HomeMy WebLinkAbout2008-107 Findings - Strawberry Lane BEFORE THE CITY COUNCIL FOR THE CITY OF ASHLAND STATE OF OREGON July 15, 2008 IN THE MAlTER OF PLANNING ACTION #2008-00182, A REQUEST FOR OUTLINE PLAN APPROVAL UNDER THE PERFORMANCE STANDARDS OPTIONS CHAPTER (AMC 18.88) FOR A SIX-LOT, FNE-UNIT SUBDMSION FOR THE PROPERTY LOCATED AT 5()() STRAWBERRY LANE. ALSO INCLUDED ARE REQUESTS FOR A PHYSICAL CONSTRAINTS REVIEW PERMIT FOR THE DEVELOPMENT OF HILLSIDE LANDS; A TREE REMOVAL PERMIT TO REMOVE 13 TREES SIX-INCHES IN DIAMETER OR LARGER, INCLUDING ONE SIGNFICIANT TREE, AN 18-INCH OAK.; AND AN EXCEPTION TO STREET STANDARDS TO ALLOW THE APPLICANTS TO END STREET IMPROVEMENTS AT THE DRIVEWAY OF THE PROPOSED LOT FNE RATHER THAN EXTENDING THEM TO THE SOUTHERN BOUNDARY OF THE DEVELOPMENT. APPLICANT: McLellan, Robert & Laura RECITALS: ) ) ) ) ) ) ) FINDINGS, ) CONCLUSIONS ) AND ORDERS ) ) ) ) 1) Tax lot 201 of Map 39 IE 08 AC is located at 5()() Strawberry Lane and is zoned RR-.5-P Rural Residential. 2) The applicants are requesting Outline Plan Approval to allow a six-lot, five-unit subdivision under the Performance Standards Options Chapter for the property located at 500 Strawberry Lane. The application also requests a Physical & Environmental Constraints Review Pennit for Development of Hillside Lands, a Tree Removal Pennit to remove 13 trees six-inches in diameter at breast height (d.b.h.) or larger, and an Exception to Street Standards to allow the applicants to end street improvements at the driveway of Lot 5 rather than extending them to the southern boundary of the project. Site improvements are outlined on the plans on file at the Department of Community Development. 3) The criteria for Outline Plan approval under the Performance Standards Options are described in Chapter 18.88 as follows: a) That the development meets all applicable ordinance requirements of the City of Ashland. b) That adequate key City facilities can be provided including water, sewer, paved access to and through the development, electricity, urban storm drainage, police and fire protection and adequate transportation; and that the development will not cause a City facility to operate beyond capacity. P A #2008-00 182 July 15,2008 Page I c) That the existing and natural features of the land; such as wetlands, floodplain corridors, ponds, large trees, rock outcroppings, etc., have been identified in the plan of the development and significant features have been included in the open space, common areas, and unbuildable areas. d) That the development of the land will not prevent adjacent land from being developed for the uses shown in the Comprehensive Plan. e) That there are adequate provisions for the maintenance of open space and common areas, if required or provided, and that if developments are done in phases that the early phases have the same or higher ratio of amenities as proposed in the entire project. f) That the proposed density meets the base and bonus density standards established under this Chapter. 4) The criteria for a Physical Constraints Review pennit are described in Chapter 18.62.040.1 as follows: 1. Through the application of the development standards of this chapter, the potential impacts to the property and nearby areas have been considered, and adverse impacts have been minimized. 2. That the applicant has considered the potential hazards that the development may create and implemented measures to mitigate the potential hazards caused by the development. 3. That the applicant has taken all reasonable steps to reduce the adverse impact on the environment. Irreversible actions shall be considered more seriously than reversible actions. The Staff Advisor or Planning Commission shall consider the existing development of the surrounding area, and the maximum permitted development permitted by the Land Use Ordinance. 5) The criteria for a Tree Removal Permit are described in Chapter 18.61.080 as follows: A. Hazard Tree: The Staff Advisor shall issue a tree removal permit for a hazard tree if the applicant demonstrates that a tree is a hazard and warrants removal. 1. A hazard tree is a tree that is physically damaged to the degree that it is clear that it is likely to fall and injure persons or property. A hazard tree may also include a tree that is located within public rights of way and is causing damage to existing public or private facilities or services and such facilities or services cannot be relocated or the damage alleviated. The applicant must demonstrate that the condition or location of the tree presents a clear public safety hazard or a foreseeable danger of property damage to an existing structure and such hazard or danger cannot reasonably be alleviated by treatment or pruning. P A #2008-00 182 July 15, 2008 Page 2 2. The City may require the applicant to mitigate for the removal of each hazard tree pursuant to AMC 18.61.084. Such mitigation requirements shall be a condition of approval of the permit. B. Tree that is Not a Hazard: The City shall issue a tree removal permit for a tree that is not a hazard if the applicant demonstrates all of the following: 1. The tree is proposed for removal in order to permit the application to be consistent with other applicable Ashland Land Use Ordinance requirements and standards. (e.g. other applicable Site Design and Use Standards). The Staff Advisor may require the building footprint of the development to be staked to