HomeMy WebLinkAbout2004-238 Contract Chg Order #2 -Dunlap Contracting
CITY OF ASHLAND
DEPARTMENT OF PUBLIC WORKS
CONTRACT CHANGE ORDER NO. 2
PROJECT:
TOLMAN CREEK ROAD LID
DATE: Oc:tober 29, 2004
PROJECT NO.: 00..17
LOCATION: TOLMAN CREEK ROAD
CONTRACTOR: DUNLAP CONTRACTING INC.
You are requested to perform the following described work upon receipt of an approved copy of this
document or as described by thH Engineer:
Item No. Description Quantity Unit Price Amount
CO2 Tolman Creek LID
Item A Install Bus Stop Benches and Signs Lump Sum $3,271.00 $3,271.00
Item B Additional Excavation at Siskiyou Bv. Lump Sum $550.00 $550.00
Item C Excavation for Drain Line at 677 Tolman Creek Lump Sum $300.00 $300.00
Item D Relocate Mail Box Structure Lump Sum $850.00 $850.00
Item E Install Area Drains Lump Sum $1,982.00 $1,982.00
Item 5 Additional Pavement Grinding 919.39 s.y. $12.00 $11,032.67
Original Contract Amount
Contract Adjustment
Total this Change Order
Previous Change Order
F\evised Contract Total
$695,779.70
$50,779.70
$17,985.67
$20,238.50
$683,224.17
The time provided for completion of this contract is increased by two calendar days. This
document shall become an amendment to the contract and all provisions of the contract will
apply.
Recommended By: k;.j()L _
Ung~~~
Approved By: ~~
n~!lneer //..-.. ~
./ ;'.,.". ~ ,.
(/ )/-// /
._v .;/( I ./ '."7
Contra~tor 7.
Dunlap Contracting Inc.
PO Box 1951
Jacksonville OR 97530
IO/Z9/cx:f
Date
z~ OG/-04
Date
10(z ~ 10'-1
Dat I
Accepted By:
ENGINEERING
20 E. Main Street
Ashland, OreQon 97520
www.ashland.or.us
G:\pub-wrks\eng\dept-admin\ENGINEER\PROJECT\2000\00-17 Dunlap CO 2.doc
Tel: 54'1-488-5347
Fax: 541-488-6006
TTY: 800-735-2900
r~'
CITY OF
ASHL~AND
NOTICE OF TRANSMITTAL
TO:
Karl Olson
DATE:
PROJECT:
JOB NO.:
SUBJECT:
11/1/2004
Tolman Creek LID
00-1 7
Closeout Documents
THE FOLLOWING ITEMS ARE BEING SENT TO YOU:
1. Copy of final acc:eptation letter.
2. Copy of final payment request.
3. Original contract Change Order No.2..
4. Original requisition for final payment.
ENCLOSED X
UNDER SEPARATE COVER
REMARKS:
COPIES TO:
Department of Public ot: s
By: James H. Olson \
Title: City Surveyor/Pr . ct 1~anager
PUBLIC WORKS
20 E. Main Street
Ashland, OreQon 97520
www.ashland.or.us
Tel: 541-488.5587
Fax: 541-488-6006
TTY: 800-735-2900
r~'
CITY OF
ASJHLAND
October 29, 2004
Tom Dunlap
Dunlap Contracting InG.
POBox 1951
Jacksonville OR 97530
RE: TOLMAN CREEK ROAD LID PROJECT NO. 00-17
Dear Tom:
I am please to announce the final approval and acceptance of the Tolman Creek Road
LID Project No. 00-17. We have received many compliments on the project and
appreciate your diligence and hard work in providing a quality project for the City of
Ashland.
A final payment has been requested incl\,Jding a release of all withheld retainages which
will be provided to you at a later date. .
Please be reminded that you are required to warranty the materials and workmanship of
the project for a period of two years from this date.
Again, thank you for a ,job well done.
Si~1fd1-
James H. Olson
Project Manager
cc: Paula Brown
Roger Balbo
Karl Johnson
Mike Thornton PE, Thornton Engineering
)" ,
\.C/ r/ r;:J f
Engineering
20 E. Main Street
Ashland, Oregon 97520
www.ashland.or.us
Tel: 541/488-5347
Fax:541~488-6006
TTY: 800n35-2900
r~'
G:\pub-wrks\eng\dept-admin\ENGINEER\PROJECT\2000\OO-17 Dunlap Acceptance Itr.doc
I CITY OF I
ASHLAND
Public Works - Engineering Division
Date: October 29,20
To: Veronica Via
From: James H. Ols
Re: PROGRESS PA
IMPROVEMEN
Payment Memorandum
Dunlap Contracting Incorporated has requested an eighth and final progress payment for services rendered in the
construction of the Tolman Creek Road LI.D project.
