HomeMy WebLinkAbout2010-101 CONT Chg Order #2 - Triad Mechanical \ CITY OF ASHLAND DEPARTMENT OF PUBLIC WORKS CONTRACT CHANGE ORDER NO. 2 PROJECf: LOCATION: Water Treatment Plant Impovements Granite St DATE: June 18,2010 PROJECf NO.: 06,02 CONTRACTOR: Triad Mechanical Inc You are requested to perform the following described work upon receipt of an approved copy of this document or as described by the Engineer: Item No. Descriotion Ouantitv Unit Price Amount Item #1 4 Flocculators installed Lump Sum , $205.132.00 Item #2 Hvpo & Soda Ash uOl!rades Lumo Sum . 23,105.00 Item #3 VFD WiriDl! Size Chanl!e Lumn Sum $6453.00 Item #4 3 ohase Breaker Replacement Lump Sum , $1569,00+ Item #5 Credit for SCADA Inte"rator Lumn Sum ($1837.50) Item #6 Credit for Fence.Gate bv COA Lump Sum , ($2.251.00) Total this Change Order Previous Total Contract Revised Overall Contract Total $ 232,170.50 $980,111,00 $1,212,281.50 The time provided for completion of this contract is increased by no calendar days. This document shall become an amendment to the contract a II provisions of he contract will apply. 6/18/2010 Date Recommended By: Approved By: 6/18/2010 Date Accepted By: Dennis Carroll Contractor Date * see attached Triad quotes ENGINEERING 20 E. Main Street Ashland, Oregon 97520 www.ashland.or.us G:\pub-wrks\eng\06-02 WTP Process Impr\Admin\Triad\C02\2010-0S-20 Change Order.doc Tel: 541-488-5347 Fax: 541.488-6006 TIY: 800-735-2900 ~;., Triad Mechanical, Inc. 1419 NE Lomhard PI. Portland, OR 97211 Phone: 503-289-9000 Fa" 503-289-0316 CHANGE ORDER REQUEST No. 18035Rl . TITLE: Flocculator Installation TO: At1n: Pieter Smeenk City of Ashland 51 Winburn Way Ashland, Oregon 97520 Phone: 541-552-2416 DATE: 11/17/2009 JOB: 37-4698 CONTRACT NO: CONTRACT PROJECT: Ashland WTP Process Improvements Fax: 541-488-6006 RE: To: DESCRIPTION OF PROPOSAL From: Number: Provide and install four (4) each Jim Myers & Son, Inc. vertical paddle wheel flocculation equipment per the attached. Installation is to include access platforms, and all electrical per Valley Electric proposal attached. Item Des<:r1ption .00001 Stoek# Quantity Units 1.000 Unit Price Tax Rate Tax Amount Net Amonnt S2051l32.00 0.00% $0.00 $205,132.00 Unit Cost: Unit Tax: Total: ' $205,132,00 $0.00 $205,132.00 . By: By: Date: f"tS":, Date: 11-{7 -of4 ExpeditiOll* 0 g>l;!;:t . 0 " ,.; ("j..;rojci '" i!~;Z:g , " ., :; .....-. <<i .. .. ~ ""flit"'" ~~ ~: 1$ "' 0 :il :il 8~t'J~ . m C> E a; ~ N si c;g~~ m .. ~ C>~ .., '5 " w .. .. ~ ~ .. .....,.69W J!l ~ '" '" '" '" ~~ N N N N e ,,; ,,; ,,; ,,; ,,; -.., .. '5 " w ~ 'E , ~ ~ ~ ~ ~ C N .. ~ ~ 0 0 ., N i! ;!; , '" .. '5 " w ~~~~ 00 R:l;~ m~~ I;; ~'" " ~i;t8 ~~ ~~~ "'~.; :!i .8 ~ ...- ...... :; ~ ~ ~ ";N."":~ :2-ci '!l ....,...... ..~ w.....,........ 44.... tit... . 10101(11) ~'" ~~:!l~~ n i! ~O(')O '"'0 ..,tri..ri:D ;!~ g;!t::;!~ " ................,. ~:: 0 " . ~ e NC\l........ ~~ ~~....OO , C":l.C":l.NN 0 ;!;;!; .c C . :E ~ Xu. u. 0 u..Q::u..tt:: u.o: u..mLl..CO lt~ ~~~M:~ Q....JQ....J :5 .. m :5 .'l 0 ., ... 0- .. 0 ::I .; :;;~~~ 'C 0 ~ ~ 0 - .. o.....m... " ..; ...:fIJ-.......: .. ~... ~ ~ ~ ~ .. 06l1t69fo1t 1! ~ U , ~ ~~ 'Ii r! .. ~ .. '" ~ N J'J .. 6 c 0: 0 0 E u. [ l!! ., ~ .. E . ~ 0: a . W C .; j ~ .. 0 ;; e U ., . 0 '" .c c c 'E", 0 10 . 0 g ~ i ~ E c BE . 0 ... Ii: ! (/)W5 ~ . 0 ~ s ..e: ~ 'E ::! ~~ 'ii ffi~E I .E ;=ffis . ~P2 t- ~ ~~ ,E ,S 5 "' . ~~~ e l; 5:e...Es 0 n 3~1 .. c ~ lU l'I:I c: C () :>"'t- 0 ~'S S 2 is ~~ ~ n Ii ~ %'0" a '5 ~l! 'r" ;:; <0 '" C gg h.. ~ h B~88 i! " o .i?