allow for accurate verification of the permit application; and 2. Removal of the tree will not have a significant negative impact on erosion, soil stability, flow of surface waters, protection of adjacent trees, or existing windbreaks; and 3. Removal of the tree will not have a significant negative impact on the tree densities, sizes, canopies, and species diversity within 200 feet of the subject property. The City shall grant an exception to this criterion when alternatives to the tree removal have been considered and no reasonable alternative exists to allow the property to be used as permitted in the zone. Nothing in this section shall require that the residential density be reduced below the permitted density allowed by the zone. In making this determination, the City may consider alternative site plans or placement of structures or alternate landscaping designs that would lessen the impact on trees, so long as the alternatives continue to comply with other provisions of the Ashland Land Use Ordinance. 4. The City shall require the applicant to mitigate for the removal of each tree granted approval pursuant to AMC 18.61.084. Such mitigation requirements shall be.a condition of approval of the permit. 6) The criteria for an Exception to Street Standards are described in 18.88.050.F as follows: A. There is demonstrable difficulty in meeting the specific requirements of this chapter due to a unique or unusual aspect of the site or proposed use of the site. B. The variance will result in equal or superior transportation facilities and connectivity; C. The variance is the minimum necessary to alleviate the difficulty; and D. The variance is consistent with the stated Purpose and Intent of the Performance Standards Options Chapter. P A #2008-00 182 July 15,2008 Page 3 7) The Planning Commission, following proper public notice, held a public hearing on March 11, 2008 at which time testimony was received and exhibits were presented. At the conclusion of the hearing Catherine Dimino, one of the parties who had participated in the hearing, requested that the record be held open for seven days, and the applicants requested an additional seven days to respond to additional written arguments. The Planning Commission continued their deliberation to the April 8, 2008 meeting at which time they approved the application subject to conditions pertaining to the appropriate development of the site. 8) A timely appeal was filed by neighbor Catherine Dimino who had participated in the previous hearing process both orally and in writing. 9) The City Council, following proper public notice, held a public hearing on June 17, 2008 at which time testimony was received and exhibits were presented. The record made before the Planning Commission was received and made a part of the record for this proceeding. At the conclusion of the hearing, appellant Catherine Dimino requested that the record be held open for seven days, and the applicants requested an additional seven days to respond to additional written arguments. The City Council continued their deliberation to the July 15, 2008 meeting at which time they approved the application subject to conditions pertaining to the appropriate development of the site. Now, therefore, the City Council of the City of Ashland finds, concludes and recommends as follows: SECTION 1. EXHIBITS For the purposes of reference to these Findings, the attached index of exhibits, data, and testimony will be used. Staff Exhibits lettered with an "S" Proponent's Exhibits, lettered with a "P" Opponent's Exhibits, lettered with an "0" Hearing Minutes, Notices, Miscellaneous Exhibits lettered with an "M" SECTION 2. CONCLUSORY FINDINGS 2.1 The City Council finds that it has received all information necessary to make a decision based on the record made before the Planning Commission, Council Communications from staff: public hearing testimony and the exhibits received. 2.2 The City Council finds that the proposal to develop a six-lot, five-unit subdivision meets all applicable criteria for Outline Plan approval and an Exception to Street Standards described in P A #2008-00 182 July 15,2008 Page 4 Chapter 18.88; that the proposed Physical Constraints Review permit meets all applicable criteria in Chapter 18.62; and that the proposed removal of 13 trees six-inches in diameter at breast height or greater, including one significant 18-inch oak, meets all applicable criteria for a Tree Removal permit in Chapter 18.61. The City Council further finds that the Performance Standards Options Chapter 18.88 provides for more flexibility than is permissible under conventional zoning codes in order to reduce the impacts of development on the natural environment, and that this flexibility can be applied to look at lot coverage in terms of the subdivision site as a whole in order to protect natural features of the site while providing for the architectural creativity and innovation that the chapter seeks to encourage. 