Please make payment as follows:
Contractor: DUNLAP CONTRACTING INC.
PO BOX 1951
JACKSONVILLE OR 97530
Project Title:
Project No.:
Purchase Order No.:
Retainage:
Account No.:
Contract Amount:
Contract Adjustment:
REVISED CONTRACT:
Change Order:
REVISED CONTRACT:
TOLMAN CREEK ROAD LOCAL IMPROVEMENT PROJECT
2000-17
4660
5%
260.08.35.00.704200
260.08.12.00.704200 '
260.08.34.00.704200
260.08.17.00.704200
$
$
$
$
4.5% $
$
Street SDCs
Streets
Storm Drain SDCs
LID Resolution
additional LID
Total LID Contribution
320,000.00
45,000.00
40,000.00
266,144.00
12,080.17
278,224.17
$ 695,779.70
$ (50,779.70)
$ 645,000.00
$ 20,238.50 CO No. 1
$ 17,985.67 CO No.2
$ 683,224.17
COST ALLOCATION
I I~ IU 1\MUUN I
DESCRIPTION COST TO DATE DATE DUE
COSTS $683,224.17 $ 662,307.77 $20,916.40
RETAINAGE $0.00 $ (16,557.69) $16,557.69
$683,224.17 $ 645,750.08 $37,474.09
Please Pay:
$37,474.09
CC: Tom Dunlap
Paula Brown
Roger Balbo
Kari Johnson
CONTRACT AMOUNT REMAINING % Complete
$ 683,224.17 Contract Total 100.00%
$683,224.17 Cost to Date
$ - Amount Remalining
*
Ir~'1
G:PubWorks\Eng\DeptAdmin\Engineer\Project\OO-17 Dunlap Payment 8 and final
OCTOBER 28, 2004
FINAL ESTIMATE
DUNLAP CONTRACTING LLC
PO BOX 1951
JACKSONVILLE, OR 97530
Tolman Creek Road Project
City of Ashland, Oregon
DUE THIS
ESTIMATE
QuantitylAmount
o
PREVIOUS
PERFORMANCE
Quantit)jAmount
PERFORMED TO
DATE
CONTRACT
AMOUNT
Price IQuantityJAmount
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$500.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00 c'
$148.40 .
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$507.00
$0.00
$0.00
o
o
o
o
o
o
o
o
125
o
o
o
o
o
o
o
o
o
o
o
o
o
14
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
195
o
o
$15,000.00
$36,500.00
$20,790.00
$5,840.00
$19,650.00
$6,800.00
$2,530.00
$0.00
$2,161.90
$1,244.00
$888.00
$3,000.00
$3,000.00
$1,000.00
$0.00
$12,690.00
$35,748.00
$11,583.00
$30,340.00
$13,369.00
$780.00
$1,700.00
$16,100.00
$0.00
$375.00
$34,875.00
$11,850.00
$2,142.00
$1,000.00
$0.00
$9,455.00
$900.00
$480.00
$4,118.00
$9,520.00
$35,100.00
$23,268.00
$41,743.00
$59,417.10
$35,430.001
$46,046.00!
