HomeMy WebLinkAbout2009-35 Restoring Electric Rate Schedules
RESOLUTION NO. aWe') ~ 3 S
A RESOLUTION RESTORING RATE SCHEDULES FOR ELECTRIC SERVICE
OMITTED FROM RESOLUTION 2009-26
THE CITY OF ASHLAND RESOLVES AS FOLLOWS:
SECTION 1. The electric rate schedules were increased 4% for rates for electric
service provided by the City of Ashland effective with usage on or after November 1,
2009 per the Resolution 2009-26. .
SECTION 2. The installation and maintenance sections of Schedules 48 & 50 were
erroneously omitted from the resolution. Two customers require those schedules for
ongoing service. The attached schedules restore the codes with the rates unchanged.
These schedules and appropriate adjustments to the rates will be incorporated in future
electric rate adjustment resolutions.
SECTION 3. Copies of this resolution shall be maintained in the Office of the City
Recorder and shall be available for public inspection during regular business hours.
SECTION 4. Classification of the fee. The fees specified in Section 1 of this resolution
are classified as not subject to the limits of Section 11 b of Article XI of the Oregon
Constitution (Ballot Measure 5).
SECTION 5. This resolution was PASSED and ADOPTED this /
, 2009, and takes effect upon signing by the Mayor.
day of
\
Barbara Christensen, City Recorder
SIGNED and APPROVED this
I
day of )).c~, 2009.
_~O>-~~___
JSRI'I Ctl'6f1'lBefgj, Mayor
Kate J(}.d:'s~1 eitair
Page 1 of 1
r
City of Ashland, Oregon
LARGE GENERAL SERVICE - USE OVER 2,000 KILOWATTS
SCHEDULE 48
Applicable:
This schedule is applicable to electric service
loads which have registered over 2,000
kilowatts more than once in any consecutive
18-month period. Deliveries at more than
one point, or more than one vOltage and
phase classification, will be separately
metered and billed. Service for intermittent,
partial requirements, or highly fluctuating
loads, or where service is seasonally
disconnected during anyone-year period will
be provided only by special contract for such
service.
Special Conditions:
Customers shall not resell electric service received from
the City under provisions of this schedule to any person.
Monthly billing:
The City will negotiate with a customer a rate
structure and rate levels based upon the
specific circumstances of the customer. At a
minimum, the rates developed for this schedule
will be set at a sufficient level to recover all of
the costs incurred by the City to serve the
customer, including a minimum contribution to
fixed assets.
Metering & Delivery Voltage Adjustments:
The City retains the right to change its line
voltage or classifications thereof at any time,
and after reasonable advance notice to any
customer affected by such change, such
customer then has the option to take service
through transformers to be supplied by City
subject to the VOltage adjustments above.
Contract:
The City may require the customer to sign a
written contract which shall have a term of not
less than one (1) year.
Effective on Usage as of November 1, 2009
C:\DOCU ME-1 Ishipletd\LOCALS-1 \TempIXPGrpWise\Elec-Sch 48 Large Users 11-1-09.xls
11/24/2009
City of Ashland, Oregon
LARGE GENERAL SERVICE - USE OVER 2,000 KILOWATTS
SCHEDULE 48
Installation and Maintenance:
The City may contract for the installation and maitenance
of electric facilities on the customer's premises. The
terms of such service shall be set forth in a contract, the
form and terms of which shall be approved by the City
Council. Monthly charges made by the City shall be
approved by the City Council. Monthly charges made by
the City as reimbursement for ownership, operation and
maintenance costs applicable to facilities installed to
furnish service under rules of the Schedule shall be
determined in accordance with the following:
(1) Operating Charge -- shall be equal to 2/3 of 1 %
per month of the installed cost of facilities paid
for by the customer.
(2) Facilities Charge -- shall be equal to 1 1/2% per
month of the installed cost of the facilites as
determined by the City for facilities installed at
City's expense.
(3) Transformer Capacity Charge -- shall be equal
to 15 (cents) per nameplate kva.
Special Conditions:
Customers shall not resell electric service received from
the City under provisions of this schedule to any person.
City of Ashland, Oregon
GENERAL SERVICE - GOVERNMENTAL LARGE SERVICE
SCHEDULE 50
Applicable:
This schedule is applicable to electric service
loads which have registered from 1,000 to 3,000
kilowatts more than once in any consecutive
18-month period. Deliveries at more than
one point, or more than one voltage and
phase classification, will be separately
metered and billed. Service for intermittent,
partial requirements, or highly fluctuating
loads, or where service is seasonally
disconnected during anyone-year period will
be provided only by special contract.tor such
service.
Monthly Billing:
The Monthly Billing shall be the sum of the
Basic, Demand, Energy, and Reactive Power
Charges, plus appropriate Metering and
Delivery adjustments.
Basic Charge:
2,114.16
Per month
Demand Charge:
For each kilowatt of Billing Demand.
3.9391
Energy Charge: per kWh
4.621
rates (for usage) shown as cents
Minimum Charge:
The monthly minimum charge shall be the basic
charge. A higher minimum charge may be
required by contract.
On-Peak Period Billing Demand:
The on peak period kilowatts shown by or
computed from the readings of City's demand
meter for the 3D-minute period of customer's
greatest use during the month, determined to
the nearest kilowatt.
Reactive Power Charge:
The maximum 3D-minute reactive demand for
the month in kilovolt-amperes in excess of
40% of the measured kilowatt demand for the same
month will be billed, in addition to the above charges, at
rate shown below, per kvar of such excess reactive
demand.
0.9191
The City retains the right to change its line voltage or
classifications thereof at any time and after reasonable
advance notice to any customer affected by such change,
such customer then has the option to take service at the
new line voltage or to accept service through transformers
to be supplied by City subject to the voltage adjustments
above.
CONTRACT:
The City may require the customer to sign a
written contract which shall have a term of not
less than one (1) year.
Special Conditions:
Customers shall not resell electric service
received from the City under provisions of this
schedule to any person.
The City retains the right to change its line voltage or
classifications thereof at any time and after reasonable
advance notice to any customer affected by such change,
such customer then has the option to take service at the
new line voitage or to accept service through transformers
to be supplied by City subject to the voltage adjustments
above.
C:IDOCUME-1IshipletdILOCALS-1ITempIXPGrpWiseIElec-Sch 50 Large govt Users 11-1-09.xls
11/24/2009
City of Ashland, Oregon
GENERAL SERVICE. GOVERNMENTAL LARGE SERVICE
SCHEDULE 50
Page 2
Installation and maintenance:
The City may contract for the installation and maintenance
of electric facilities on the customer's premisis. The
terms of such service shall be set forth in a contract, the
form and terms of which shall be approved by the City
Council. Monthly charges made by the City shall be
approved by the City Council. Monthly charges made by
the City as reimbursement for ownership, operation and
maintenance costs applicable to facilities installed to
furnish service under rules of the Schedule shall be
determined in accordance with the following:
(1) Operating Charge -- shall be equal to 2/3 of 1 %
per month of the installed cost of facilities paid
for by the customer.
(2) Facilities Charge -- shall be equal to 1 1/2% per
month of the installed cost of the facilities as
determined by the City for facilities installed at
City's expense.
(3) Transformer Capacity Charge -- shall be equal
15 (cents) per nameplate kva.