Ashland.
Very truly yours,
BROWN AND CALDWELL
Project Manager
JEH:WBS:jdc.cm
Enclosure(s)
ENGINEERING SERVICES CONTRACT
Engineering services contract made on the date specified below in
Recital A between the City and Engineer as follows:
Recitals:
A. The following information applies to this contract:
CITY: CITY OF ASHLAND ENGINEER: Brown and Caldwell
20 E. Main St. Address: 2300 Oakmont Way,
Ashland, Oregon 97520 suite 100,
(503) 482-3211 Eugene, OR 97401.
FAX: (503) 488-5311 Telephone: (503) 686-9915
FAX: (503) 686-1417
Date of this agreement: ~A. Date of RFP:
Proposal date:Jan. 24, 1992
¶2.4. Contracting officer: City Director of Public Works
~6.1 Engineer's representative: Walt Meyer
~8.3. Maximum contract amount: To be negotiated based on
rates published by Engineer and accepted by City.
B. City issued a request for proposals (RFP), on the date
specified in Recital A above, for engineering services needed by
City for the reconstruction and upgrading of the City's anaerobic
digester. Engineer submitted a proposal in response to the RFP
on the date specified in Recital A above.
C. After reviewing Engineer's proposal and proposals submitted
by other offerors, City selected Engineer to provide the services
covered by the RFP.
City and Engineer agree as follows:
1. Relationship between City and Enqineer: Engineer accepts the
relationship of trust and confidence established between Engineer
and City by this contract. Engineer covenants with the City to
perform services and duties in conformance to and consistent with
the standards generally recognized as being employed by
professionals of engineer caliber in the locality of the project.
Engineer further covenants to cooperate with City, City's
representatives, contractors, and other interested parties in
furthering the interests of City as those interests are
specifically described within the scope of work to the Engineer.
In order to promote successful completion of the project in an
expeditious and economical manner, Engineer shall provide
professional engineering services for City in all phases of the
project to which this contract applies, serve as city's
professional engineering representative for the project, and give
professional engineering consultation and advice during the term
of this contract.
PAGE I-ENGINEERING SERVICES AGREEMENT (p:agree\br0wn-en.k)
2. Definitions: Generally words, terms and phrases used in this
contract shall have the meaning ascribed to them in the
construction industry, unless the context clearly indicates
otherwise. As used in this contract:
2.1. "Contract documents" shall mean this contract, written
authorizations under subsection 5.4, written assignments under
subsection 5.2, written amendments to this contract, schedules
established under subsection 5.4 and exhibits incorporated in
other contract documents.
2.2. "City" or "Owner" means the City of Ashland, Oregon.
2.3. "Proposal" means proposal submitted by the Engineer
in response to the RFP.
2.4. "Contracting officer" means the person specified in
Recital A above or that person's designee.
2.5. "Project" means the Digester Rehabilitation Project.
2.6. "Work" or "Services" shall mean all labor, materials,
plans, specifications, construction contract documents, opinions,
reports, and other engineering services and products which
Engineer is required to provide under this contract.
3. Term: The term of this contract shall commence on the date
specified in Recital A above and end on completion of all
services required by this contract unless sooner terminated as
provided in this contract.
4. Authority of Contractinq officer: The contracting officer
shall have the authority to act on behalf of City in the
administration and interpretation of this contract. Subject to
the limitations on authorization of assignments under subsection
5.2, the contracting officer shall have complete authority to
authorize services, transmit instructions, receive information,
interpret and define city's policies and make other decisions
with respect to Engineer's services.
5. Enqineerinq Services:
5.1. Engineer shall provide services to City that are
described in Section 1 of the proposal and as are further
specifically agreed to by City.
5.2. In addition to the services described in subsection
5.1, the parties may agree to have Engineer provide other
discrete services that are necessary for completion of the
project. Such services will be initiated by written assignments
as follows:
5.2.1. Assignments under this subsection should
be used only for services that are beyond the scope of
the services described in subsection 5.1. No
assignment is necessary to authorize services that are
PAGE 2-ENGINEERING SERVICES AGREEMENT (p:a§re¢\br0wn-en.k)
customarily provided in conjunction with, or are
ancillary to, the services described in subsection 5.1.