~ . _.5 ~ ~ :e ~() ti "u. u:w5: u: "'t- ~S:moc ~. _ ~. -4 A~ TRIAD 1419 NE Lombard PI. Portland, OR 97211 Ph: 503,289,9000 Fax:503-289-Q316 CHANGE REQUEST No. 18040 Triad Mechanical, Inc. DATE: 5/15/2009 TO: Attn: Pieter Smeenk City of Ashland 51 Winburn Way Ashland, Oregon 97520 Phone: 541-552-2416 Fax: 541-488-6006 CONTRACf NO: 4698SUB06 JOB: 37,4698 PROJECT: Ashland WfP Process Improvements TITLE: Soda Ash System Modifications DESCRIPTION OF PROPOSAL Provide labor, material, equipment and supervision to update the soda ash sys1em per discussions ou,sit., and iu accordance with the attached quotations. Total: $23,105.00 Date: Carroll .:,--/~- -09 Pieter Smeenk By: By: Date: 5-1 ~- WI D Pro MDllIiementSystems,. lnc 8~8 le:&:::g; " U~ 8~8~ , t'I!.~"I~ VI ~""'ori" ..- - _ N """ .,.,M.. 1/1.1/1. C!~ ~...: 1; ~ go........ -~.. . ;:;:"'gj E ~ - - '5 0' W .. .. .. ..~~.. ~ ~ ~ ~ ~~ N N '" .; .; .; -.. ~' '5 0' W '" c , , ~ ~ ~ C ~ 0 0 0 l! , .., ~ '5 IiI 0 ~ OOf')OG) , N 0 ...on. l;i ...: R:~g II ~ j ~ m_ :: .. t$....M~ M~"~ ~ ~ G)U)or)lOlO ."." " ....MOMm 00 L it g~~~~ ci"": 0 N_ " . -' e ~ 00....00 , 0 j; :i! ~ :l:~ ~ U ~ ~ ~~::;~~ 0. 0.0.0. , 00 OlOMID 00 o~~m ;; cilt'i .ncri.nrj 1: ON >1" " ! N_ O; .... .........,... .. ."." 00 , ~:: lii 0; .. 6 c . I :ll ~ ,g .Ii g 2- ~ ~ I ~ ri B ! N ! E .. .. IE H 0 ~ '8 H ~ i E ~L .,. 0; ~ E l!! ~1l. i ! hl~~ ..!!: ~H~i I- u. ~ l:l ~ ~: n~ D~ u ::><1- m f~! ~ Zc' i'" ~ '8.lill hKJE al2:'! . liS ES2~~~ ~n ~ 0 Qo~ ti :i! Ul I- ) Industrial Systems LLC 4110 NE 122"" Ave, Suite #130 Portland, OR 97230 Phone: (503) 601-0076 Fax: (503) 262-0371 e-mail: is(lj)industrialsvstemsllc.com OR CCB #134897 WA #INDUSSL004K4 04/15/2009 Dennis Carroll Triad 1419 NE Lombard PI. Portland, OR 97211 Subject Ashland Soda Ash System Update Dear Mr. Carroll Industrial Systems, LLC is pleased to provide you with the following proposal for Control system Integration services. We have Included our scope of work, cost proposal, rate schedule and our standard terms and condijions for your use. As always, we look forward to working with you on this project. ScoDe of Work: Replace existing control of Soda Ash system with I/O wired into the Chemical Building PLC. The existing equipment will be modified to make up a batch to be transferred to the new Use Tank. Equipment We will supply two (2) new Hydroranger 200 ultrasonic level transmitter units to be used in the existing batch tank and Use tank. These will include XPS-15 sensor heads. Time: This quote contains the following breakdown of required time. 16 hrs Design, ACAD and management of project 16 hrs HMI and PLC programmin9 40 hrs (1 week) of time for Travel, finish install, test and siartup of the Soda Ash System. This also allows time for whatever else may come up. Actual cost of Motel, mileage and meals + 15%. Total cost ..............' '............ ........."...,..,..... '.. ...... ...........' ,.. '.........,...... ...... $12,500.00 AssumDtions: 1) Valley Electric will mount and run required conduits to new equipment and modify existing equipment as necessary. (Wire In additional relays etc.) 2) Triad will mount new level sensors and provide mounting materials. 3) City will provide direction on how the new system will work. Terms shall be as stated in the attached terms and conditions. For the purpose of time and material work and any hourly work agreed to beyond this scope, the enclosed billing rates shall be considered as our standard rates, Our standard rates shall be subject to annual revision. To initiate this letter agreement, please sign below and retum a copy to our office. Please feel free to call with any questions that you might have. Again, we look forward to working with you on this project. Larry Helenius Date Triad Date Enclosures: Rate Schedule and Standard Terms and Conditions . . Mike Hamitton \t ALLEY ELECTRICAL CONTRACTORS, INC. P,O, Box 1555 Medford. OR 97501 Tel # (541) 773-1405 Fax #(541) 770-2819 eCB 1/55415 Change Order To: Triad Mechanical, Inc 1419 NE Lombard Portland, Oregon 97211 Attn: Dennis Carroll Project Name Ashland Water Treatment