2.3 The City Council finds that the development meets all applicable ordinance requirements of the City of Ashland with the attached conditions of approval. The Site Plan provided delineates the proposed building envelopes, setbacks, and driveway locations. The setbacks on the perimeter of the subdivision and for the front yards are ~uired to meet the standard setback requirements of the Rural Residential zoning district, and the proposal satisfies this requirement. The City Council finds that the applicable Solar Access standards must be protected, and further finds that if the applicants wish to exceed the applicable Solar Access standards, Solar Access Variances will be required to be applied for concurrently with the Final Plan application. The City Council finds that adequate key City facilities can be provided to serve the project including water, sewer, paved access to and through the development, electricity, urban storm drainage, police and fire protection and adequate transportation; and that the development will not cause a City facility to operate beyond capacity. Water, sanitary sewer, storm water, and electric services are available from the Strawberry Lane and Hitt Road rights-of-way and will connect through the individual lot driveways. Storm drain facilities will include private detention systems on the individual lots. Paved access is available from both Strawberry Lane and Hitt Road. The City Council finds that the significant natural features of the property are the existing trees and the steeply-sloped, heavily-wooded slopes on the southern end of the site. The Council further finds that the proposed lot layout, common area and building envelope placements, and driveway locations have been selected in order to protect these natural features. 59 of the 72 trees on the site over six-inches in diameter at breast height are to be preserved, driveways are to be located in response to the site topography to minimize site and slope disturbances, and the applicants also propose to protect the most steeply sloped southern portion of the site in a commonly owned open space tract. The City Council finds that development of the land will not prevent adjacent land from being developed for the uses shown in the Comprehensive Plan. The parcels to the north, east and west are similarly zoned and have recently been subdivided for development as part of the Strawberry Meadows subdivision. The undeveloped properties to the south are zoned WR Woodland Residential, and their further development is already severely constrained by the presence of P A #2008-00182 July 15,2008 Page 5 slopes over 35 percent. The City Council finds that the applicants proposal to deed restrict the proposed open space Lot 6 from further development and to provide Conditions, Covenants and Restrictions (CC&R's) to provide for the necessary maintenance of the open space lot, including the implementation and maintenance of the approved fire prevention and control plan, and petpetual maintenance of required long term erosion control measures, represents adequate provisions for the maintenance of the open space. The City Council finds the density meets the base density standards established under the Performance Standards Options for the Rural Residential (RR-.5-P) zone. The site has a base density of five units (4.62 acres x 1.2 dwelling units per acre = 5.544 units), including the existing single family home already in place on the proposed Lot 4. The City Council finds that no new streets are proposed with the proposed application, and that the proposed lots will take access from the existing Strawberry Lane and Hitt Road rights-of- way. A condition has been added to require that sidewalks and street tree installation be completed along a small portion of the subject property's Strawberry Lane frontage where they are lacking, and an Exception to Street Standards has been requested by the applicants to end street improvements at the relocated gate past the driveway of Lot 5 rather than extending them to the southern boundary of the project. 2.4 The City Council finds that potential impacts and hazards have been considered and that adverse impacts will be minimized through the proposed subdivision's design and the associated mitigation measures recommended by the project geotechnical expert. The applicants have provided a geotechnical study which concludes that the proposed subdivision and associated site grading are considered to be feasible with respect to the stability of the subsurface and slope conditions observed on site. This report includes recommendations for necessary site preparation, retaining, and erosion control, and proposes an inspection schedule to insure that these recommendations are properly implemented during site work. The more steeply sloped areas at the southern end of the site will be preserved as commonly owned open space, and protected from future development, and development of the proposed Lot 5, which includes slopes in excess of 25 percent within its building envelope, will be subject to a separate Physical Constraints Review. The Council finds that the applicants have taken all reasonable steps to reduce the adverse impacts of the development on the environment. 2.5 The City Council finds the request for a Tree Removal Permit to remove 13 trees six- inches or larger in diameter at breast height (d.b.h.), including one significant IS-inch d.b.h. oak tree meets the applicable approval criteria in IS.61.0S0. These trees are located within the proposed building envelopes, and all other trees on site are to be preserved. The Council finds that the removals have been requested in order to permit the application to be consistent with other applicable Ashland Land Use Ordinance requirements and standards in attempting to minimize site disturbance associated with the subdivision, will not have significant negative P A #2008-00 182 July 15,2008 Page 6 impacts to the site or SUlTOundings, and that the removal of the significant oak will be mitigated either on-site or off-site as provided in the ordinance at the time of removal. 