$18,256.001
$2,800.00
1
1
1890
365
1637.5
17
23
o
3326
311
222
2
1
1
o
282
1324
297
820
461
30
17
23
o
50
4650
6
1
1
o
1891
150
10
142
2380
1755
1108
642.2
1320.38
7086
17710
28
4
Amount
"$'15,000.00
$36,500.00
$20,790.00
$5,840.00
$19,650.00
$6,800.00
$2,530.00
$0.00
$2,161.90
$1,744.00
$888.00
$3,000.00
$3,000.00
$1,000.00
$0.00
$12,690.00
$35,748.00
$11,583.00
$30,340.00
$13,369.00
$780.00
$1,700.00
$16,100.00
$148.40
$375.00
$34,875.00
$11,850.00
$2,142.00
$1,000.00
$0.00
$9,455.00
$900.00
$480.00
$4,118.00
$9,520.00
$35,100.00
$23,268.00
$41,743.00
$59,417.10
$35,430.00
$46,553.00
$18,256.00
$2,800.00
Quantity
-
1
1
1890
365
1637.5
17
23
0
3326
436
222
2
1
1
0
282
1324
297
820
461
30
17
23
14
50
4650
6
1
1
0
1891
150
10
142
2380
1755
1108
642.2
1320.38
7086
17905
28
4
$15,000.00
$36,500.00
$20,790.00
$19,024.00
$4,632.00
$6,800.00
$2,310.00
$16,012.50
$2,161.90
$1,244.00
$520.00
$1,500.00
$3,000.00
$1,000.00
$8,790.00
$2,925.00
$35,748.00
$7,020.00
$28,675.00
$13,369.00
$806.00
$1,200.00
$16,100.00
$3,943.20
$375.00
$34,875.00
$11,850.00
$2,142.00
$1,000.00
$3,000.00
$7,380.00
$900.00
$480.00
$4,118.00
$7,712.00
$35,100.00
$23,268.00
$13,000.00
$70,560.00
$23,035.00
$50,185.20
$20,864.00
$700.00
1
1
1890
1189
386
17
21
10675
3326
311
130
1
1
1
293
65
1324
180
775
461
31
12
23
372
50
4650
6
1
1
2
1476
150
10
142
1928
1755
1108
200
1568
4607
19302
32
1
Unit
rn,ooo.oo
$36,500.00
$11.00
$16.00
$12.00
$400.00
$110.00
$1.50
$0.65
$4.00
$4.00
$1,500.00
$3,000.00
$1,000.00
$30.00
$45.00
$27.00
$39.00
$37.00
$29.00
$26.00
$100.00
$700.00
$10.60
$7.50
$7.50
$1,975.00
$2,142.00
$1,000.00
$1,500.00
$5.00
$6.00
$48.00
$29.00
$4.00
$20.00
$21.00
$65.00
$45.00
$5.00
$2.60
$652.00
$700.00
Unit
LS
lS
CY
CY
SY
EA
EA
SY
SY
LF
IF
EA
LS
lS
LF
LF
IF
LF
LF
LF
LF
EA
EA
LF
LF
LF
EA
EA
EA
EA
LF
LF
LF
SY
SY
CY
CY
TON
TON
SF
SF
EA
EA
No
- .
1 Mobilization
2 Temp Protect & Direction of Traffic
3 excavation & Subgrade Preparation
4 Below Grade Patch Exc-Exist. Pavement
5 A.C. Pavement Profiling(Grinding)
6 djust Manhole
7 djust Water & Gas Valves & Monuments
8 Paving Fabric
9 Subgrade Fabric
10 Remove Concrete Curb & Gutter
11 Remove Exist. Straight Curb
12 Remove Exist. S.D. Manhole
13 Remove exist Trees & Stumps
14 Remove Exist. 5S Clean-out & 10' Pipe
15 24" S.D. Class "B" Backfill
16 24" S.D. Class "E" Backfill
17 18" S.D. Class liB" Backfill
18 18" S.D. Class "E" Backfill
19 12" S.D. Class liB" Backfill
20 12" S.D. Class "E" Backfill
21 8" & 10" S.D. Class "B" Backfill
22 Connect Exist. 4" Drains to S.D>
23 Curb Inlets
24 Concrete Straight Curb
25 Concrete Curb & Gutter 7" Face
26 Concrete Curb & Gutter
27 48" S.D. Manhole
28 48" San. Sewer Manhole
29 Concrete Diverter Island @ Siskiyou
30 Reconst. Irrigation Box W/Lid & Frame
31 Remove Existing Culverts
32 Fumish & Place 2" PVC under Sdwalk
33 8" Irrigation Line
34 SawcutiRemove PC Conc. Surface
35 SawcutlRemove AC Pavement
36 4"-0 Shale Base
37 1"-0 Aggregate Base
38 1.5" AC Pre1evel & Drway Tie-ins "C"
39 2.5" AC Overlay Class "C"
40 Conc. Drway Apron 6" Thickness
41 Conc. Sidewalk 4" Thickness
42 Handicap Pamps
43 Parallel Style Handicap Ramp
Item
o
.,,0
zd
~m
'm
m::o
C/)'"
-i0)
~N
~g
m~
c... 0
f> ~
~ >
0,,-0
zOO
<mO
,OZ
r-X-l
J11....~
0<00
::o~-I
<0 -
....... Z
(11 G)
w r-
o r-
o
got
~-
o 3
-0,)
~::J
~O
-CiJ
Q) (I)
5."