5.2.2. Assignments which cover services that will
cost less than $15,000 may be initiated by the
contracting officer. Assignments that cover services
which will cost more than $15,000 must be approved by
the City Administrator.
5.2.3. Each assignment shall specify the duties
of Engineer, the objective of the assignment, the scope
of the assignment and the estimated cost of the
services.
5.2.4.
parties.
Each assignment shall be signed by both
5.2.5. Each assignment shall incorporate and be
subject to the provisions of the contract documents
unless the assignment specifically provides otherwise.
5.3. In connection with the services described in
subsection 5.1 and services authorized by assignments under
subsection 5.2, Engineer shall:
5.3.1. Consult appropriate representatives of
City to clarify and define City's requirements relative
to the services.
5.3.2. Review available data relative to the
services.
5.3.3. Identify data which is not available and
is needed to fulfill the services, and act as City's
representative in obtaining such data.
5.3.4. Prepare monthly progress reports to the
contracting Officer on the status of services.
5.3.5. Cooperate with other consultants retained
by City in the exchange of information needed for
completion of the services and the project.
5.4. The services described in subsection 5.1 are divided
into discrete work elements. Engineer shall commence performance
of services within five days after receiving written
authorization from the contracting officer for work elements
described in subsection 5.1 or assignments made under subsection
5.2. Engineer shall perform the services as expeditiously as is
consistent with professional skill and care and the orderly
progress of the project. Upon request of City, Engineer shall
submit for City's approval, a schedule for the performance of
work elements described in subsection 5.1 and assignments made
under subsection 5.2. Each schedule shall include allowance for
periods of time required for City's review and approval of
PAGE 3-ENGINEERING SERVICES AGREEMENT (p:agree\brown-en.k)
Engineer's services. Each schedule, approved by City, shall
become a part of this contract.
5.5. Engineer shall perform the services as an independent
contractor in accordance with generally accepted standards in
Engineer's profession. Engineer shall be responsible for the
professional quality, technical accuracy and the coordination of
all services performed by Engineer. Engineer shall, without
additional compensation, correct or revise any error or
deficiencies in the services that are caused by Engineer's
negligence. City's review, approval, acceptance of, or payment
for, any of the services shall not be construed to waive any of
city's rights under this contract or of any cause of action
arising out of Engineer's services. In the event of any breach
of this contract by Engineer or negligent performance of any of
the services, City's cause of action against Engineer shall not
be deemed to accrue until City discovers such breach or
negligence, or should have, with reasonable diligence, discovered
such breach or negligence. The preceding sentence shall not be
construed, however, to allow City to prosecute an action against
Engineer beyond the maximum time limitation provided by Oregon
law.
6. Assiqnment of Enqineer's Personnel:
6.1. The services covered by this contract shall be
rendered by, or under the supervision of the person specified in
Recital A above, who shall act as Engineer's representative in
all communications and transactions with City.
6.2. Engineer will endeavor to honor reasonable specific
requests of City with regard to assignment of Engineer's
employees to perform services if the requests are consistent with
sound business and professional practices.
7. Responsibilities of City:
7.1. City will cooperate fully with Engineer to achieve the
objectives of this contract.
7.2. City will provide information, documents, materials
and services that are within the possession or control of City
and are required by Engineer for performance of the services.
7.3. City will arrange for access to, and make all
provisions for Engineer to enter upon, public and private
property as required for Engineer to perform the services.
7.4. City will provide all permits necessary for completion
of the project.
7.5. The contracting officer will act as liaison between
city, Engineer, public agencies, and others involved in the
project.
PAGE 4-ENGINEERING SERVICES AGREEMENT (p:a§ree\brown-en.k)
7.6. City shall perform such other functions as are
required by written assignments under subsection 5.2.
