HomeMy WebLinkAbout2002-204 CONT Chg Order #4 - Adroit ConstructionPECK SMILEY ETTLIN*
architects
C H A N G E O R D E R
Change Order No.: 4
Date: 26 February 2003
Project: Ashland Fire Station Date of Contract: 10 July 2002
Owner: Ashland Fire & Rescue Contractor: Adroit Construction
You are directed to make the following changes in this Contract:
ADD work described in the attached COPR #28, 30R, & 31 $6,325.87
DELETE work described in the attached COPR #29 ($230.50)
Contract Amount: Add to the Contract Amount the sum of:
Six Thousand Ninety Five & 37/100 .........................................................$ 6,095.37
The Contract Time will be changed by 0 days.
The Date of Completion as of the date of this Change Order is
Original Contract Amount $ 2,513,093.00
Previous Additions $ 49,845.48
Total $ 2,562,938.48
Previous Deductions $ 0.00
Contract Sum prior to this Change Order $ 2,562,938.48
Amount of this Change Order (Add) $ 6,095.37
Contract Amount to Date $ 2,569,033.85
ARCHITECT CONTRACTOR LNER
Date Date Date
J:\99\9924\WP\construction\change orders\co4.doc 4412 SW Corbett, Portland, OR 97201
tel503.248.9170 fax 503.248.0223
www.psearchs.com
adroit
CONSTRUCTION COMPANY, INC.
January 31, 2003
Robert Thrapp
Peck/Smiley/Ettlin, Architects
4412 S.W. Corbett
Portland, OR 97201
Re: Ashland Fire Station
Change Order Cost Proposal #28
Dear Bob,
The following are costs to excavate and haul off site additional buried concrete footings encountered
during retaining wall footing excavation.
Back-hoe 1 hour @ $75.19 per hour
Dump truck 1 hour @ $65.00
Adroit overhead / profit
Bond / insurance
$75.19
65
Subtotal
14.01
3.08
Total Cost 157.2
Please advise us in writing if these costs are acceptable to you. Feel free to call me if you have any
questions or need additional information.
Sincerely,
Steve Lawrence
SL/cr
cc: Jack Nickels
Keith Woodley
Jim McNamara
Accepted by
ADROIT CONSTRUCTION COMPANY, INC.
P.O. Box 609, Ashland, Oregon 97520 • 541-482-4098 • Fax: 541-482-4218
OREGON NO. 44384, CALIFORNIA NO. 454960B
an 30 03 03:54p Burl Brim Excavation 154141iti??5?
6orl Brim Excavation, Inc.
SUBCONTRACTOR TIME & MATERIALS DAILY WORK RECORD
F. e
Job Name: Date: o -?
Extra Work Requestor.
Description of Work: v" lz?
X r .n t r.. k '?, .^v'. r•?. ?? ?, t 4? r? n ?. L , it, c_v , C C_..
Relative to the following directive(s) by the Owner;
ASI # RF1 # CCD # RFP #
Authorized by Adroit:
LABOR
Date:
Workmen(s Name Classification Hrs Pay Rate Pay Total
R.lt?? ?.CL %J r?r e? ?tr r.• ?. ?2 ??
tICV Drives 1 zo
DAILY TOTALS S ?l
MATERIALS
Material Items Number Unit Price Total Invoice #
DAILY TOTALS
EQUIPMENT
Equipment Items Hours Rate Total Invoice #
C- T!?ICICA-
?'? n ???c?: ?M • 1 0 Ytb Y„r4
r ?.
, .
1 ?s-
DAILY TOTALS S Z
This work was completed as witnessed by me:
Adroit Project Superintendent: Date: / 3C? G
NOTE: Signature by Adroit Project Superintendpnt is not an acknowledgement or cclptance of cost . ,
Job Complete ? More work to Signature: „_ ? • ......-
perform Aut rized Subcontractor Representative
Forward all signed Time & Materials Daily Work Record(s) to: Adroit Project Manager upon completion of the work.
All Time and Materials Daily Work Records must be accompanied by Material Invoice Copies, Rental Receipt Copies,
Workmen(s) Pay Rata as authorized by the Contract Documents for the Project or pre-arranged with Adroit.
ALL T & M DAILY WORK RECORDS ARE TO BE SIGNED BY ADROIT PROJECT SUPERINTENDENT DAILY.
A SIGNED COPY BYADROIT PROJECT SUPERINTENDENT WILL BE ISSUED TO YOUR FOREMAN EACH DAY.
DD
adroit
CONSTRUCTION COMPANY, INC.
