HomeMy WebLinkAbout2006-150 CONT Chg Order - LTM Inc
t for rt';l3~',',0
REQUISTION FORM
THIS IS A REQUEST FOR A:
[X ] Change Order (existing PO#054~
~?Ii~o
Vendor Name:
Address:
City, State, Zip
Phone:
Project Title:
Project Number:
L 1M INCORPORATED
PO BOX 1145
MEDFORD OR 97501
CITY OF
ASHLAND
Date of Request:
Required Date of Delivery/Service: 1__
2004 MISCELLANEOUS CONCRETE PROJECT
200404.120
Services Only Solicitation Process:
[ I Exempt [ ) 3 Written Quotes (copies
attached)
[ I Sole Source [X I Invitation to Bid (copie~ on
file)
[ I Less than $5000 [ ) Request for Proposal (copies
on file)
Description
2004 Miscellaneous Concrete project including Downtown Pedestrian Safety
Improvements; Sidewalk School Link; Nevada Street LID and Miscellaneous
Concrete Repairs.
Change Order No.1 for the 2004 Miscellaneous Concrete Project, Itemized
below. Change order total: $16,990.71
Dash No. 45101 Extra sidewalk and under structure removal.
Dash No. 45102 Costs associated with lighted arrow board for traffic control.
Dash No. 45103 Installation of 8 inch storm drain
Dash No. 45104 Installation of 4 inch storm drain
Dash No. 45105 Utility conflicts at Lithia Way & 1 st Street
Dash No. 45106 Installation of 8 inch storm drain at 1st & Lithia
Dash No. 45107 Adjustments to irrigation utilities
Dash No. 45108 Removal of curb and weepholes
Dash No. 45109 Retaining wall installation
Account Number
Account Number
Account Number
Total Cost
260.08.12.00.704200 - 57% ($9,684.70)
260.08.35.00.704200 = 31% ($5,182.18)
Supervisorl Dept. Head Signature:
tha the above request meets WIth Ctiy 01 Ashland Solicitiation Process require e
Z ';/TI~ u,
Updated on: 10113103
PROJECT ACCOUNTING WORKSHEET
CITY OF
ASHLAND
PROJECT TITLE
2004041
12004 MISCELLANEOUS CONCRETE PROJECT
PROJECT NUMBER (YEAR XX)
PROJECT DESCRIPTION
Miscellaneous concrete involves several projects identified in the Capital Improvement
Projects: Nevada Street LID; Downtown Pedestrian Safety; Sidewalk School link and
Miscellaneous Sidewalk Improvements. Bids for construction were advertised twice and
the final accepted bid was modified to only include the Downtown Pedestrian Safety
Imorovements and the Nevada Street LID and some extra sidewalk reoairs.
Department
Project Manager
Department Head
BUDGET INFORMATION
Identify fiscal year I potential splits
Identify Funding Codes
and Funding Code names
Engineer Name
PO
COST
Public Works Engineering
Jim Olson
Paula Brown
12004-2005
Engineering
Construction
260.08.12.00.704200 - 85% $
260.08.35.00.704200 - 15% $
$
Thornton Engineering
$
5107
15,850.00
13,472.50
2,377.50
15,850.00
260.08.12.00.704200 $
260.08.35.00.704200 $
26008.41.00.704200 $
$
$
CONSTRUCTION .120
contractor name L TM Inc.
PO pending
budget estimate
Nevada Street $ 249,050.50
SDC Street Fees $ 37,357.58 15%
LID $ 49,810.10 20%
Developer Fees $ 40,000 00 15%
Street Fees/Rates $ 124,525.25 50%
$ 251,692.93
Downtown Pedestrian Improvements $ 123,269.50
ODOT Grant $ 35,000.00 29%
SDC Street Fees $ 70,615.60 57%
Street Fees/ Rates $ 17,653.90 14%
$ 123,26950
Extra Concrete Work $ 13,017,30
SDC Street Fees $ 10,413.84 80%
Street Fees/ Rates $ 2,603.46 20%
$ 13,017.30
bid I contract tota I
Contingency
change order
total
CONSTRUCTION MANAGEMENT .150
engineer name
PO
budget estimate
bid I contract tota I
changes
total
PERMIT COSTS (Building Dept) .170
budget estimate
final costs
$
385,337.30
5%
16,990.71
404,604.17
$
$
...w
..."1
179,782.61 Street Fees
118,387.02 Transportation SDC
49,810.10 LID Fees
40,000.00 Developer Fees
387,979.73
$ 219,782.61
57%
31%
13%
100%
G:Pub.wrks/eng/dept-adminlenglprojectl2004/04-04 Pro; Acct Worksheet 2 06.xls
Dash-NulI/berSulI/lI/ltry
I of 2
iHiscellaneous Concrete Project Dash-Number Summan'
Dash-Number #-15101- Time & Alaterials to remol'e sidewalk and place metal plates over exis/in~ 11/ewl
sheetint:
L TM uncovered a section of sidewalk, at the intersection ofN. Main and Water St, which had been
previously poured on top of metal roofing which has been placed on top of railroad rails. Under this
section was an open space that this rail and sheeting combination was supporting the sidewalk over. Pieter
and Jim came out and looked at the situation and decided that the easiest and cheapest fix was to remove
the existing sheeting and replace with steel plates. After that the new sidewalk could be poured on top of
the steel plates. The hole under this area was also backfilled with material removed from the adjacent area.