2.6 The City COWlcil finds that the proposed Exception to Street Standards to allow the applicants to end street improvements at the relocated gate near the driveway of Lot 5 rather than extending them to the southern bowulary of the project meets the applicable criteria in Chapter 18.88. The installation of the full public street improvements including sidewalks would require that significant site disturbance along more than 300 feet of the Hitt Road right-of-way in a steeply- sloped and heavily- wooded area which the applicants have proposed to protect as one of the site's principal natural features, which the COWlcil finds to represent a demonstrable difficulty given the unique aspects of the site and its proposed use. The future development of properties to the south is constrained by steep slopes, and the Exception requested aids in the preservation and protection of the sloped areas on the project site. An existing gate is in place on Hitt Road to control public access to a city-owned water tank on the property immediately south of the project site, and will be slightly relocated to accommodate the driveway for the proposed Lot 5. The application proposes to ensure adequate fire protection through the installation of fire sprinklers in all homes and the implementation of a fire prevention and control plan, and the applicants will install a new fire hydrant on Hitt Road. The applicants have previously provided easement access and trail improvements across the southern portion of the subject property to provide a pedestrian link between Hitt Road and the nearby Birdsong Lane, and have agreed to sign in favor of any future improvements to Hitt Road. The applicants have also proposed to provide a third off-street parking space for each of the proposed lots to address visitor parking demand, and the COWlcil also finds that additional on-street parking spaces should be identified on Hitt Road at the time of Final Plan submittal in order to ensure adequate fire access in the wildfire interface and to off-set on- street parking that would otherwise have been provided if Hitt Road were extended to the boundary of the proposed subdivision. The COWlcil finds that the proposed Exception is the minimum necessary to alleviate the difficult as paved access is proposed to be provided to the last developable lot in the development, and its driveway placement has been planned to avoid further disturbance of the steeply sloped portions of the site in a manner consistent with the purpose and intent of the chapter. 2.7 The City Council finds that the issue of the applicants' participation in the completed Strawberry Lane Local Improvement District (LID) is not relevant to the approval criteria applicable to the current request. SECTION 3. DECISION 3.1 Based on the record of the Public Hearing on this matter, the City Council concludes that the proposal for Outline Plan approval to develop a six-lot, five-unit subdivision; an Exception to Street Standards; a Physical Constraints Review permit; and removal of 13 trees greater than six-inches in diameter at breast height (d.b.h.) including one significant tree, an 18-inch d.b.h. oak, is supported by evidence contained within the record. P A #2008-00 182 July 15, 2008 Page 7 Therefore, based on our overall conclusions, and upon the proposal being subject to each of the following conditions, we approve Planning Action #2008-00182. Further, if anyone or more of the conditions below are found to be invalid, for any reason whatsoever, then Planning Action #2008-00182 is denied. The following are the conditions and they are attached to the approval: 1) That all proposals of the applicant are conditions of approval unless otherwise modified herein. 2) All conditions of the geotechnical report prepared by Amrhein Associates, Inc. and dated October 12, 2007, including but not limited to the inspection schedule, shall be conditions of approval unless otherwise modified herein. 3) That all proposed lots shall be subject to Solar Access Standard A unless 1) materials are provided with the Final Plan submittal demonstrating that an individua110t has a negative north slope in excess of 15 percent which would render it subject to Solar Access Standard B; or 2) a Solar Access Variance is applied for and approved for the individual lots concurrently with Final Plan approval. Solar setback calculations shall be submitted with each building permit to demonstrate compliance with the applicable standards, and shall include identification of the required solar setbacks with supporting formula calculations and elevation or cross-section drawings clearly labeling the height of the solar producing point(s) from the identified natural grade. 4) That all measures installed for the purposes of long-term erosion control, including but not limited to vegetative cover, rock walls, retaining walls and landscaping shall be maintained in perpetuity on all areas in accordance with 18.62.089.B.7. 