January 31, 2003
Robert Thrapp
Peck/Smiley/Ettlin, Architects
4412 S.W. Corbett
Portland, OR 97201
Re: Ashland Fire Station
Change Order Cost Proposal #29
Dear Bob,
The following is a credit to delete the generator grounding as requested.
Credit electrical labor and materials
($230.50)
'Total Credit: ($230.507
Please advise us in writing if you would like us to proceed with this change. Feel free to call me if you
have any questions or need additional information.
Sincerely,
Steve Lawrence
SL/cr r
Accepted by
cc: Jack Nickels
Keith Woodley
Jim McNamara
ADROIT CONSTRUCTION COMPANY, INC.
P.O. Box 609, Ashtand, Oregon 97520 • 541-482-4098 • Fax: 541-482-4218
OREGON NO. 44384, CALIFORNIA NO. 454960B
01/30/2003 16:16 VALLEY ELECTRICAL CONTRACTORS -> 4824218
PO Box 1555 Phone 541-773-1405
ModFord, OR 87501 Fax 541-770-2819
N
-WW
CC 55415
FAX COVER SHEET
NO. 325 D01
DATE: a ua 3 2003
COMPANY: Adroit Constructs
FAX NO: X 18
ATTN: Stavo LggM22
RE:
FROM: Stuart
NUMBER OF PAGES FOLLOWNG THIS COVER SHEET: 1
IF YOU DO NOT RECEIVE A L PAGES AS INDICATED ABOVE, PLEASE
CALL THE ABOVE TELEPH NE NUMBER IMMEDIATELY.
THANK YOU.
REMARKS: Steve
Stuart
01/30/2003 16:16 VALLEY ELECTRICAL CONTRACTORS 4 4824218
Mike Hamilton ALLEY ELECTRICAL
Steve Hills
CCB#55415 Cif"ONTRACTORS, INC.
Steve Lawrence
Adroit Construction Co.
P.O. Box 609
Ashland, Or. 97520
NU. 152b W02
P.O. Box 1555
Medford, OR 97501
Tel # (541) 773-1405
Fax # (541) 770-2819
January 30, 2003
RE: Ashland Fire Station
Steve
per your request I hav puWnd together a credit for the generator grounding on the above-
meationed project. please below the detail for this credit.
4 Ground rods 16.00
3 Hours labor 43.50
1 Lot misc. 15,00
(%10)
De uct for this change
Sincerely,
l
Stuart Davis -
64.00
130.50
15.00
209.50
21.00
$230.50
CITY OF ASHLAND
20 E MAIN ST.
ASHLAND, OR 97520
(541) 488-5300
CITY RECORDER'S COPY
Page 1 /2
036~4
VENDOR: 000013
ADROIT CONSTRUCTION, INC
P O BOX 609
ASHLAND, OR 97520
SHIP TO: Ashland Fire Department
(541) 482-2770
455 SISKIYOU BLVD
ASHLAND, OR 97520
FOB Point:
Terms: Net
Req. Del. Date: 07/20/2002
Special Inst:
Req. No.:
Dept.: FINANCE
Contact: Keith Woodle¥
Confirming? No
Quantity Unit Description Unit Price Ext. Price
THIS IS A REVISED PURCHASE ORDER
BLANKET PURCHASE ORDER
Fire Station Construction
2 513 093.00
Bid
:.: Contract dated: July 10, 2002
Start date: July 20, 2002
.... Completion date: 365 Days (07/20/2002)
Insurance required/on file ':
Revised purchase order 10-15-2002 23,697.62
Change Order No. 1
Add work described in the memos of 15th
· . & 16th of August 2002 & COPR
#1,2,3,4,6,&6A
Revised purchase order 12/05/2002
20,907.81
Change Order No. 2
: ADD work described in the attached COPR
#5,9,10R2,11,12R,13R,16 & 17
$22,109.81. DELETE work described in
the attached COPR #8 & 18.
Revised purchase order 02/05/2003 5,240.05
Change Order #3
· ." ADD work described in the attaced COPR
#20, 21,24, 25 ,& 26R- $14,007.42.