Plant Process Improvement CONSTRUCTION CHANGE ORDER NUMBER #-6 GENERAL SCOPE OF WORK DESCRIPTION: Soda Ash System Modification Provide & Install: Provide & Install: Provide & Install: Provide & Install: Provide & Install: Provide & Install: Conduit and wire for 120 volt circun to display panel 18,2 twisted shielded pair cable from display panel to PLC Rework existing 1" conduit at both tanks extend 1" condun to west wall and mount display panels reconnect (3) Soda Ash pumps with permanent electrical connection plate and pipe to mount sensor in Soda Ash Tank Pursuant to the Construction Agreement between Contractor and Owner dated 3/1412008 the Contractor agrees to.perform the following changes THE AMOUNT OF THE CONTRACT WILL BE INCREASED (DECREASED) IN THE SUM OF: $ $ 5,343.00 OAbove changes to resun in increase of time to complete the project of 5 days. (To be added to the completion date in the Construction Agreement) In the event the project shall require work in excess of the quantities above set out, and If this Is a lump sum proposal, extra charges shall be made for such additional work al the rates then being regularly charged by the undersigned for such Ilems, peyment shall be due on or before 10 days aller billing, The parly prevailing in any litigation arising out of the work, or this agreement, shan be entitled 10 recover such as the court may adjudge reasonable as attorney's fees In litigation Lete charges of 1 1/2 % per month (18% annual percentage rate) will be charged on past due accounts, Past due accounts are invoices not paid within 30 days of blillng. , Price is subject to a mutually acceptable contract. Special Conditions: 1 Labor and material will be provided during normal working hours 2 Siding, sheetrock, carpentry repair, painting or touch up work are customers responsibility 3 All sensors and display panels to be provided by other 4 All programming to be done by other, 5 0 This change is made for acceptance within 30 days only of the date hereof Dated this day Thursday, April 23, 2009 Valley Electrical Contractors, Inc. ACCEPTANCE The foregoin9 proposal is accepted this day of 20 By: .JlXar~ :Dank/s Marly Daniels Project manager / Estimator Sign authorizing work and prico, return to Valley Electrical Contractors, Inc . -.. .r Triad Mechanical, Inc. 1419 NE Lombard PI. Portland, OR 97211 Phone: 503-289-9000 Fax: 503-289-0316 CHANGE ORDER REQUEST No. 18042 TITLE: Panel PP-2 Breaker Replacement TO: Attn: Pieter Smeenk City of Ashland 51 Winburn Way Ashland, Oregon 97520 Phone: 541,552-2416 DATE: 4/6/2010 JOB: 374698 CONTRACT NO: CONTRACT PROJECT: Ashland WTP Process Improvements Fax: 541488-6006 RE: To: DESCRIPTION OF PROPOSAL Existing breaker designaled for use with the flocculator upgrade is a 2 pull breaker; a 3 pull is required. Provide labor and material necessary to replace the breaker per attached Valley Electric quotation. From: Number: Item Deseriptinn 00001 Stoek# Quantity Unit. 1.000 Unit Price Tax Rate Tax Amount Net Amount $l,569.00 0.00% $0.00 $1,569.00 Unit Cost: Unit Tax: Total: $1,569,00 $0,00 $1,569.00 A:~OVtfJ~fJ Pieter Smeenk Date: 1- 5- J 0 By: Date:,! -.:r _10 Expeditionf:l . '" :5 :5iil1lill '" r:i ~Nci.,; ~,,~ , "'. (")....... '<f. ., ~ ....lo4...... ".". 00 6'"": C l '3 0- W ~ ~ ...,..... S ., ., ".". " " E ,,; ,,; 00 -. 0- '3 0- W " C , .c " " C 0 0 . l! , .. 0- '3 0- W ;g ll)Cl>_1Il (l) It) ",co .8 " r::~--';i ~ ,j ww..""".. ..w...... ~ ~~:g~:g ~~ .8 gr!J::~~ c:i"': ,,- ,j e 00..-00 , . " C c ::Ii '" e :I:~ ~ <J ~lt~:t~ 'ii 1:: tl .. ....ilItw " ".". C 00 , Lri~ j ., S 0 ~ ~ ;; 0- E ,,; .5 . . ~ g- ill, . . '~ ;;; ~ u il c .. ~ ill "- " . ~ ., E w '" ~ '~ "i c ~ ~ e ~ Q; ~ J! -If ~ E I c jj ..