HomeMy WebLinkAbout2010-152 CONT Chg Order #2 - Visar Construction RECEIVED CITY OF ASHLAND DEPARTMENT OF PUBLIC WORKS , City of Ashland CONTRACT CHANGE ORDER NO. 2 SEP 2 0 2010 PROJECT: LOCATION: Liberty Street Improvement Liberty Street DATE: 9/13/10 PROJECT NO.: 2004-21 CONTRACTOR: Visar Construction Co. Inc. You are requested to perform the following described work upon receipt of an approved copy of this document or as described by the Engineer: Item No. DescriDtion Quantity Unit Price Amount CO2-II Re-route phone service at sta. 6 + 90 L.S. $1,821.00 $1,821.00 Re-route sanitary sewer service in C02-12 conflict with storm Sewer L.S. 250.00 250.00 Replace 12" HOPE with 12" CO 2-13 CL.V.RCP Not aooroved Acquire additional water service CO 2-14 permits L.S. 204.00 204.00 Replace existing broken 12" storm CO2-IS drain 'L. S. 408.00 408.00 Original Contract Amount Total this Change Order Previous Change Order Revised Contract Total , $142,798.75 $2,683.00 6,690.00 $152,171.75 (6.56% total increase) Recommended By: The time provided for completion of this contract is increased by 10 calendar days. become an amendment to the contract and all provisions of the contract will apply. r/fJ~ff'r~ j___~)h . y of Ashland ~~~ This document shall ~J71/() Date Approved By: .., /ZO//b Date Accepted By: -Jl1~ 1)0 Oat ENGINEERING Tel: 541-488.5347 20 E, Main Street Fax: 541-488-6008 Ashland, OreQon 97520 " TTY: 800-735.2900 www,ashland,or,USG:lpub-wrkslengI04.21 Liberty StreetlA_Admin\Cons Vendor1\Contract DocumentslChange OrdersI04-, r~' doc , i 1. Page 1/1 ~~, ASHLAND CITY RECO 20 E MAIN ST. ASHLAND, OR 97520 (541) 488-5300 7/1/2010 PO NUMBER 09585 VENDOR: 015201 VISAR CONSTRUCTION CO INC PO BOX 3101 CENTRAL POINT, OR 97502 SHIP TO: Ashland Public Works (541) 488-5587 51 WINI;lURN WAY ASHLAND, OR 97520 FOB Point: Terms: Net Req. Del. Date: Special Inst: Req. No.: Dept.: Contact: Mike Faught Confirming? No Q'uantitv -. . Unit ; - - :. Descrlpti"on THIS IS A REVISED PURCHASE ORDER Construct the Liberty Street Improvement Project #2004-21, Payment to be made in accordance with the proposal received on 05/06/10 and attached to the contract. I.:' Unit Price Ed. Price 142,798.75 Contract for Public Works Construction Date of contract: June 7, 2010 Insurance & Bonds required/On file Approved by City Council May 18, 2010 Insurance & Bonds required/On file Processed change order 08/18/2010 Change Order No. 1 Processed change order 09/23/2010 Change Order NO.2 Change Order NO.2 - Cumulative change 6,69000 2,683.00 :ILL TO: Account Payable 20 EAST MAIN ST 541-552-2028 ASHLAND, OR 97520 SUBTOTAL TAX FREIGHT TOTAL 152171.75 0.00 0,00 152,171.75 Account Number Project -Number", Amount Account Number Project Number Amount. : 260.08.35.00.70420 E 200421.120 27 390.92 : 260.08.41.00.70420 E 200421.120 124780.83 , . ~J.- fut~ E:.:ied VENDOR COPY CITY OF ASHLAND A request for a Purchase Order REQUISTION FORM Date of Request: THIS IS A REQUEST FOR A: Required Date of Delivery/Service: l;z{~::;:;':::;_::-;": I [X ] Change Order (existing PO #9585 Vendor Name: Address: City, State, Zip Phone: Project Title: Project Number: Visar Construction Co. Inc. PO Box 3101 Central Point, OR 97502 541-944-9060 Liberty Street Improvement 2004-21 Services Only Solicitation Process: [] Exempt ( I 3 Written Quotes (copies attached) I ) Sole Source [X) Invitation to Bid (copies on fife) [ ] less than $5000 { ] Request for Proposal (copies on file) Description Original Contract Amount Change Order No.1 Change Order NO.2 Employee Signature: Total Cost Account Number Account Number 260.08.35.00.704200 (18%) 260.08.41.00.704200 (82%) 'Please attach the Original signed contract and Insurance Certificates. --~ Supervisorl Dept Head SIgnature: /jt:.h":) G:\pub-wrks\eng\04-21 liberty StreellA_Admin\04-21 Change order 2 Req Visar.xls