HomeMy WebLinkAbout1984-032 Change Order-StraamEngineers, Inc.
Contract Change Order
CITY Ashland
ORDER No. 2 STATSregon
DATE~)e
CONTRACTFOR Tolman Creek Reservoir pt. 17, 1984
OWNER
City of Ashland, Oregon
TO Visar Co., Inc., 933 Bellview Avenue, Ashland, Oregon 97520
(Contractor)
You are hereby requested to comply with the following changes from the contract plans and specifications:
DESCRIPTION OF CHANGES DECREASE IN INCREASE IN
CONTRACT PRICE CONTRACT PRICE
Change time of completion to November 21, 1984,
due to weather-related delays.
TOTALS
NETCHANGEIN CONTRACTPRICE
JUSTIFICATION: Worse than average weather in late 1983 and into April 1984.
The sum of $ is hereby
the total contract price (added to) (deducted from)
The adjusted contract price to date is thereby $
The tirade.provided for completion is increased to November 21, 1984
by ~b calendar days. (increased) O(~)~ ~va~) (r~lX~)
This document will become a supplement to the contract and all provisions of the
contract will apply hereto.
Accepted ~'-- - ~-'-*'
(Contractor) Visar Co., Inc. (Date)
Recommended '-~&~ /',-] .'--2 . '
k,--',~:, ~- September 17:
(Engineer)
Approved f~_]
(Owner)
806022-2L,~
1984
claSP'.Si rri ne, Inc.
:
-- ..~ (Date~