- O:~g e - c c:: c:: w\ii " i ~llllll Ii; ~{i~ e " ~ e e J!J'l 0 0. .. HHC '-' ::>"'.... ~ N"- , 0. ~ ~ Z'016 1\- .Ii e~ "- ~ .g-g~ ~ r:D~1ii c =c "..H ga:: ii _ c ~ ;:;:iii :la' g ,,"- "'" /. Mike Hamilton 1f ALLEY ELECTRICAL CONTRACTORS, INC. P,O, Box 1555 Medford, OR 97501 Tel #(541) 773-1405 Fax#(541) 770-2819 CCB #55415 Change Order To: Triad Mechanical, Inc 1419 NE Lombard Portland, Oregon 97211 Atln: Dennis Carrol Project Name Ashland Water Treatment Plant Process Improvement CONSTRUCTION CHANGE ORDER NUMBER #-9 GENERAL SCOPE OF WORK DESCRIPTION: Change out breaker in panel PP-2 Provide & Install: Provide & Install: Provide & Install: Provide & Install: Provide & Install: (1) 3 phase 70 amp 480 volt Type EDH breaker (1) set of mounting hardware for breaker Labor to install breaker hot Pursuant to the Construction Agreement between Contractor and Owner dated the Contractor agrees to perform the following changes 3/1412008 THE AMOUNT OF THE CONTRACT WILL BE INCREASED (DECREASED) IN THE SUM OF: $ $ 1,322.00 'Above changes to resu~ in increase of time to complete the project of 1 days, (To be added to the completion date in the Construction Agreement) In the event the project shall require work in excess of the quantities above set out, and if this is a lump sum proposal. extra charges shall be made for such additional work at the rates then being regularly charged by the undersigned for such items, Payment shall be due on or before 10 days after billing, The party prevailing in any litigation arising out of the work, or this agreement, shall be entitled to recover such as the court may adjudge reasonable as attorney's fees in litigation Late charges of 1 1/2 % per month (18% annual percentage rate) will be charged on past due accounts, Past due accounts are invoices not paid within 30 days of billing, Price is subject to a mutually acceptable contract Special Conditions: 1 2 3 4 5 Labor and material will be provided during normel working hours Siding,sheetrock, carpentry repair, painting or touch up work are customers responsibility o o o This change is made for acceptance within 30 days only of the date hereof Dated this day Thursday, April 01, 2010 Valley Electrical Contractors, Inc. By: .:;U'llTty :J5aniefs Marty Daniels Project manager / Estimator ACCEPTANCE The foregoing proposai is accepted this _day of 20 Sign authorizing work and price, rotum to Valley Electrical Contractors. Ine Change order cost sheet \ Ashland Water Treatment Plant Process Improvement . '\. Change Order I NOI #-9 Thursday, Anril 01, 2010 WIlii IIecItIaI CCB _,. COIItTR4C1'QRS lNC ~ Wire Take off Pace Pioe Take off oaoe Steel Fittino Take off Paoe PVC Fittinos Paoe Elbows take off naoe Boxes take off nane Steel Flex Take off Paoe Seal Tinht Flex Take off nane Hubs and Ninnle Take Off page Lock Nuts and bushinn take off page Strut and Fasteners Take off nage Make Un and LUQS take off page Devices and covers take off paQe Disconnects and meters take off paoe Mise material take off paoe Total Material Cost Reiltal! Scissor lift Jack Hammer iJiW1f!iCOiIt@!,li 0,00 0,00 0.00 0,00 0,00 0,00 0,00 0,00 0.00 0.00 0,00 0,00 0.00 0,00 731,00 731,00 2 -1/2" to 4" Threader 1/2" to 2" Threader 2-1/2" to 4" Bender 112" to 2" Bender Wire TUQger Welder Large Concrete Drill Small Concrete Drill Band Saw Hydraulic crimoer Hvdraulic wire cutter Hvdraulic KO nuller High voltage term kit Hol stick Truck Total tool cost $45,00 $0,00 $25.00 $0,00 $45.00 $0,00 $25,00 $0,00 $25,00 $0,00 $25.00 $0,00 $25.00 $0,00 $15,00 $0.00 $15,00 $0,00 $25,00 $0,00 $25,00 $0,00 $25,00 $0,00 $25,00 $25.00 $15,00 $0.00 $20,00 $0,00 ~~$2500 0.00 MeQoer $15.00 $0,00 0,00 Pena scanner $25,00 $0,00 0.00 Fiber termination kit $50,00 $0,00 ~inment rental cost =~o Circuit 10QQer $50,00 $0,00 ~ ~~ Fiber tester $25,00 $0,00 Fire Alarm 0,00 Under Qround wire 10 $25,00 $0,00 Low Voltaae 0,00 600amp clamn on $25,00 $0.00 Excavation 0,00 Wire scope $15.00 $0,00 Total Subcontractor Cost 0,00 Total Meter cost $0,00 ~';:'ii)';':i.