DELETE work described in the attached
COPR #19 & 23- ($8,767.37)
SUBTOTAL
BILL TO: TAX
FREIGHT
TOTAL
...... AccOUnt Number · . Amount ' Account Number "Amount
E 410.03.43.00.702200 2,569,033.85
Authorized Signature VENDOR COPY
Page 2 / 2
CITY OF ASHLAND
20 E MAIN ST.
ASHLAND, OR 97520
(541) 488-5300
VENDOR: 000013
ADROIT CONSTRUCTION, INC
P O BOX 609
ASHLAND, OR 97520
FOB Point:
Terms: Net
Req. Del. Date: 07/20/2002
Special Inst:
DATE PO NUMBER
09/20/2002 03624
SHIP TO: Ashland Fire Department
(541) 482-2770
455 SISKIYOU BLVD
ASHLAND, OR 97520
Req. No.:
Dept.: FINANCE
Contact: Keith Woodley
Confirming? No
Quantity Unit Description Unit Price Ext. Price
Revised purchase order 03/10/2003 6,095.37
Change Order #4
ADD work described in the attached COPR
#28, 30R, & 31 $6,325.87. DELETE work
described in the attached COPR #29
($230.50)
SUBTOTAL 2,569,033.85
BILL TO: Account Payable TAX 0.00
20 EAST MAIN ST FREIGHT 0.00
541-552-2010 TOTAL 2,569,033.85
ASHLAND, OR 97520
Account Number Amount Account Number Amount
3// v3
Authori ed Signat re VENDOR COPY
CITY OF
-AS H LAN D
REQUISITION FORM
THIS REQUEST IS A:
Change Order(existing PO # 03624)
Date of Request: 03-06-2003
Required Date of Delivery/Service:
Vendor Name: ADROIT CQNSTRl1CTION
Address: PO Box 609
City, State, Zip: Ashland, OR 97520
Phone: 482-4098
Fax Number
Deliver Location 482-4218
Services Only
Description
Total Cost Solicitation Process:
? Exempt ? 3 Written Quotes
(copies attached)
? Sole Source ? Invitation to Bid
(copies on file)
Fire Station Construction Project ? Less than ? Request for
Change Order # 4 $ 6,095.37 $5000 Proposal (copies on file)
Account Number 410-03-43-00-702200
*Please attach the Original signed contract and Insurance certificate.
Materials Only
Account Number
*Please attach the quotes.
Employee Signature: Supervisor/Dept. Head Signature:
NOTE: By signing this requis ion form, I certify that the above requ t meets the City of Ashland Solicitation Process requirements and can be provided
when necessary.
G:Finance\Procedure\AP\Forms\Requisition form - Change Order 4 Updated on:07115102
D
adroit
CONSTRUCTION COMPANY, INC.
February 13, 2003
Robert Thrapp
Peck/Smiley/Ettlin, Architects
4412 S.W. Corbett
Portland, OR 97201
Re: Ashland Fire Station
Change Order Cost Proposal #30 Revised
Dear Bob,
The following are revised time and material excavation & backfill costs to remove the tanks and
contaminated soils. We had left out Burl Brim backfill time and material sheet for 2/3/03 and 2/4/03.
Burl Brim Excavation Time & Material 2-3-03
Burl Brim Excavation Time & Material 2-3-03
Burl Brim Excavation Time & Material 2-4-03
Burl Brim Excavation Time & Material 2-3-03 and 2-4-03
Adroit Labor Traffic Control 3 hours at $46.00/hour
Adroit Labor Relocate Fence 4 hours at $46.00/hour
Trash Pump Rental
Pick up & Delivery
$2,312.15
64.97
468.36
1,450.08
138.00
184.00
42.10
35.00
Sub-Total: $4,694.66
Adroit Overhead/Profit: 469.46
Bond/Insurance: 103.28
Total Cost: $5,267.40
Please advise us in writing if these costs are acceptable to you. Feel free to call me if you have any
questions or need additional information.
Sincerely,
Steve Lawrence
SL/cr
cc: Jim McNamara; Keith Woodley; Jac Nickels
ADROIT CONSTRUCTION COMPANY, INC.
P.O. Box 609, Ashland, Oregon 97520 • 541-482-4098 • Fax: 541-482-4218
OREGON NO. 44384, CALIFORNIA NO. 4549608
eb 04 03 11:31a Burl Brim Excavation
154.14888353.
i
P.2
Burt Of rn Finantide IN-
- j
SUBCONTRACTOR TIME & MATERIALS DAILY WORK REC6R1) Job Name: ?C art Date: ca
a
Extra Work Requestor:?,,
Description of Work.
, r
Relative to the following directive(s) by the Owner;
ASI #
LABOR
Authorized by Adroit:
RF1 #
CCD #
RFP #
Date:
MATERIALS
Material Items Number Unit Price Total Invoice #
?.vrd.?•-< s? a-c?c Sa ; / Lo rl (c c
5.5 a 330.53
DAILY TOTALS 30.
EQUIPMENT
Adroit Project Superintendent: Date:
NOTE: Signaturu by Adroit Project Supe . ten dent is not an acknowledgement or acceptance f costs.
