HomeMy WebLinkAbout2010-189 CONT Chg Order #3 - Visar Construction . CITY OF ASHLAND DEPARTMENT OF PUBLIC WORKS CONTRACT CHANGE ORDER NO. 3 PROJECT: LOCATION: Liberty Street Improvement Liberty Street DATE: 11/08/1 0 PROJECT NO.: 2004-21 CONTRACTOR: Visar Construction Co. Inc. You are requested to perform the following described work upon receipt of an approved copy of this document or as described by the Engineer: Item No. Description Quantitv Unit Price Amount C03-17 Reconstruct sewer lateral (a) sta. 4 + 28 L.S. 267.32 267.32 C03-18 Reconstruct sewer lateral (a) sta. 4 + 62 L.S. 278.32 278.32 CO 3-19 Reconstruct sewer lateral (a) sta. 5 + 55 L.S. 300.32 300.32 CO 3-20 Install two (2) nhone droos to 790 & 796 Libertv L.S. 342.44 342.44 Construct 4" drain pipe with area drains sta. 7 + 96 CO 3-21 to 9 + IS L.S. 502.25 502.25 CO 3-22 Adiust concrete wall can to match curb L.S. 418.99 418.99 CO 3-23 Relocate I" water line and valve L.S. 309.31 309.31 CO 3-24 Restack block around transformer L.S. 57.60 57.60 Fee for additional mobilizations due to phone and CO 3-25 !!as conflicts L.S. 1308.41 1308.41 CO 3-26 Relocate water service at 769 Libertv L.S. 357.13 357.13 Original Contract Amount Total this Change Order Previous Change Orders Revised Contract Total The time provided for completion of this contract is increased by 10 calendar days. become an amendment to the contract and all pr isions of the contract will apply. $142,798.75 4,142.09 9,373.00 $156,313.84 (9.46% total increase) This document shall Recommended By: t1-n.-- 1t/9.ht'/t' Date 1/ Iii I ZOIC> 111'1/ {)..% Date Ashland ......- Approved By: Accepted By: I ?l \ 0 Oat ENGINEERING 20 E. Main Street Ashland, Oregon 97520 www.ashland.or.us G:\pub-wrksleng\04.21 Liberty StreetlA--^dmin\Cons Vendor1\Contract DOGumentslChange Orders104.21 VisarChange Order 3.doc Tel: 541-488.5347 Fax: 541-488-6006 TlY: 800.735.2900 r~' .~.. ._~ CITY RECORDER Page 1/1 CITY OF ASHLAND 20 E MAIN ST. ASHLAND, OR 97520 (541) 488-5300 'f:":DATE 7/1/2010 .. PO'NI;)MBEW'. 09585 VENDOR: 015201 VISAR CONSTRUCTION CO INC PO BOX 3101 CENTRAL POINT, OR 97502 SHIP TO: Ashland Public Works (541) 488-5587 51 WINBURN WAY ASHLAND, OR 97520 FOB Point: Terms: Net Req. Del. Date: Speclallnst: Req. No.: Dept.: Contact: Mike Faught Confirming? No ~'q2Quaniitv~:q 3~:lfnit';:;(;1 ,X';,":' /";'.' .,": :;::',; 'i ,.,;,LiiOlls'criiilidri:, .:: . . "",,;' -~:-;:,'~ .~... 'J-~~ .,:;~. ,:~. -jJnifP,riceS~ ',: ~l::,-!ExtiRfjce~~.I';;: - THIS IS A REVISED PURCHASE ORDER Construct the Liberty Street 142,798.75 Improvement Project #2004-21, Payment to be made in accordance with the proposal received on 05/06/10 and attached to the contract. Contract for Pubiic Works Construction Date of contract: June 7, 2010 . - Insurance & Bonds required/On file Approved by City Council May 18, 2010 Insurance & Bonds required/On file Processed change order 08/18/2010 6,690.00 Change Order No. 1 Processed change order 09/23/2010 2,683.00 Change Order NO.2 Change Order NO.2 - Cumulative change Processed change order 11/17/2010 4.142.09 Change Order NO.3 - SUBTOTAL 156313.84 31LL TO: Account Payable TAX 0.00 20 EAST MAIN ST FREIGHT 0.00 541-552-2028 TOTAL 156,313.84 ASHLAND, OR 97520 r&ill!~countr!iiiiiibei~ [~p.roject;NlhnHert;;,~;rX~ {;.~i;'~,~lAmQUr)i:~:f:igl~I ;j;/, ~cco-unt~Numlier,1/? ;;~;i:~rf?'l:OjectfNum~~;l~ g~~JgKm()unt)k~ E 260.08.35.00.70420 E 200421.120 28 136.50 E 260.08.41.00.70420 E 200421.120 128 177. 34 ft'I<. 1.. ~ ';/7/0 - Aut~zed Signature VENDOR COpy FORM #13 "CONTRACT AMENDMENT APPROVAL REQUEST FORM Request for a Change Order CITY OF ASHLAND Description of Contract Amendment resulting from: "....-...