- ;0
00
CiJ D)
(Qo.
0-0
~ a
(D'
Sl
(:It "'"
cow
:,..:,..
(:It (:It 0 0 "'" (:It
00Q)000
000000
000000
"'" "'"
~,!JJ"(:It"'"
COI\)O!WQ)
~~g8~~~~~~~~~~~~~~~~~
888888888888888888888
o
~~ me
C!:C/)c
o 0 0 0 0 0 0 0 0 0 0 0 0 0 j\) .... 0 o~ :::f mi
~ s:: :
5~~
cm~
~
-
"'" "",tf
~.... "'" ~" !>>
~~(:It""'~~
o!oooow
8;gg8g~
o
....c
I\) Q) Q) m"
01 I\) ~
01 ..a. ~ C!: ::0 ""Q
.... .... 0 0 00 01 " :::0
>om
3 ::0 <I
03:0
c ::i> c
~zC/)
o
m
*
ioIt ioIt ioIt "'" W
..... * !D .w ." !>>
~~~~~~
O!OQ)oow
8;8g8g~
o
.IJC: -c
I\) ~ ~ m
g: .... .... ~ C!: ::tJ
.... .... I\) .... 00 01 "T1
~OO
3 ~ ::o!!
g m
~
-
o
.... 11m.
o . a (1
co I\) ........ -. ~ o.
o .... W ..a. 0> " s:.
)> 0 Zj
* ioIt5 c~
.... "'" "'" W c: Z ~
(:It "'" s>> _w !>> ~I::J -i C1
~~s~~m- -i
0101\)001\)
888g8g
"
:J.
Q
C
::J
;:;:
c
~
;::;:
;:;:
(I)
3
Z
o
*
~~~~*
~8~88al
gggggg
~
Co
Q)
I\)
:...,
01
(:It~~~t1t1~~~
W8~~~g:~~~
80~000""o..a.
gggg8g8gg;
"
co
"
i\)
~
.... ~
w....m......a.....~..a.~
(:It~~~~~~~~ ~
woo>wWO!WI\)Q) co
88~888~8~ ~
8888888gm ~
"
co
.... . :-"
00 0> co I\)
w....O>..........a.......a.I\)O~
~
....
I\)
01
o
o
........ W
w..a.~..a.........~....~
."
~
~I ***ioItiolt***
* _..a. ~ !'J _w .w ,!JJ ~ }.II
woo>wWO!WI\)CO
. gg~ggg~g<>>
88888888~
m
o
-'" .... .... .... .... 0 0 0 0 0
I
"'" (:It **
~ ~I\) * -I\) ~
o W~..
8~~~~~mo;m~
g8gg8g8;ggg
....
0>
.... 0000........(11....
~*ioIt (:It ioIt*
~~t;~~~~~~~
000"01001........000>
01\)....0000>000>0
OOOOOOUtOOO
000000000>0
....
0>
........~~.....................<.n.....
m
~~* * _I * *ioIt" *
,!JJ~~***~* ~.*~ !'J~,!JJ ~
OCON~W~W~-~ ....O*wwO!ioItl\)(:It
000~~8~--~~mOO""880I\)0""
?!'>:"'P. P!"!>>iPQ:!=>!=>!D. . !=>~!=>~
8888g8!8~~~8888gg8B~
i
ioIt
0>
i\)
01
mmrrrrOrr r rrmrmo~
)>)>"TIenenen-(en"TI "TI "TIen)>en)>z
mg~~~~~~~ g:~&~~~t
::1 ~ ~ ~ i -u ';j I>>" ~ tp ~ ~ :J ., -u en ~ ;'>1
~s~~3f~:J:J~.:Jna~-!~~o
-:J<~ -~~- _~m I-m-u
g=~:J~~g~~_i~~_~~O'~
-..,- -i I>>-IIII-I>>:JCI>>-' ~n
oa~~~= ~(1Ii(1l2~en~~~~
gl>>en:J~ ~3 3 o~r~l>>:J
q~CI>>qCl>> ~~~~0:J-1>>~~
o:J<~8 -~-m::l~~~~
~O~:J 0 ~~ ~~O
...-.~ a ~.~;::;: :J(Q~.