7.7. Owner shall use its best efforts to assure that the
construction contract requires that the Contractor indemnify
Engineer and Construction Manager as well as City, and that the
Contractor name Engineer and Construction Manager as additional
insureds on Contractor's insurance policies covering Project.
8. Payment:
8.1. City shall pay Engineer for services and reimburse
Engineer for expenses incurred by Engineer in performance of
services in accordance with a payment schedule to be submitted by
Engineer and accepted by City Exhibit 2 which is attached to and
incorporated in this contract. No reimbursement will be made for
expenses that are not specifically itemized in this payment
schedule without prior approval by the contracting officer.
8.2. Engineer shall submit monthly invoices to City for
Engineer's services within ten days after the end of the month
covered by the invoice. City shall pay Engineer within thirty
days after receipt and approval of the invoice.
8.3. Total payments under this contract or any amendments
shall not exceed the sum specified in Recital A above.
9. Compliance with Law:
9.1. This contract will be governed by and construed in
accordance with laws of the State of Oregon. Engineer shall
promptly observe and comply with all present and future laws,
orders, regulations, rules and ordinances of federal, state, City
and city governments with respect to the services including, but
not limited to, provisions of ORS 279.312, 279.314, 279.316 and
279.320.
9.2. Pursuant to ORS 279.316(2) any person employed by
Engineer who performs work under this contract shall be paid at
least time and a half pay for all overtime in excess of 40 hours
in any one week, except for persons who are excluded or exempt
from overtime pay under ORS 653.010 to 653.261 or under 29 U.S.C.
Sections 201 to 209.
9.3. Engineer is a "subject employer" as defined in ORS
656.005 and shall comply with ORS 656.017. Prior to commencing
any work, Engineer shall certify to City that Engineer has
workers' compensation coverage required by ORS Chapter 656. If
Engineer is a carrier insured employer, Engineer shall provide
City with a certificate of insurance. If Engineer is a self-
insured employer, Engineer shall provide City with a
certification from the Oregon Department of Insurance and Finance
as evidence of Engineer's status.
10. Ownership of Documents: Ail documents prepared by Engineer
pursuant to this contract shall be the property of City. To the
PAGE 5-ENGINEERING SERVICES AGREEMENT (p:a§ree\brown-en.k)
extent permitted by law, City shall, within the limits of the
Oregon Tort Claims Act, defend, indemnify and hold harmless
Engineer, its consultants, agents and employees against all
damages, claims, expenses and losses arising out of any reuse of
plans, specifications and other documents prepared by Engineer
without prior written authorization of Engineer.
11. Records:
11.1. Engineer shall develop and maintain complete books of
account and other records on the services which are adequate for
evaluating Engineer's performance. Engineer shall maintain
records in such a manner as to provide a clear distinction
between the expenditures and revenues related to the project and
the expenditures and revenues related to Engineer's other
business.
11.2. Engineer's books and records shall be made available
for inspection by City at reasonable times, to verify Engineer's
compliance with this contract. City shall have the right to
request an audit of Engineer's books and records by a certified
public accountant retained by City.
12. Indemnification: Engineer shall defend, indemnify and save
City, its officers, agents, and employees harmless from any and
all claims, actions, costs, judgments, damages or other expenses
resulting from injury to any person (including injury resulting
in death,) or damage to property (including loss or destruction),
of whatsoever nature, to the extent arising out of the negligent
performance of this contract by Engineer (including but not
limited to, the negligent acts or omissions of Engineer's
employees, agents, and others designated by Engineer to perform
work or services attendant to this contract). Engineer shall not
be held responsible for any claims, actions, costs, judgments,
damages or other expenses, directly and proximately caused by
the negligence of City.
13. Insurance:
13.1. Engineer shall, at its own expense, at all times
during the term of this contract, maintain in force:
13.1.1. A commercial general liability policy
including coverage for contractual liability for
obligations assumed under this contract, blanket
contractual liability, products and completed
operations and owner's and contractor's protective
insurance;
13.1.2. A professional errors and omissions
liability policy; and
13.1.3. A comprehensive automobile liability
policy including owned and non-owned automobiles.