5) That prior to Final Plan approval: a) Engineering for the utility plan including but not limited to the water, sewer, storm drainage and electric facilities shall be submitted. The utility plan shall include the location of connections to all public facilities in and adjacent to the development, including the locations of water lines and meter sizes, fire hydrants, sewer mains and services, manholes and clean-outs, storm drainage pipes and catch basins, and locations of all primary and secondary . electric services including line locations, transformers (to scale), cabinets, meters and all other necessary equipment. Transformers and cabinets shall be located in areas least visible from streets, while considering the access needs of the Electric Department. Any required private or public utility easements shall be delineated on the utility plan. b) An Electric Distribution Plan shall be coordinated with the Ashland Electric Department, and shall be included in the utility plan with the Final Plan submittal. c) A drainage plan including necessary final engineering for the private lot stormwater detention systems and any off-site storm drain system improvements shall be provided. d) The engineering for sidewalk improvements to complete sidewalk installation along the subject property's full Strawberry Lane frontage shall be provided with the Final Plan submittal. e) The recommendations from the March 6, 2008 meeting of the Ashland Tree Commission, where consistent with applicable standards, shall be incorporated into the Final Plan submittal's Landscaping, Irrigation, and Tree Protection and Removal Plans. P A #2008-00182 July 15,2008 Page 8 t) A draft copy of the CC&R's and the applicants' proposed Deed Restrictions shall be provided. The CC&R' s shall describe responsibility for the maintenance of all commonly-owned open space including but not limited to the implementation and maintenance of the approved fire prevention and control plan, and perpetual maintenance of required long tenn erosion control measures. The CC&R' s shall note that any deviation from the approved Tree Removal and Protection Plan must receive written approval from the City of Ashland Planning Department. The CC&R's and Deed Restrictions shall be recorded concurrently with the final plat. g) The overall lot coverage for the subdivision as a whole shall be limited to no more than 20 percent. At the time of final plan submittal, the applicants shall provide a breakdown, by square footage, of the allowed lot coverage allocated to each lot and demonstrating that the overall subdivision's lot coverage does not exceed the 20 percent allowed in the RR-.5 zoning district. h) That written verification from the project geotechnical expert shall be provided with the Final Plan submittal indicating that the revised six-lot subdivision configuration and associated improvements are consistent with the original report. i) That a landscape and irrigation plan addressing the re-vegetation of cut and fill slopes required in the geotechnical report shall be provided with the Final Plan submittal. j) That in addition to the third off-street parking space proposed to be provided on each of Lots 1-5 by the applicants, the Final Plat submittal shall identify four on-street parking spaces to be provided on Hitt Road in bays near the relocated gate and between the driveways of Lots 2 and 4. 6) That prior to the issuance of an excavation pennit: a) A preconstruction conference to review the requirements of the Physical Constraints Review Pennit shall be held prior to site work, storage of materials, or the issuance of an excavation pennit. The conference shall include the Ashland Planning Department, Ashland Building Department, the project engineer, project geotechnical experts, landscape professional, arborist, and contractor. The applicants or applicants' representative shall contact the Ashland Planning Department to schedule the preconstruction conference. b) That a Verification Pennit in accordance with 18.61.042.B shall be applied for and approved by the Ashland Planning Division prior to site work, storage of materials and/or the issuance of an excavation or building permit. The Verification Pennit is to inspect the trees to be removed and the installation of tree protection fencing. The tree protection for the trees to be preserved shall be installed according to the approved Tree Protection Plan prior to site work or storage of materials. Tree protection fencing shall be chain link fencing a minimum of six feet tall and installed in accordance with 18.61.2oo.B. c) That the temporary erosion control measures (i.e. fabric sediment fencing, straw bales, crushed rock pads, straw erosion control matting or plastic sheeting) shall be installed and maintained according to the approved plan prior to any site work, storage of materials, or issuance of an excavation permit. These measures shall be inspected and approved by the P A #2008-00 182 July 15, 2008 Page 9 Staff Advisor prior to site work:, storage of materials, or the issuance of an excavation permit. d) The applicants shall provide a performance bond, letter of credit or other financial guarantee in an amount equal to 120 percent of the value of the erosion control measures necessary to stabilize the site. 7) That prior to the signature of the final survey plat: a) All easements for sewer, water, drainage, electric, streets or public pedestrian access shall be indicated on the final survey plat as required by the City of Ashland. b) Street trees, located one per 30 feet of street frontage, shall be installed along the Strawberry Lane street frontage as part of the subdivision infrastructure