~t~X"E~~Eqii;pmenf'ifXWP;;;;'i?ii~ Electrical Permit Scissor Lift' $8.00 $0,00 Others SUB Fork Lift $15.00 $0,00 Travel Boom Truck $125,00 $0,00 Total Misc cost Total eouinment cost $0,00 TbtaJ(ti/iQfri9i;$I3Cti6if'''''.'., ."NCi,!:i61.1iSN 2oo8:RA ',F LabotC6St;;/.',/ ~ Wire Take off Paoe 0 p]De Take off oaoe 0 $55,97 General Forman 0,50 $27,99 Steel Fittina Tak.e off Paoe 0 $52,50 Forman 0,95 $49,88 PVC Fittinas Paae 0 549.74 Joumevman 4.75 $236,27 , Elbows take off paae' 0 $44.08 Apprentice 0,00 $0,00 Boxes take off nane 0 $54,97 Office 0,12 $6,53 Steel Flex Take off Pane 0 $25,28 Labor 0,30 $7,51 Seal Tinht Flex Take off nane 0 Total Labor Cost $328.16 Hubs and Ninnle Take Off nane 0 Total Material Cast $731,00 Lock Nuts anCl bushino take off oaoe 0 Consumables 3,00% $31,77 Strut and Fasteners Take off naoe 0 Total Tools $25,00 Make UP and Luas take off paae 0 Total Meters $0,00 Devices and covers take off page 0 Total eauipment $0,00 Disconnects and meters take off page 0 Total Rental Cost $0,00 Misc material take off oaoe 4 Total Subcontractor $0,00 Production Labor 4 Total Misc $0,00 Lost nroduction labor adder 1 Total Material and eauIPment Cost $787,77 T otallabor wrth lost oroduction 5 Prolrt on Labor Profit on material I I $328,16 22,00% $787.77 17.00% Total Change order cost wijh nrofit Proposal Cost I $72,19 $133.92 $1,322.05 1,322,00 $ ~, - " Triad Mechanical, Inc. 1419 NE Lombard PI. Portland, OR 97211 Phone: 503-289-9000 Fax: 503-289-0316 CHANGE ORDER REQUEST No. 18043 TO: Attn: Pieter Smeenk City of Ashland 51 Winburn Way Ashland, OREGON 97520 Phone: 541,552-2413 Fax: 541-488-6006 DATE: 5/26/2010 JOB: 37-4698 . CONTRACT NO: CONTRACT TITLE: VFD Wire & Conduit Changes PROJECT: Ashland WTP Process Improvements RE: To: DESCRIPTION OF PROPOSAL From: Number: Provide labor and material to change wire and conduit as required for the flocculator VFD wiring. Item Description 00001 Siock# Quantity V nits 1.000 Vnit Price Tax Rate Tax Amount Nei Amount $6,453.00 0.00%1 SO.OO $6,453.00 Unit Cost: Unit Tax: Total: $6,453,00 $0,00 $6,453.00 APPROVAL: ~ By: f?~ JI - r f1o'}; By: 1>' -:J..r" -10 Date: Date: ExpeditioniW , "- 8 88~~ " .,; ocir-.:r--: 0 01'-(010 . ... ...'" '" '" on ",' <i .. ~............. '11''11' 00 o~ t! . g, ;; .if .. .. .......wUJ S '" '" '11''11' N N e .; .; 00 -'" .. ;; " w .. c . " " c 0 0 0 e . " .. ;; " w '" 1t)<3>_1t) '" Q)Il)MCO g ~ ~~...:;t j ....~"'...... ........... ~ COIt)U')\01O ~~ ....l")CDMCD ci.,.:t...:'<ill'i c:::i'll: g I()I'-I'-I'-'" N~ j E 00....00 . g c l'l " e Xu. u. U ~1.I..~Li..W o..o..CL.CL. ~ ~ :l! ..........." .. ";/.<f!. c 00 . ~: ~ J!l 5 c . E . > '" e '" 0. N .s ~ '" ~ '" ... . c <i ~ . '~ '," .. 1l c ~ " " "- " U '" E u '" <! ~ E ~ .'i '3 ... "- ~ " ,1! ~ . ~ E c i ..!: m 0 "'''g u 1:ijcg >- w~ 8. .. g~.g";::l '" ~ ~ m e ~~~!!S 0 0. E . ~.[CC " ::>">- . ~~ > .. 0. ]i ~ %'5" '" >- o e! E E ~"OS i'O al~~ C 00 .!!! E<!o.U H~ ~ ..!:; 1ij '0" 0 0, ;: It ;:;:0; .". > >- ." . CCB #55415 \t ALLEY ELECTRICAL CONTRACTORS, INC. P,O, Box 1555 Medford. OR 97501 Tel # (541) 773-1405 Fax#(541) 770-2819 Mike Hamilton Change Order To: Triad Mechanical, Inc 1419NE Lombard Portland, Oregon 97211 Attn: Dennis Carrol Project Name Ashland Water Treatment Plant Process Improvement CONSTRUCTION CHANGE ORDER NUMBER #,10 GENERAL SCOPE OF WORK DESCRIPTION: Change wire to motor and rework conduit for VFD Provide & Install: Provide & Install: Provide & Install: Provide & Install: Provide & Install: (2000') XHHW Stranded copper wire (4) wire to each drive motor ($ 1,900,00) Conduit, wire, gutter and fittings to instaUlarger VFDs on waU ($ 3,800,00) Pursuant to the Construction Agreement between Contractor and Owner