PAGE 6-ENGINEERING SERVICES AGREEMENT (p:agree\brown-en.k)
13.2. The coverage under each liability insurance policy
shall be equal to or greater than the limits for claims made
under the Oregon Tort Claims Act with minimum coverage of
$500,000 per occurrence (combined single limit for bodily injury
and property damage claims) or $500,000 per occurrence for bodily
injury and $100,000 per occurrence for property damage.
Provided, however, that coverage for professional errors and
omissions liability may be for a minimum coverage of $100,000.
13.3. Liability coverage shall be provided on an
"occurrence" basis. "Claims made" coverage will not be
acceptable, except for the coverage required by subsection
13.1.2.
13.4. Certificates of insurance acceptable to the City
shall be filed with City prior to the commencement of any work by
Engineer. Each certificate shall state that coverage afforded
under the policy cannot be cancelled or reduced in coverage
cannot be made until at least 30 days prior written notice has
been given to City. A certificate which states merely that the
issuing company "will endeavor to mail" written notice is
unacceptable.
14. Default:
14.1. There shall be a default under this contract if
either party fails to perform any act or obligation required by
this contract within ten days after the other party gives written
notice specifying the nature of the breach with reasonable
particularity. If the breach specified in the notice is of such
a nature that it cannot be completely cured within the ten day
period, no default shall occur if the party receiving the notice
begins performance of the act or obligation within the ten day
period and thereafter proceeds with reasonable diligence and in
good faith to effect the remedy as soon as practicable.
14.2. Notwithstanding subsection 14.1, either party may
declare a default by written notice to the other party, without
allowing an opportunity to cure, if the other party repeatedly
breaches the terms of this contract.
14.3. If a default occurs, the party injured by the default
may elect to terminate this contract and pursue any equitable or
legal rights and remedies available under Oregon law. All
remedies shall be cumulative.
14.4. Any litigation arising out of this contract shall be
conducted in Circuit Court or District Court of the State of
Oregon for Jackson County.
15. Termination without Cause:
15.1. In addition to the right to terminate this contract
under subsection 14.3, City may terminate by giving Engineer
written notice sixty days prior to the termination date.
PAGE 7-ENGINEERING SERVICES AGREEMENT (p:agree\brown-en.k)
15.2. If City terminates the contract under subsection
15.1, Engineer may complete such analyses and records as may be
necessary to place its files in order and, where considered
necessary to protect its professional reputation, to complete a
report on the services performed to date of termination.
15.3. If City terminates the contract under subsection
15.1, Engineer shall be paid for all fees earned and costs
incurred prior to the termination date. Engineer shall not be
entitled to be compensated for lost profits.
16. Notices: Any notice required to be given under this
contract or any notice required to be given by law shall be in
writing and may be given by personal delivery or by registered or
certified mail, or by any other manner prescribed by law.
16.1. Notices to City shall be addressed to the contracting
officer at the address provided for the City in Recital A above.
16.2. Notices to Engineer shall be addressed to the
engineer's representative at the address provided for the
Engineer in Recital A above.
17. Assiqnment: City and Engineer and the respective
successors, administrators, assigns and legal representatives of
each are bound by this contract to the other party and to the
partners, successors, administrators, assigns and legal
representatives of the other party. Engineer shall not assign or
subcontract Engineer's rights or obligations under this contract
without prior written consent of City. Except as stated in this
section, nothing in this contract shall be construed to give any
rights or benefits to anyone other than City and Engineer.
18. Modification: No modification of this contract shall be
valid unless in writing and signed by the parties.