~~m 2 ~ -~ (Q ~
m<~ ~ ~ ~~ I>> ~
o Ai n m )> VI .... Ii)
)( <m ~ :: =0 0 '<
~CI>>~ ~ OJ m~ a ~
0..... - 1111>>; (I) -.
i~~ I ~ ~~ ~ ~
:B ~ .s oS'=: ~
nom mOt3 (I)
- ii' iJ'
s- ~ (11 n~.
:J -
~
'fj)'ij;u;u;u;u;u;u;::;:i
m~~mm~~~~~
":J~oC;:~~i':i
~I(I)(6cD9cg:Ji-
-'-CJ)O era flit ~ n-.
~-os."~-~:T::I
(Q~"O@~!!!. ~!. c~
(') I>> "0 en -. c;: ;. = !!. 6
OJc!.iii"::Io...~:J-
o.iJ(I)~ ~~.:;~
;::;::i" I>> '< ~ CI>> ~ < .
Uls.g ;-o;~~
en UJ 0;"
cO' :r
'3' <
"tJ 01
o (11
a 0
1'1.)
CI
~~
01
~.
C)
=r
iii"
nil
CI)
r-t-
-,
O~
O~
....)
~)
C)
.....
:....
.....
r}
~
co
~!~
(I) (/) ~
iU-i3
-. 0 (I)
~ C.
~c_:
&>>0
coo
&>>
co
."
:j"
!!!.
-c
&>>
'<
3
CD
::J
-
QQ
~m
0"1 w
-"""'""N
(1I"'I~
O,f:l..O
(:)~(:)
0)......0
-C~
~. 3
0.0
-iC:
o~
eo
Q) c:
co (I)
~
w
......
..
.......
,f:I..
(:)
co
c
c:
(I)
-
=r
iif
(I)
en
ct.
3
Q)
co
CITY OF ASHLAND CITY RECORDER'S COpy
20 E MAIN ST." DATE'
ASHLAND, OR 97520 11/16/2004
(541 ) 488-5300
Page 1 / 1
,PO NUMBeR"
05578
VENDOR: 007981
DUNLAP CONTRACTIING llC
PO BOX 1951
JACKSONVillE, OR 97530
SHIP TO: Ashland Public Works
(541) 488-5587
51 WINBURN WAY
ASHLAND, OR 97520
FOB Point:
Terms: Net
Req. Del. Date:
Speciallnst:
Req. No.:
Dept.: PUBLIC WORKS
Contact: Paula Brown - PW
Confirming? No
:;::~:'i:::cUIr1ft'!JrtCi&~~si ;~\:jL~\i~;Diii'fta;~[,:~{ttf.':
~tg~'~]~~,;~R<
,: ..:~t~, ".~' .~ '.' y.:':~ .~.~,?~-:<
BILL TO: Account Payable
20 EAST MAIN ST
541-552-2028
ASHLAND, OR 97520
20 916.4
0.00
0.00
20,916.40
E 260.08.12.00.704200
E 260.08.17.00.704200
E 260.08.34.00.704200
E 260.08.35.00.704200
1 459.28
7 782.85
1 297.14
10377.13
,&.,( ~ //~~h5L'
Auth . ed Signature
VENDOR COpy
A request for a Purchase Order
REQUISTION FORM
CITY OF
ASJHLAND
Date of Request: 110/29/20041
THIS IS A REQUEST FOR A:
Required Date of DHliverylService: IASAP
[ X] Change Order (existing PO# 46613
Vendor Name:
Address:
City, State, Zip
Phone:
Project Title:
Project Number:
DUNLAP CONTRACTING
PO BOX 1951
JACKSONVILLE: OR 97530
TOLMAN CREEK ROAD LOCAL IMPROVEMENT DISTRICT
00-17
Services Only Solicitation Proce!;s:
[ ] Exempt [ ] 3 Written Quotes (copies
attached)
[ ] Sole Source [X] Invitation to Bid (copies on
file )
[ ] Less than $5000 [ ] Request for Proposal (copies
on file)
Description
Total Cost
Change Order No. 1
Tolman Creek Road Local Improvement Construction
Contract Adjustment
Change Order No. 2
Account Number 260.08.35.00.7042100
Account Number 260.08.12.00.7042100
Account Number 260.08.34.00.7042100
Account Number 260.08.17.00.7042100
, Supervisorl Dept. Head Signature: ~~
uistiion foc . I eerily tha the above request meets with Ctiy of Ashland Solicitiation Process requre~' be provided when necessary.
G:Pub\Vrl(s\Eng\OO-17 Dunlap CO 2 Req 1004
Updated on: 7/15/02