Dash-Number #451302 ~ Arroll'bollrd Rental
The project did not include a bid item for an arrowboard for the downtown portion of the project. Jim
thought it would be a good idea to include one due to decreased vision clearance in the downtown corridor.
DlIsh-iVumber #45103 - Time & Ala/erials to install additional 8-in storm drain
Plans showed that a new 12-in storm drain line was to go from a new inlet adjacent to the Washington
Mutual driveway on E. Main and travel into E. Main and intersect the existing storm drain. A new
manhole was also to be installed at this location. Due to conflicts with the water main in E. Main, there
was not enough room for the installation of the manhole or the 12-in pipe. The new storm drain line was
rerouted and downsized and taken to a new basin on I sl Street.
Dash-Number #4510-1 - Time & iHlIferials to il1stall additional 4-in storm drain
Plans showed that a new 12-in storm drain line was to go from a new inlet along Oak Street, on the west
side, and travel into E. Main where it was to intersect the existing storm drain. The existing storm drain
was not in the location that was sown on the plans but rather approximately IS-ft further into E. Main. It
was decided that the inlet could still be install along Oak Street and due to the low volume of water that this
basin would gather, two 4-in storm drain pipes under the sidewalk and daylighting along E. Main would
work to get rid of the water. There is also some fall around the bumpout to deal with any excess water that
is not dealt with.
Dash-Number #45105 - Time & ll1aterials to work around existin!! utilities either in conflict or not
shown 011 plans
Plans showed a 12-in storm drain line running south along the easterly side of 1st Street from Lithia Way to
a new curb inlet. During digging multiple utilities were found that were not shown on the plans that were
either in conflict and had to be moved or had to be worked around in order to install the new storm drain
Ine.
Dash-Number #45106 - Time & Materials to ins/all additiol1al 8-il1 storm drain and catch basin
An additional catch basin and storm drain line was requested by ODOT after there review of the plans.
This catch basin will collect storm water before it reaches the handicap ramp on the southwest comer of 151
Street and Lithia Way.
Dash-Number #45] 0 7 - Time & ~ll1ferials to complete ad;ustments at irri~ation diversioll box
Plans showed the existing irrigation diversion box on the comer of Helman Street and Nevada Street to be
used as the location for a new curb inlet. The existing box was to far away from the face of curb to make
this work and had an existing line that needes to be reinstalled into the box, so adjustments were made to
both the inlet and the irrigation diversion box to make the system flow the best it could.
H:\PROJECTS\04-04 (2004 Miscellaneous Concrete Project)IPaymentslDash-Number Summary - Miscellaneous Concrete
Project. doc
8/3/2006 10:32:33 AM
I
'"
'"
~
J
f
r:
~ "" I;l
~ ~ ~ ~ ~ ~ ~ ~ e;
- - - - - - - - - C-
o 0 :3 0 s: 0 S :3 :=: :z
'" oc 0- "" ~
'" <n '" t""
~ :;;: '" ..
~ ,~ :;l - C"
'~ '" '" 0
'~ ~ 0- J;: 0 w
"" '" ,~ 0 G.> " Co I~ ...
0 00 00 --' ... 'A ~ 0 6 >-l
oc "" 0 0 0- 10 0- S
~ ... 0 e:.
p
'" '" '" '" <n '" '" '" S'
I-' ~ '"
~ c; 0 '-" "" 0' C '" OJ
I-' 1 ~ IJ ,~ '-" '" 0' 0 0 "
Co ;~ ,~ '~ a '-" c 0 "" :a
0 0 0 0 DC 0 ""
...,
S
e:.
is:
~ '" ~ <A '" be '" ~
be '~ be ...