dated 3/14/2008 the Contractor agrees to perform the following changes THE AMOUNT OF THE CONTRACT WILL BE INCREASED (DECREASED) IN THE SUM OF: $ $ 5,700.00 "Above changes to result in increase of time to complete the project of 0 days. (To be added to the completion date in the Construction Agreement) In the event the project shall require work in excess of the quantities above set out, and if this is a lump sum proposal, extra charges shall be made for such additional work at the rates then being regularly charged by the undersigned for such items. ' Payment shall be due on or before 10 days after billing, The party prevailing In any litigation arising out of the work, or this agreement, shall be entitled to recover such as the court may adjudge reasonable as attorney's fees in litigation Late charges of 1 112 % per month (18% annual percentage rate) will be charged on past due accounts. Past due accounts are invoices not paid within 30 days of billing, Price is subject to a mutually acceptable contract. Special Conditions: 1 2 3 4 5 Labor and material will be provided during normal working hours Siding,sheetrock, carpentry repair, painting or touch up work are customers responsibility o o o This change is made for ecceptance within 30 days only of the date hereof Dated this day Tuesday, May 25, 2010 Valley Electrical Contractors, Inc. By: :Jl'arty ;[janie/of Marty Daniels Project manager / Estimator ACCEPTANCE The foregoin9 proposal is accepted this day of 20 Sign authorizing work and price, return to Valley Electrical Contractors, Inc Apr 13 2010 9:58AM . HP LASER JET FAX p.l Bill To nvole City of Ashland WTP PI ET E R Dale Invoice # 20 E Main Street Ashland. OR 97520 4/612010 10.03.01'2 P.C.No. Terms Project Net 20 10.03.0] _201O_T & M Description Qty Rate ' Amount , service trip 3/30 through 411 29 100,00 2,900.00 mileage 600 ". .. . ._~..~ '._~ .n .. 0.52 ... .. ,. ....312.00' Meals il ' "t'..",'....' . .1.,.q9' '4:~ 7:69 ~~~ ... 10.-.;", '...'.... ,~...,," _ ~; Meals iJ 8.0 8,03 Mell1~' .n.", ...._. ..... '_."__ __~_"____U.~___._.._..'__" ~--_.,._. ...-.-........-1' ,----.---... '..., '6.99 ""'-'._"-""'.'~ , ,. '6.99" Meals II .~5'~'l 10.46 . loA6 Meals (I 6.$9 6,59 Mear~'-'"'''' .....=~'c:'O' co' .C.'''' .. "'--"-' '. ..,-_....., ...._._..~T '1--"" -"'-' ....,. '1E7 ......_" . .........-. '''1,81' Meals '3 Ie;;. PC>\~J , I 3.95 3.95 Lodg,ing - ,..... I 269.67 269.67 fun ~ 11fS72.. I ,... 1",,~u..Jt rio.. \ ~)I!>To.."""'.s ~:i:'(:'- .. o Approved for Payment .- CJ Do Not Pay Signature Account .. Date PLEASE RETURN TO PAYABLES . , , . '" '!Total '......;; " , ::",,:',i $3.533',2.~ .~I , .' : , .. .' - ;-\1"':'. , ~.:~ . . '.- Oe,fb WOlI", . i PaymentsICrl.cU!:s $0:0I! .','. ~~ " ,. Balance Due , $3.533,25 c;r . Industria I Systems LLC Ot1M ) 51:% 7?1~ 1-.., ,,I 4110 NE 122nd. Ave., Suite 130 Portland, OR 97230 Phone (503) 601-0076 Fax (503) 262-{)371 Email: is@industrialsystemsllc.com OR eCB #134897 WA #INDUS.SL004K4 Al"TN, I . e .. .... . t~D-fl ne ~j -- RlMln/^j (JoW -- ivJ f-zo eat~ , ;.. . . Ma~ 12 2010 IO:IOAM HP LASERJET FAN Frot): 05/0512010 09:23 p.l #341 P _001/001 .....TOlI .... _110 l1li TlIG ...... (541) 664-2281 ~'1l"'l.{P' ..t;, 01'-1 Qua~ence CO., Inc. _ CCB 08936 tJ;t1:;-: '1n~ 114 W. Pine Street P.O. Box 3985 Central Point OR 97502 Fax (541) 664-2949 (8001451-8883 tl , ~ ~ - ----- -- ------------- Cfl'Y OF ASHLAND ATTN.' GREG HUNTER 90 N. MOUNTAIN ST. ASHLAND, OR 97520 A'iN, P,' e. -r12.