ENGINEER
Fed. ID # 94-1446346
CITY
REVIEWED ~S ~TO CONTEN~k
C~ty Department He~d )
Date: ~--~
REV~E~,~O FORM
By .~.f~ ~
City Leqal ~ounsel
Date: ~/~)/~--~
Coding
(for City use only)
PAGE 8-ENGINEERING SERVICES AGREEMENT (p:agree\browo-en.k)
BC
Brown and Caldweli
Consultants
2300 Oakm0nt Way
Suite100
Eugene
Oregon 97401-5556
(503)686 9915
FAX (503)686d417
April16,1992
Mr. Steve Hall
Director of Public Works
City of Ashland
20 East Main Street
Ashland, Oregon 97520
13-92-27
Dear Mr. Hall:
Thank you for selecting Brown and Caldwell for the design and construction
management of the Ashland digester modifications. We are eager to begin work
on this challenging project and look forward to working with you and your staff.
We have received your letter of April 9, 1992, and the contract form you
provided is currently being reviewed by our legal department. We understand
your budget constraints and intend to design a project to fit with your budget.
Construction cost estimates at each stage of the project will help you make
decisions on which project features should be included.
The drawing list provided during our previous work with you on digester
improvements has been trimmed to provide a level of engineering effort
consistent with your budget. We have prepared a detailed scope of engineering
services and cost estimates for the design, bid period, and construction phases of
the project. The following sections discuss the project scope, costs, and
schedule.
Design Phase
Initial work on the project will be a predesign effort to define design criteria and
develop an approach for implementing the improvements. Predesign tasks include
recommending a replacement cover for the existing anaerobic digester, selecting
sludge circulation and transfer equipment, and analysis of the adequacy of the
existing boiler and gas system. Construction techniques and schedule will be
discussed. A technical memorandum outlining the predesign results will be
provided for your review.
Mr. Steve Hall
April 17, 1992
Page 2
Upon obtaining and incorporating your suggestions for the design, we will
proceed with preparation of the detailed plans and specifications. We have made
three key assumptions in defining our scope for detailed design.
The existing plant electrical system is likely adequate to serve the new
sludge circulation and transfer equipment. We anticipate a vendor
package for the equipment will include local control with all other
control and all power provided by the existing motor control systems.
The design will not include improvements to the existing electrical or
control system.
The boiler analysis will include interviews with the personnel who
conducted a recent inspection of the boiler and an analysis of interim
boiler capacity requirements. Recommendations will be made on the
basis of the analysis, but the design will not include boiler
improvements.
There will be two technical design reviews for this project. At the first
review we will solicit input and gain consensus on the approach
presented in the predesign technical memorandum. The second review
will present the plans and specifications for comment at approximately
the 90 percent completion level. To make best use of the expertise of
senior members of the Brown and Caldwell staff at the earliest possible
point in the project, we recommend that the first review take place at
our office in Eugene. The second review could be held in either Eugene
or Ashland at your convenience.
Our approach for this phase is to minimize both the design effort and changes to
the electrical and boiler systems until definitive plans are made for the future of
the Ashland wastewater treatment facility. We will maintain regular
communication with you and your staff throughout the course of the work with
regard to detailed design decisions.
You will note in the breakdown of services for the design phase that we will
provide a coordinating cross-check of the contract documents and a construction
cost estimate prepared by our construction management division. The
coordinating cross-check will be conducted by a senior level engineer and will
provide a third party check for completeness and cohesiveness of the bid
document. The cost estimate will provide you a preview of the project
construction cost and will assist in assessment of the bids. These tasks complete
the design phase of the project.
Browl~ a~l(I Calllwell
Mr. Steve Hall
April 17, 1992
Page 3
Bid Phase
To assure a smooth transition from design to construction, we will provide
assistance to the City while the contract is out for bid. During this time we will
review questions that arise during the contractors' bid process and will
incorporate additional information required for bid into the contract by addendum.
Construction Phase
Construction phase services include office and field engineering. Office
engineering comprises submittal review, clarification and change order assistance,
attendance at selected jobsite meetings, and involvement in the final inspection
and punchlist preparation. These activities will be closely coordinated with you
and your staff to ensure that your input is included in all direction to the
contractor.