-J 0 '~ co ::s ,~ 0 c ~
-~ oc
I~ 0 ~ 0 co '~ 0' 0 c
0. 0 v, 0 0 0 '~ 0 c
0 'J, ...,
0
[
<A v; be '" be be vo ri ~
"" - ,~ '" '~ 0'
:~ ~ ~ '~ co ~ 0 "" ""
'-" 0 0 0' '0 0 '" ...,
~ ;~ g: v, co = '~ 0 -J S
0' ,~ "" 0' 0 '~
=-
'" '" ~ '" '" '" '" '" '" '"
I~ ,~ - -
'00 ..., ;~ v, C 'x a ;~ c:
'-" ':; "" C"
~ ~ '~ -J - "" 0 ~ 0
'~ ,:; loJ 0 - .., 0 ,oJ
0 0 '-" ~ ~ '~ 0 0. el
'" I~ - a - c
t""
..
C"
'" ~ '" '" '" '" '" '" !;
'~ - - ~ - I-' '" I-'
00 ;X '''' 00 --' v, 0 c; is:
I~ a '" '" ,~ loJ C
'0 ~ I-' '~ a loJ "" 0 '~ ~
'" a "" '-" loJ 'A " ".
~
~
..
""
p
'" be c:
be be be be be ~ ~.g:
DC "" oc -J ~
- 0- '" 0 "" oc X -J '"
"" .c i...J 0 0 00 "
,:; 0: x :i
~ IJ a '" 0 ~
~
~
".
~
...,
~ be v; be V. ~ v; C
be - - ,-IC - be - ~
,~ .c Co 0. '~ 13 ioJ ." v,
..., '~ :; ;3 '~ - ~ '~ ;..
IJ is '~ IJ oc oc ~ 3
v. v, ~ "" ~ -, 0 v, c
- oc "" '~ '~ '-" c:
=.
)> " )> )> I~ )> )> 5" v;
0. :;- 0. 0. 0. 0. 0.
g- or ~ ~ g- o. 0 ~
~ <
~ ~ ~ ~ v; ~ ~ or ~
C ~ ;c
~ ~ - ~
r ~ oc ; oc ci.
9 9 ~ 9
'" ,.;- '" oJ '" v;
t:J '"
< a a n ~ a 0
R C ~ g ~ ~ ~ 5.
:;; "U g- ~ '" ~ 9 ~
~- g- 2 v;
~. " n:
~ ff ~ ~ ~
oc :; ~ 0.
~ " ~
"" 5. .~ ~
z g v: n:
~ :f ~
[ :z
~ 0
'" ;;
~
:;;:
r,
-
'"
r,
"
rE.
r:
7
R
~
g
v
~
n
~
1
,~
I
f
r:
~
2
~
v:
~
.0
...,
o
...
a
0'
....
(j
:;'
;0
=
aQ
",
o
....
Co
",
....
'lIo
-=
......
""
....
J:^
\0
\0
-=
~
~
.;
o
t-
o
-IC
~
:!..
;;-
11
c
~
n
c
5
~
:::
c
a
o
~
:r
.z
c:
OJ
~
tr.
c:
~
~
s.
Page 1 / 1
~A'
CITY Of
ASHLAND
20 E MAIN ST.
ASHLAND, OR 97520
(541) 488-5300
DATE
7/1/2006
PO NUMBER
06650
VENDOR: 000100
L TM INC
P 0 BOX 1145
MEDFORD, OR 97501
SHIP TO: Ashland Public Works
(541) 488-5587
51 WINBURN WAY
ASHLAND, OR 97520
FOB Point:
Terms: Net 10th of Month
Req. Del. Date: 2/16/2006
Speciallnst:
Req. No.:
Dept.: PUBLIC WORKS
Contact: Paula Brown
Confirming? No
Quantity Unit Description Unit Price Ext. Price
THIS IS A REVISED PURCHASE ORDER
BLANKET PURCHASE ORDER
2004 Miscellaneous Concrete Project 123,269.50
Approved by Council February 7,2006
Schedule B Downtown Pedestrian Safety
Schedule C Nevada Street LID 249,050.50
Extra Work 13,017.30
Processed Chanqe Order 08/31/2006 16,990.71
Chanqe Order No. 1
Per attached details on requisition
SUBTOTAL 402 328.01
BILL TO: Account Payable TAX 0.00
20 EAST MAIN ST FREIGHT 0.00
541-552-2028 TOTAL 402,328.01
ASHLAND, OR 97520
Account Number Project Number Amount Account Number Project Number Amount
E 260.08.12.00.70420( 200404.120 229326.99
E 260.08.35.00.70420( 200404.120 124,721.70
E 260.08.41.00.70420( 200404.120 48,279.32
~ ~~ ?/0~
Author.' CI Signature
VENDOR COPY