improvements. Street trees shall be chosen from the Recommended Street Tree List and shall be installed in accordance with the specifications noted in the Recommended Street Tree List. The street trees shall be irrigated. c) Subdivision infrastructure improvements, including but not limited to utilities; driveways, driveway approaches and associated erosion control measures; the extension of curbs, gutters, paving and sidewalk improvements on Hitt Road between the end of the existing improvements and the relocated gate location; and sidewalks and street trees on Strawberry Lane shall be installed according to approved plans prior to the signature of the final survey plat. The Hitt Road improvements beyond the driveway of Lot 5 shall be sufficient to accommodate the placement of parking bays to accommodate two parking spaces and associated vehicular circulation, and shall be shown in the Final Plan submittal. d) That the installation of driveway approaches shall be completed according to city standards under permit from the Public W orks/Engineering Department and any necessary inspections approved. e) The existing sidewalk on Hitt Road shall be extended to the northerly edge of the Lot 5 driveway's approach. t) Electric services shall be installed underground to serve Lots 1-5. At the discretion of the Staff Advisor, a bond may be posted for the full amount of underground service installation (with necessary permits and connection fees paid) as an alternative to installation of service prior to signature of the final survey plat. In either case, the electric service plan shall be reviewed and approved by the Ashland Electric Department and Ashland Engineering Division prior to installation. g) That the sanitary sewer laterals and water services including connection with meters at the street shall be installed for Lots 1-5. h) That Amrhein Associates, Inc. shall inspect the site according to the inspection schedule of the engineering geology report dated October 12, 2007 provided with the application. Prior to signature of the final survey plat, Amrhein Associates, Inc. shall provide a final report indicating that the approved grading, drainage and erosion control measures were installed as per the approved plans, and that all scheduled inspections were conducted by the project geotechnical expert periodically throughout the project. P A #2008-00 182 July 15, 2008 Page 10 i) The landscaping and irrigation for re-vegetation of cut/fill slopes and erosion control shall be installed in accordance with the approved plan prior to signature of the final survey plat. Vegetation shall be installed in such a manner as to be substantially established within one year of installation. j) The applicants shall sign an agreement to participate in the future cost of street improvements for Hitt Road, including but not limited to sidewalks, curbs, gutters, paving, and storm drains. k) That the applicants shall complete the relocation of the gate at the end of the improvements on Hitt Road to the southern extent of the street improvements. The relocation of the gate will be coordinated with the City of Ashland Water Department. 8. That prior to the issuance of a building permit: a) Individual lot coverage calculations including all impervious surfaces shall be submitted with each building permit to demonstrate compliance with the lot coverage allocated to each lot. Building footprints, walkways, driveways including the flag drive for Lot 3, parking areas, and any impervious surfaces shall be counted for the purpose of lot coverage calculations. b) The setback requirements of 18.88.070 shall be met and identified on the building permit submittals including but not limited to the required width between buildings as described in 18.88.070.D. c) Building permit submittals shall clearly demonstrate compliance with the applicants' proposed "Elevation Height Limits" by providing cross-sections or elevation drawings with building heights and elevations above sea level clearly labeled. d) That a Physical and Environmental Constraints Permit for Hillside Development shall be applied for and approved in accordance with 18.62.040 for the development of Lot 5 prior to submission or issuance of a building permit. 9. That prior to the issuance of a certificate of occupancy: a) That the requirements of the Fire Department, including that approved addressing shall be installed prior to combustible construction; that a fire prevention and control plan shall be implemented and maintained; and that fire apparatus access, fire sprinklers as proposed by the applicants, and a fire hydrant shall be installed, shall be addressed. b) All exterior lighting shall be directed on the property and shall not illuminate adjacent proprieties. c) For Lot #3, the applicants shall provide mitigation for the removal of Tree #31 through on-site replanting, off site replanting, or payment in lieu of planting as provided for in AMC 18.61.084. P A #2008-00 182 July 15,2008 Page 11 d) Driveways greater than 50 feet in length, which are considered by definition to be flag drives and thus subject to the flag drive standards, shall be constnlcted according to flag drive requirements that a I2-foot paved width and IS-foot clear width be maintained, and that parking spaces be configured so that vehicles can turn and exit to the street in a forward manner. CITY OF ASHLAND, OREGON 1f7/0Y \. Date P A #2008-00182 July 15,2008 Page 12