-r S r--, ".... n \-<.. DATE INVOICE NO. 3/1212010 2] 126 TERMS Duo 01) Receipt OESCRIPl'ION AMOUNT 1400 GRANITE STREET, ASHLAND SECURJTY FENCE SET I GATE POST, TIE IN 6' HIGH CHAIN LINK FENCING WITH 3 STRANDS OF BARB WIRE ON TOP, INSTALLAIION OF 35' OF 6' HIGH CHAIN LiNK FENCING WTTH 3 STRANDS OF BARBED WIRE ON TOP AND 2 EXT.RA LONG TERMINAL POSTS, INSTALLATION OF 4' OF 5' HiGH CHAIN LiNK FENCING WiTH 3 STRANDS OF BARBED WiRE ON TOP. INSTAlLATION OF] WALK GATEATSTAIRS, 2,251.00 NOTE: RE-USE OF AS MUCH EXISTING MATERiAL AS POSSIBLE AND WELD AS NEEDED. EJ..TEND REMOVAL OF 70' OF 6' HIGH CHAIN UN/( FABRiC AND 3 STRANDS OF BARBED, EXTEND 2 TERMINAL POSTS AND 6 LiNE POSTS. INSTALLATION OF 70' OF 8' HIGH CHAIN LINK FENCING WITH 3 STRANDS OF BARBED WIRE ON TOP, [ig Appr NOTE: RE,USE 01'- FX/fiTING BARB A1l.MS AND TOP RAIL 0 Do N J ,575_00 &,-10 iJtb .1(.\ ,00 lOlf'ZCC (7S~) &70. OC(J .$5.(0.70'\2..(:Q (ZS~) THANK YOU, WE APPRECIATE YOUR BUSINESS Signature ". Accoun Date c' o URN TO PAYABLES FINANCE CHARGE: I 1/2% Per Month (1ll'A, Annual Rate) on pasl due accounts. We accept Visa, MasterCard and Discover. Payments/Credits $0.00 $3,826,00 Balance Due "Fencing is our Field" ~0M)I'J .hrw. W~'yr;IJUrJt~ ~~, CITY RECORDER CITY OF ASHLAND 20 E MAIN ST, ASHLAND, OR 97520 (541) 488-5300 Page 1 / 2 I' 'DA' T.E ',..' "I - "'-' , . .......... 7/1/2009 ;'1: ,P,O'iJUMBERU,,-, 08062 VENDOR: 012974 TRIAD MECHANICAL INC 1419 NE LOMBARD PLACE PORTLAND, OR 97211 SHIP TO: Ashland Public Works (541) 488-5587 51 WINBURN WAY ASHLAND, OR 97520 FOB Point: Terms: Net Req. Del. Date: Speciallnst: Req. No.: Dept.: Contact: Jim Olson Confirming? No :;: ;.~:Quanijt\f:;; .'~ tjjUni(:' I'~:,:\>:- ." "'.',, ";.,.. [)es'criDtlor( ';: .. ":': ,. "-~'-l,-.;.''1,>~'W:~~ ;. ';~;Unin:~rice::f-::.~; ;;~~tT~~ THIS IS A REVISED PURCHASE ORDER Construction of water treatment process 0 969,322,00 improvements at the Water Treatment Plant to achieve higher functions. Base bid $742,711,00 Additive A - Install Chemical Feed Line - $59,320,00 Additive B - Install overflow weir- $65,379.00 Additive C - Install soda ash feed - $101,912,00 \ , Bid Contract start date: 12/15/2007 Contract completion date: 12/31/2009 Insurance required/On file Project No, 200602,120 Approved by City Council 11/20/2007 per Dawn Lamb's memo dated 12/15/2007, Processed Change Order 06/01/2009 10.789,00 FY 2008 Field Engineering Cuts ($8,075.00) Water Pump/Foot Valve $9,626.00 Sodium Hypo Modifications $7,438,00 Deferred Mag Meter Install $1,800.00 Processed Change Order 06/22/2010 232,170,50 Change Order NO.2 SUBTOTAL BILL TO: TAX FREIGHT , TOTAL !:,J,;:,o.tA"CCOlJrit1Nur;fber.&.~1f.s~ ~:'&i~{p,;:ojeCt:;iiumt)e;t:;;.r~B i\}'~; :JAmoi..fnfi;!~~ ..1r ;;. ,A'ccouniiNu'm"tlef.0 ~-:. :'. :":: ,::~-rc)jec.fiftlnn)e"'r,~~~ ~~mo'Unt_ E 670,08.19,00,70420 E 200602,120 791 183,86 E 670.08,38,00,70420 E 200602,120 421 097,64 I M "L.. . & 0/ z.y 1"0 AU~ Signature VENDOR COPY Page 2 /2 ,,~, CITY OF ASHLAND 20 E MAIN ST, ASHLAND, OR 97520 (541) 488-5300 ;,')! :,_'DATE!A~.',~;'.;; :""., p.o"Nurliu3ERnLig 7/1/2009 08062 VENDOR: 012974 TRIAD MECHANICAL INC 1419 NE LOMBARD PLACE PORTLAND, OR 97211 ' SHIP TO: Ashland Public Works (541) 488-5587 , 51 WINBURN WAY ASHLAND, OR 97520 FOB Point: Terms: Net Req. Del. Date: Speciallnst: Req. No,: Dept.: Contact: Jim Olson Confirming? No ?}';:QuarltiiV;C;: ~~r. Unit::l i r.;-,; ',,';,UY: ,> -, :1,: ,'. :,r:;:./' _ :;:' ':; ~h>;in'(De~scriDtion" ,_' . ;:'~ : f "j .. .. ;., ':( ';'" ;': : Unit :>prlce'; ;~F;:' ~i:::;}:i'!'Ei1~'p.riCe~j rj~ Floculattors, Soda Ash, Fencing and Electrical Equipment - Per attached change orders SUBTOTAL 1 212 281,50 BILL TO: Account Payable TAX 0,00 20 EAST MAIN ST FREIGHT 0.00 541-552-2028 TOTAL 1,212,281,50 ASHLAND, OR 97520 k(,~tA"cC()unFNljmB'e~b;:il.h~~tij f:;1)1TProject:-N-umbe'r;f~::; :",: :;r::~~;AmounttL:;r\::,,: ~,:,;j;Ac''C_o_unt~~-um6eK: ,~;':; :"t;,;~t#rojEtcf;Number~Ufi~~,~ ~~- ~ ~ ~:t?;; signtSff~ VENDOR COPY CITY OF ASHLAND, I FORM #11 I 1'--'..;...:'.....,.. ", "- " . -.... .:" -,',J' '''.', Ga0DSAND SERVICES ,::.: .;> --. .,' - ,- ,-," ;<- " ",- - - CHANGE ORDER/CONTRACT AMENDMENT APPROVAL REQUEST FORM Description of Change Order / Contract Amendment to original contract Contractor: <::::;:1-'7 /' A ~ ?