Job Complete. More work to Signature: Z_J
perform uthorize ubcontractor Representative
Forward all signed Time & Materials Daily Work Record(s) to: Adroit Project Manager upon completion of the wutk.
All Time and Materials Daily Work Records must be accompanied by Material Invoice Copies, Rental Receipt Copies,
Workmen(s) Pay Rate as authorized by the Contract Documents for the Project or pro-arranged with Adroit.
ALL T & M DAILY WORK RECORDS ARE TO BE SIGNED BY ADROIT PROJECT SUPERINTENDENT DAILY.
A cu--man rnpy RY ADROIT PROJECT SUPERINTENDENT WILL BE ISSUED TO YOUR FOREMAN EACH DAY.
This work was completed as witnessed by me:
Feb it 03 11:12a Hurl Brim Excavation 15414888353 P.2
Bat( Brut FxryFitira, ine.
Relative to the tollowing directive(s) by the Owner-,
SUBCONTRACTOR TIME & MATERIALS DAILY WORK RECORD
Job Name: Asvl i a-AgA t) R Date: <: 32
Extra Work Requestor: ph rx CS 6e `T
Description of Work: I LA by 1
ASl # RFI # CCD #
LABOR
Authorized by Adroit:
Workmen s) Name C:lassiticatinn Hrs Pa Rate Pay Total
DAILY TOTALS
MATERIALS
Material Items Number Unit Price Total Invoice #
. _. , 5.93 a2- c
DAILY TOTALS
EQUIPMENT
Equipment itern;s) Hvurs Rate Total Invoice #
DAILY TOTALS
This work was completes{ a3 witnocced by me:
Adroit Project Superintendent:
NOTE: Signature by Adroit Project Superintendent is not an acknowledgem ni o acceptance of st .
Job Complete More work to Signature. `
perform At6orized Sube n actor Representative
Forward all signed Time & Materials Daily Work Record(s) to: Adroit Proiect Manager upon completion of the work.
All Time and Materials Daily Work Records must be accompanied by Material Invoice Copies, Rental Receipt Copies,
Workmen(s) Pay Rate as authnri7t'd by the Contract Documents for the Project or pre-arranged with Adroit.
ALL T & M DAILY WORK RECORDS ARE TO BE SIGNED BY ADROIT PROJECT SUPERINTENDENT DAILY.
A SIGNED COPY BY ADROIT PROJECT SUPERINTENDENT WILL BE ISSUED TO YOUR FOREMAN EACH DAY.
RFP #
Date:
UBCONTRACTOR TIME & MATERIALS DAILY WORK RECORD
Job Nam ey-AY..:?54? Date:
Extra Work Requestor.
De cription of Wor".
?
Relative to the following direetive(s) by the Owner:
ASI # RFI #
Authorized by Adroit:
LABOR
CCD #
RFP #
Date:
Workmen(s) Name Classification Hrs Pa Rate Pay Total
Irv
DAILY TOTALS 5 ri r
MATERIALS
Material Items Number Unit Price Total Invoice #
DAILY TOTALS
EQUIPMENT
Equipment Items Hours Rate Total Invoice #
za ,o? /_30, 00 mfl6?to?, ?r
DAILY TOTALS
This work was completed as witnessed by me:
Adroit Project Superintendent: Date
NOTE: Signayrd by Adroit Project Superintendent is not an acknowledg t o cceptance of c
Job Complete I I More work to Signature:
U perform Authorized Subcont or epresentative
Foeward all signed Time & Materials Daily Work Record(s) to: Adroit Project Manager upon completion of the work.
All Time and Materials Daily Work Records must be accompanied by Material Invoice Copies, Rental Receipt Copies,
Workmen(s) Pay Rate as authorized by the Contract Documents for the Project or pre-arranged with Adroit_
ALL T & M DAILY WORK RECORDS ARE 710 BE SIGNED BYADROIT PROJECT SUPERINTENDENT DAILY.
A SIGNED COPY BY ADROIT PROJECT SUPERINTENDENT WILL BE ISSUED TO YOUR FOREMAN EACH DAY.
DO NOT FORWARD THESE FORMS WITH YOUR MONTHLY BILLING INVOICING
q
z'd CSCBPBt?T*SI uot2eneox3 wl ig ling eG*:,, CO 11 q4J
a'
ti
X
yn
J
'-1
a
A
Q
O
W
N ?V N N N
1A
N eo ?
N IV f3 (V N
G.1 (,7 ? ? ?..) W
(D (^?D f0 fD '? .I7
? 7 Ozl
3
N N N qi p) p?
a C ii iZ i], O.