Field engineering will include on-site inspection of critical construction activities
throughout the course of the project. However, due to the cost of providing
extensive inspection services, and the City's budget limitations, we cannot
provide day-to-day inspection. We have allowed ten inspection visits to the site
during construction of the project. The contractor's work schedule will determine
the timing of the inspection trips. We will depend on the City to assist us in
maintaining communication with the contractor to ensure that critical
construction activities are inspected for conformance with the contract
requirements. We are confident that we can obtain a quality project by working
together for efficient oversight of construction.
To most efficiently use the limited budget available for inspection, we are open to
the possibility of utilizing City staff or subcontracting a portion of the inspection
to a local inspector. However, our attempts to identify an available, local
inspector have not been successful. We have therefore included costs for a
limited amount of inspection by our own staff. Material testing services will be
provided by local subconsultants to Brown and Caldwetl.
As the project is completed, we will be available to assist with final testing and
start-up of the new facilities and with finalizing record drawings for your future
use. These activities will be included as "Special Services" in the engineering
services contract. The contract cost will not include these services; however, if
your budget allows, the City may wish to add these services to the contract by
amendment.
Brown and Caldwell
Mr. Steve Hall
April 17, 1992
Page 4
We assume the City of Ashland will handle administration of the contract with
the contractor, process all progress payments to the contractor, and make all final
decisions regarding contract matters. Brown and Caldwell will be available to
provide recommendations and assistance to the City regarding contract
administration questions.
Project Costs
Spreadsheets are enclosed outlining the costs for the engineering services
described above. For your convenience, the cost information is broken down into
tasks for design services, bid period services, and construction services.
Project Schedule
Brown and Caldwe~l is ready to begin work on your project as soon as we are
authorized to proceed. A preliminary schedule for design and construction is
provided below.
· Award engineering service contract - May 1, 1992
· Notice to proceed - May 1, 1992
· Begin preliminary design - May 1, 1992
· Preliminary design report and review - June 8, 1992
· 90 percent design review - July 13, 1992
· Final plans and specifications - July 24, 1992
· Advertise for bids - July 24, 1992
· Open bids - August 21, 1992
· Award contract - September 4, 1992
· Start construction - September 11, 1992
· Complete digester structural modifications - November 11, 1992
· Project completion - January 15, 1993
I~row~ a,~(~ Caldwcll
Mr. Steve Hall
April 17, 1992
Page 5
We have tailored the above scope and cost to fit the project as discussed with
your staff. Please call us if you need further information or have specific
questions or concerns. Once again, we thank you for the opportunity to serve