/ Y <' tit d!. c.../,v( lA'. ~_.( a-'11_Lt! ~ Purchase Oider Number: 0 g 0 66 :?-- Description: AI';; ~ L/t --h ~ &--r cLef ~ ./ ~r attached contract amendment ./ C;oritr~C;;t.~";endlTle~t for GOODS 8. SERVI(i:ES _...n._.... _'. ~"_ __.-- __'_'__'__0_'_ _ _ ....0._ 0"'_'. "_""'_ ___. _'______ 0' __. _._ _____. Original contract amounl $ 'f 6 f "3 P::< . ~ ---1.Q!L.. % of original contract Tolal amount of Drevious contract amendments r't!? /' If3 ''I. ~ r; / % of original contract Amount of this contract amendment ;;Z ".:3 ::;z, r 7 CJ . '50 ::zq;. 9% of original contract' , 4 TOTAL AMOUNT OF CONTRACy?::: ~ p' f7-I() $;: ;;z- /;2, :z. tC f. "70 /,::u:; % of original conlract ----- Q '1p~ - ( . Is the total aggrega st h nge for the Goods & Services contract ' less than or equal 35o/~ the original contract amount? YES ........-- NO _ Not Applicable_ If "No', City Council approval is required, City Council approval was received on (Date) Are there any applicable performance or payment bonds and insurance coverages that need to be adjusted to account for the change in the contract amount? YES _ NO _ Not Applicable ~ Was the original contract approved by the City Council, or is it exempt? p'-"-Y ~ ~ nt.tf.d YES (Approved by Council) ~ -..., d K.Y c.L ~ /':2 - rG'-"'NO (Exempt/Not Required) e-~'t." a~;--y~, a-rz-2' "'-.a/ L ~'i4--~ '//7:LP/~7 co~nts I Additional information: ~;r;;,. , e~ ~~~L' p-;r~.I$~ .... ") ~t!.~1'''''-''''/ ~/2. ~~ (f v Lee Tuneberg ~ V 6 - ~:2- - (0 p ~te: b/Z;/r; , ~~./~/of ~~ Prepared by: &<;n. Please circle: Department: Date: (Reason for exemption) ~ c::: ~ "5-<' jJE;:Jc:.JZ-q ?<.-L~ ~ d=2ft ~d" ~ bC'-- c..e.}<GL r ~ '-'" -d.-^-L Approved Not Approved Form #11 - Contract Amendment Approval Request Form - GOODS & SERVICES, Page 1 of 1, 6/22/2010 A (equest for a Purchase Order REQUISITION FORM CITY OF ASHLAND THIS REQUEST IS A: ~ Change Order(existing PO # 8062) Date of Request: 6/18/10 I Required Date of Delivery/Service: 9/16/10 I, Vendor Name , Address City, State, Zip Tefephone Number Fax Number Contact Name Triad Mechanical. Inc 1419 NE Lombard PI Portland OR 97211 503-289,9000 503-289,0316 Dennis Carroll SOLICITATION PROCESS Small Procurement o Sole Source 0 Invitation to Bid o Less than $5,000 o Written findings attached (Copies on file) o Quotes (Optional) o Quote or Proposal attached Coooerative Procurement IlSI Reauest for Proposal o State of OR/WA contract (Copies on file) Intermediate Procurement o Other govemment agency contract 0 Soeclall Exemot o (3) Written Quotes o Copy of contraCt attached 0 Written findings attached (Copies attached) o Contract # 0 Quote or Pronasal attached 0 Emeraencv 0 Written findings attached . 0 Quote or Prooosal attached Description of SERVICES ~ '~;i:i1~lr~;; . $,tj!11e~~In:i~tetj~!~(i; ;~ :;n()u~~j'c~~4~'$t32;i~7' r"'~';~;'~:'4:~'~~~""!~?i}-,'~~~'~ ...~ijt,..",_~:.._~ ~ Floculattors Soda Ash, Fencing And electrieal equipment Per the attached Change Order No.2 Description of MATERIALS Item # Quantity Unit Unit Price Total Cost Project Number 06-02 .:t5"~ "'v Account Number 670.08,19.00.704200 (~) AccountNumber 670,08.38.00.704200~) 75/.. ",Cl' D Per attached QUOTE (cAcctNoll . Items and selVices must be charged to the appropriate account numbers for the financials to reflect the actual expenditures accurately, By signing this requisition form, I certify that the i formation provided above meets the City of Ashland public contracting requirements, and the doc e tatio be pr ided upon request. . L Employee Signature: Supervisor/Dept. Head Signature: ~ 1;>' 0 ~- G:lpub-wrkslengI06-02 TP Process ImprlAdminlTriadlC02120 10-05-20 Change Order.doc J6b."~' ~" t" /18' /.!)Q16