O' O' O O O O
it t x
x ;:o
CD !D cD M CD
O P H O A
O
aaQaaa
Vf Vl N M M V?
a1 N
cy,
h
o
o O
a C? Co
0
O
m = U N 0
?c
y A
a 4
S. O x z
e t9 co c c
n m
0
C
O
c 0
-n 0
CD m
NA C n
m X cD
r-j m C3L Cn io
N Z7
CA :3 1: T ? O
p' O CO O
?
j N 4 t0
d
N N X
n
O CD
m
x
N
a -+ N
A (?
-4 U) CA
A oo p N p i
g
X
m
lD
m
N
r
L].
C?
O
77
CD
0
Q.
N
J
C
L
CO a)
O
a N N-
a a M.
C) E3
a o m
Q p c
T ;D 7
cn o p•
zr o 0
? n
G
a
J
r
E'ai ESB8B8*T*ST uoizeneox3 wtJg tang e6 *:Ti Co 11 qaj
rep U0 UJ VT: 0-rf, DUr-1 Dr-110 GAVO V OM1vii
l J T 1 T V V V V V J r+ • 1
1
BURL BRIM EXCAVATION, INC.+534 CROWSON RD ? ASHLAND OR 97520
PHONE 1-541-488-1095 • FAX i-541 498-8353
FAX COVER SHEET
DATE: 02/05/03
ATTN: Project Manager Ashland Fire Station
RE: Change Order
FAX #: 452-4218
# Of Pages including cover 2
Please give me a call if you should have any more questions.
Sine rely,
my Owen
Office Manager
Burl Brim EXcavation, 11:c.
u u
?'? to
eu uu ua uT: anp• Duf A DI L111 LAI?OVOVIV„ av?a?---
rr • C_
9trrl grim Excavation, (a?.
SUBCONTRACTOR TIME & MATERIALS DAILY WORK RECORD
Job Name: a (/j Date:
Extra Work Requestor: .2 {? `j D!7 ,I
Descriotion of Work: A24b ,, ®®-?'?i4?
Relative to the following directive(s) by the Owner;
ASI # RFI #
Authorized by Adiuit.
LABOR
CCD #
RFP #
Date:
Workmen(s) Name -Classification Hrs Pa Rate Pav Total.
?Da,?e 1? t ?•??- ? a?. ?Y 55 •?
DAILY TOTALS • Z g
MATERIALS
Material Item(s) Number Unit Price Total Invoice #
r o Bwc r 5?sa s S.
DAILY TOTALS Oo?L
EQUIPMENT
2/y
213
43
This wut k was wmpleted as witnessed by me:
Adroit Project Superintendent: Date:
NOTE: Signature by Adroit Project Superintendent is not an acknowledges r accepta e o costs.
Job Complete More work to Signature-
perform orized Su c r ctor Representative
Forward all signed Time & Materials Daily Work Record(s) to: Adroit Project Manager upon completion of the work.
All Time and Materials Daily Work Records must be accompanied by Material Invoice Copies, Rental Receipt Copies,
Workmen(s) Pay Rate as authorized by the Contract Documents for the Project or pre-arranged with Adroit.
ALL T & M DAILY WORK RECORDS ARE TO BE SIGNED BYADROIT PROJECT SUPERINTENDENT DAILY.
A SIGNED COPY BYADROIT PROJECT SUPERINTENDENT WILL BE ISSUED TO YOUR FOREMAN EACH DAY.
D
adroit
CONSTRUCTION COMPANY, INC.
February 14, 2003
Robert Thrapp
Peck/Smiley/Ettlin, Architects
4412 S.W. Corbett
Portland, OR 97201
Re: Ashland Fire Station
Change Order Cost Proposal #31
Dear Bob,
The following are costs to delete the plastic laminate countertop at the kitchen island and install
stainless steel.
-Credit plastic laminate top
1 1/8" plywood sub top materials
Sub top labor l hour ( $46.00
Stainless steel top
Adroit overhead / profit
Bond / insurance
($390.00)
27.20
46.00
1,120.00
Subtotal $803.20
80.32
17.67
Total Cost $901.19
Please advise us in writing if you would like us to proceed with this change. Feel free to call me if you
have any questions or need additional information.
Sincerely,
Steve Lawrence
SL/cr
Accepted by
cc: Keith Woodley
Jim McNamara
ADROIT CONSTRUCTION COMPANY, INC.
P.O. Box 609, Ashland, Oregon 97520 • 541-482-4098 • Fax: 541-482-4218
OREGON NO. 44384, CALIFORNIA NO. 454960B