the City of Ashland.
Very truly yours,
BROWN AND CALDWELL
John Holroyd
JEH:WBS:cm
Enclosure
Brown and Caldwell
PROJECT: ASHLAND DIGESTER UPGRADE - DESIGN
DATE:APRIL 15, 1992
Labor Catalog/
Task Numbers
1 2A 2B 2C 2D 2E 2F 2G 2H 2 I Tolal
Cost. $
PROFESSIONAL
Executive II 16 8
Exec I/Exec Engr
Chief-Engr, Sci, Gaol/Hydro 8
Mng-Engr, Sci, GeolAHydro 4 4
Supv*Engr, Sci, GeoVHydro 40
Principal-Engr, Sci, Gaol/Hydro 12 32 16
Sr-Engr, Sci, Gaol/Hydro 56 .80 45 75 73 8 80 12 16
Engr, Sci III, Geol/Hydro 20 8 20 20 56 8
Aec Engr, Sci II, Asc Geol/I-lydro
Asr Engr, Sci I, Asr GeoFHydro
Engr Aide, Asc Sci
Asr Scientist
SUBTOTAL 80 80 53 95 113 48 136 48 48 16
TECHNICAL
Sr Engr Tach
Engr Tech
Asc Engr Tach
Ast Engr Tach
Std Trainee II
Std Trainee I
Manager, CAD
Chief Drafter
Supv-CAD Op, Drafter
Lead-CAD Op, Drafter
Sr-CAD Op~ Drafter
CAD Operator, Drafter
CAD Op Trainee, Ast Drafter
CAD Plotter Op, Drafter Trainee
Chief Designer
Supv Designer
Pdncipai Designer
Sr Designer
Designer
Asr Designer
SUBTOTAL
ADMINISTRATIVE
/~lm Mgr
Supv-Adm/K)fc Sn/, Sr Proj Coord
WP Supv, WP IV, Proj Coord II
WP III, Proj Coord I
WP II, Sr Proj Ast, Ofc WI~ III
WP I/Proj Ast/Ofc Wkr II
Office Worker I
SUBTOTAL
DESIGN PHASE
1-PREDESIGN
2A- DESIGN MANAGEMENT
2B- GENERAL DRAWINGS
2C - STRUCTURAL DRAWINGS
2D - MECHANICAL DRAWINGS
2E - ELECTRICAL DRAWINGS
2F - SPECIFICATIONS
2G - DESIGN REVIEW
2H - CROSS CHECK
2 I - COST ESTIMATE
4 59 95 137 24
4 0 59 95 137 24 0
12 8 40
0
6 325
0
0
0
0
0
0
0
0
0
24 44~.00
0 0.00
8 1136.00
8 1032.00
445 40060.00
1~ 10164.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0
0 0.00
0 0.00
0 0.00
0.00
0.00
12 B 0 0 0 0 40 8 4 0 72 3384.00
Other Direct Costs
Transportation 360.00
Per Diem 0.00
Communication 400.00
Reproduction 2750.00
Computer 3000.00
SUBTOTAL 6510.00
Markup on ODC's 651.00
TOTAL COST 96335.00
0 0.00
0 0.00
0 0.00
8 4 72 3384.00
0 0.00
0 0.00
0 0.00
0 6 0 325 18200.00
Labor Cate.qo~'
PROFESSIONAL
Executive II
Exec I/Exec Engr
Chief-Engr. Sci. Gaol/Hydro
Mng Engr. Sci. Get, Hydro
Supv-Engr. Sci. GeoUHydro
Prir~ipaI-Engr. Sci. GeofJHydro
Sr-Engr. Sci. Geol/Hydro
Engr. Sci Ig. G eolAHydro
.Asc Engr, Sci I[. Asc Geo,/Hydro
Asr Engr. Sci I. Asr Geol~lydro
Engr Aide. Asc Sci
Task Numbers Cos~, $
2J Total
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
4 4 408.00
20 20 1800.00
16 10 1232.00
SUBTOTAL
40 40 3440.00
TECHNICAL
S~ Engr Tach
Engr Tach
Asc Engr Tech
Asr Engr Tech
Std Trainee II
Std Trainee I
Manager, CAD
Chief Drafter
Supv-CAO Op. Drafter
Lead-CAD Dp. Drafter
St-CAD Dp. Drafter
CAD Operator. Drafter
CAD Dp Trainee. Asr DreJter
CAD Plotte~ Op. Drafter Trainee
Chief Designer
Supv Designer
Principal Designer
Sr Designer
Designer
As~ Designer
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0 0.00
0
0 0.00
0 0.00
0 0.00
0 0.00
SUBTOTAL
ADMINISTRATIVE
Adm Mgr
Supv-Adn'~)fc Srv, Sr Proj Coord
WP Supv. WP IV, Proj Co(xd II
WP Ill. Proj Coord I
WP g. Sr Pr~ AsL Dfc Wkr I1{
WP VPro~ Ast/Ofc Wkr II
Office Worker I
SUBTOTAL
BID PHASE
2J - BID PERIOD SERVICES
Other Direct Costs
Transportation
Per Diem
Communication
Reproduclion
Computer
SUBTOTAL
Markup o? OOC's
0.00
0.00
0.00
188.00
0.00
0.00
0.00
90,00
TOTAL COST 461800