-...' " ,-r' - -, . ~". -:'-"',:"' -'.. .~,.._ -:''''''',",'"'1-- "__M'_. ~...... ~"'~ ' C..... .C-. .. '--. . 'C.-' "h,,__ -- '-: -:, -: "-.. .. .'F''-' -- ,':,_ ':'''~'-''''''--'' ",., - :~,_ '_ _~. :"'~""""'._''''''. _':"'" .-,_r,'; _~.. 11'Coriipetitive Sealed Bid'(ITB), 2)Cciinpetitive'Seall!i1 'Proposal' (RFP) or 3)SoleSource'.Proclirement: . --'"....-,.- "'-' ~ ,,---~-.,-----_. ,-.- -,.-.._.+._.,----_._----~.._._.._-~_.._._-~-.. ".-. ......_-_._--_.~._.._- ...----.. ._----" Supplier / Contractor: , .y' ,( -7 d--Y' ~ 41-~ V:r- ~ )7'(' ,/~ cY f ~ 6 c.;;- ~.-h ~ -f--P ct2-?- L..__ ~, .3 Purchase Order Number: Description: tJ Per attached contract amendment Contract Amendment Original contract amount $ ,/~.;2f 7 9~. ?'7" ~<f 'i? '( 3 , ~ '<'?/~;<.t71 $ /~6 8/3. e,JJ Total amount of previous contract amendments Amount of this contract amendment TOTAL AMOUNT OF CONTRACT ~ % of original contract 6, "",-6oj, of original contract .:2.. ., % of original contract ?.tJ?, ~~ of original contract Is the total amount of the cumulative amendments less than or equal to 25% of the original contract amount or $250,000 \y:hI~h!y~f1s'i~ss? ~ES~' NO' .... - .. . 'If "No", a Special Procurement is required for the amount that exceeds authority. Council approved on (Date) In accordance with OAR 137.047.0800, the amendment is: 1) Within the scope of procurement 2) Necessary to comply with a change in law that affects performance of the contract. 3) Results from renegotiation of the terms and conditions, including the contract price making it advantageous to the contracting agency a) Provided goods and services are the same as in the unamended contract b) The amended contract does not have a total term greater than allowed in the solicitation document YES .",.-' NO' "If "No', a Special Procurement Is required for the amount that does not meet these.criteria. Council approved on (Oate) Project Number ______. ___ ~ nr? '. , \..)"';...""'.- l"C<..L'f4lA ~(~ Account Number ___' __' __' __1______ Account Nu~r ___' __' __' __' ______ Account Number ___' __' __' __' ______ Account Number __:'" __' __' __' ______ "Expenditure must be charged to the eppropriatza 50unt numbers for the financiats to re ect the actua' expenditures accuretely. Mach extra pages if needed. ~ 4"1 o4"",~ h .....- ;( ... ~ r /'.- / 7.- /'''' Prepared by: t <-.. {;/ - ~ Department' ~. Date: <./ '. . -...,5;.,.~ rc..L.d,.--e.u ",~.9'!'u'l~I\'a~: Reviewed by: tI Approved 1 Not Approved Date: Department Head Comments: Funds appropriated for current fiscal year: ~ NO Comments: .at J..- .~ Finance Director 11/t7{:.J ate Form #13 - Contract Amendment Approval Request Form -ITS, RFP or SOLE SOURCE PROCUREMENT, Page 1 of 1,11/17/2010 CITY OF ASHLAND A request for a Purchase Order REQUISTION FORM Date of Request: 1~~'~1:012O:1 III THIS IS A REQUEST FOR A: Required Date of Delivery/Service: Ie [X J Change Order (existing PO #9585 Vendor Name: Address: City, State, Zip Phone: Project Title: Project Number: Visar Construction Co. Inc. PO Box 3101 Central Point, OR 97502 Phone: 541-664.3032 Cell: 541-944-9060 Liberty Street Improvement 2004.21 Services Only Solicitation Process: II Exempt (13WrlttenQuotes(copJes attached) [ I Sole Source [X) InvitaUonto Bid (copies on file) [ ] less than $5000 [ 1 Request for Proposal (copies on file) Description Total Cost Original Contract Amount Change Order No.1 & 2 Change Order No.3 Account Number Account Number 260.08.35.00.704200 (18%) 260.08.41.00.704200 (82%) Employee Signature: "Please attach the Original signed contmct and Insurance CeJ1J'ficates. ~J/Z.i Supervisorl Dept. Head Signature: G:\pub-wrks\eng\04-21 liberty Street\A_Admin\04-21 Change order 3 Req Visar.xls